Gate House 1 - 6 Farringdon Street London EC4M 7LG Data via plota.co.uk

PA/26/01973 - Observations to Other Authorities Registered

Proposal

Observation Request by City of London for Change of use of part basement floor, part ground floor, and upper floors from offices (Class E) to visitor accommodation (Class C1), demolition of the 4th and 5th floors to allow the erection of a three-storey extension at roof level with rooftop terrace, alterations to existing facade and retail frontage, and other associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 17 Nov 2026
Decision
Expected by 8 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 12 Jan 2027 and 19 Jan 2027, from Tower Hamlets's recent changes of use.

Site constraints 12

Fleet Street conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: City of London AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 36 m away: Thames Tideway Tunnel
The site is about 36 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 342 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
Scheduled monument about 141 m away: Remains of Roman and medieval wall and gateway W of boundary of Stationers' Hall to Ludgate Hill
Its setting is a consideration for work nearby.
Nationally important archaeology protected by the Secretary of State. Work that affects the monument or its setting is rarely permitted.
Historic England ↗
Also on the record
15 listed buildings within 150 m of the postcode pin; Wider setting of protected view 5A.2 Greenwich Park Wolfe statue to St Paul's Cathedral; Inside the City and County of the City of London built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Town centre about 33 m away: Fleet Street; Designated open space about 38 m away.
Not affected
Outside flood zones 2 and 3 · Not green belt

Checked on 21 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Observations to Other Authorities
Postcode
EC4M 7LG
Received
around 17 Nov 2026
Validated
17 Nov 2026
Case officer
Show
Target decision
8 Dec 2026
Applicant
Show

Decision outlook

Day 6 of the 56-day target. Tower Hamlets usually decides changes of use by day 56.

Day 650 days to the 56-day target
53%decided within 8 weeks
59%approved
71decided in the last year

Plota live figures for changes of use decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Statutory expiry
8 Dec 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 overall
Relevant to this application:
Change of use

Tower Hamlets is slower than most councils at deciding householder applications: #207 of 296 on speed. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026