33 Wentworth Street, London, E1 7TD Data via plota.co.uk

PA/26/01903/NC - Full Planning Permission Registered

Proposal

Installation of extraction system with external vent on side wall; renew surface finishing to solid wall areas of front & side elevations; and internal alterations to facilitate the use of the premises as a noodle bar (Use Class E(b)) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 11 Nov 2026
Decision
Expected by 6 Jan 2027

Under consideration

No decision has been issued yet. Plota predicts a decision between 6 Jan 2027 and 13 Jan 2027, from Tower Hamlets's recent changes of use.

Site constraints 11

Wentworth Street conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Heritage at risk: Wentworth Street, Bethnal Green
On the register of historic places assessed as at risk.
A designated building, monument, park or conservation area assessed as at risk from neglect, decay or development. Proposals that secure its future are looked on favourably.
Historic England ↗
Archaeological priority area: Tower Hamlets APA 2.12
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: Wentworth Street
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
National infrastructure project 756 m away: Thames Tideway Tunnel
The site is 756 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 342 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
4 listed buildings within 150 m; Inside the Tower Hamlets built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 17 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
E1 7TD
Received
around 11 Nov 2026
Validated
11 Nov 2026
Ward
Spitalfields and Banglatown
Case officer
Show
Target decision
6 Jan 2027
Decision level
Delegated
Applicant
Show
Agent
New Image Design

Decision outlook

Day 7 of the 56-day target. Tower Hamlets usually decides changes of use by day 56.

Day 749 days to the 56-day target
53%decided within 8 weeks
59%approved
71decided in the last year

Plota live figures for changes of use decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Site or press notice
26 Nov 2026
Statutory expiry
6 Jan 2027
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions