Calcutta House Old Castle Street London E1 7NT Data via plota.co.uk

25/01307/OBS - Observations from other Boroughs No Objections to OBS

Proposal

Consultation by the London Borough of Tower Hamlets for the request for an Environmental Impact Assessment (EIA) Scoping opinion under Regulation 15 of the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (as amended), in respect of the proposed part retention and extension, and part demolition and construction of a new mixed-use development. Within the northern portion of the Site, the Proposed Development will include an extension of two floors to the existing retained elements of the Calcutta House building, housing higher education uses (Use Class F1), resulting in overall eight levels (including ground level), and providing a total of circa 10,588m2 of educational space, as well as approximately 215m2 of retail (Use Class E) and 110m2 of community uses (Use Class F2), along with associated public realm, cycle parking spaces, refuse storage, plant and loading bay. Within the southern portion of the Site, the Proposed Development will include the construction of a new multi-level Purpose-Built Student Accommodation (Sui Generis) building and community facilities (Use Class F2) ranging from approximately 2 to 21 storeys in height (including ground level and excluding rooftop plant), with approximately 787 rooms, associated amenity and ancillary space (LBTH ref: ). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Sept 2025
✓
Consultation
30 Sept 2025
Decision
Target date was 13 Oct 2025

Under consideration

No decision has been issued yet. The council's target date, 13 Oct 2025, has passed.

The consultation period closed on 14 Oct 2025.

Site constraints 10

Archaeological priority area: Tower Hamlets APA 2.11
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 599 m away: Thames Tideway Tunnel
The site is about 599 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 446 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
3 listed buildings within 150 m of the postcode pin; Inside the Tower Hamlets built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Conservation area about 95 m away: Whitechapel High Street; Heritage at risk about 95 m away: Whitechapel High Street, Aldgate.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in City of London - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Observations from other Boroughs
Postcode
E1 7AA
Received
22 Sept 2025
Validated
22 Sept 2025
Ward
Portsoken
Case officer
Show
Target decision
13 Oct 2025
Decision level
Delegated Decision
Applicant
Show

Public comments

No public comments yet.

Last counted 17 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Consultation
30 Sept 2025
Comments by
14 Oct 2025
Committee
31 Oct 2025
Statutory expiry
13 Oct 2025
Env. assessment
No
City of London
Planning Authority Score
6.7/10
Good
#71 of 296 overall
Relevant to this application:
Householder decisions

City of London is one of the fastest councils in England for householder decisions: #1 of 296 on speed. The council extends the time limit on 84% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 100% approval rate vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
City of London decision statistics
Based on MHCLG data, the year to March 2026
97%
Overall approval rate
Above avg (87%) #3 of 296
100%
Householder approved
Above avg (90%) #1 of 296
100%
Decided in 8 weeks
Above avg (63%) #1 of 296
84%
Extended time limit
Above avg (41%) #296 of 296
50%
Minor dwellings approved
4 decided (1-9 homes)
91%
Change of use approved
22 decided
460
Total decisions
14 refused in the year to March 2026