Description

Construction and operation of a Battery Energy Storage System (BESS) and associated infrastructure with fire water storage tank and pumphouse, landscaping, attenuation pond, CCTV cameras and fencing Data via plota.co.uk

Last checked

Planning committee

Decided by North Northamptonshire Planning Committee on 11 Mar 2026. The council has not yet issued its decision notice.

Approved by 10 votes to 1

As officers recommended.

  • Officers advised approval because energy-management benefits outweighed limited agricultural and landscape impacts, subject to conditions.
  • The parish council, residents and a ward councillor raised concerns about fire, contamination, ecology, agricultural land, flooding and cumulative impacts.
  • The committee voted 10 to 1 to grant permission, while noting continuing concerns about fire, traffic and contaminated runoff.
Read how the committee decided The proposed facility, site history, officer assessment, consultation responses, committee debate, vote and decision.

Source: Plota analysis of North Northamptonshire's committee minutes of 11 Mar 2026.

Site constraints 4

Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 3. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 140 m away: Green Hill Solar Farm
The site is 140 m from the project boundary. Generating station, awaiting the Secretary of State's decision. Also within 2 km: Weston Marsh to East Leicestershire (at pre-application, the site is inside its boundary).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
SSSI 250 m away: Upper Nene Valley Gravel Pits SSSI.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 1 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area339 m² (3,649 sq ft)
Energy ratingB (asset rating 49)
UseOffices and Workshop Businesses
HeatingAir Conditioning

From the energy performance certificate lodged in November 2023, the latest held for this property. The building may have changed since. View the certificate

Looking for land for battery storage?

Plota Sites searches every land parcel in England and Wales: 9,119 sites fit this search. On and off the market, free to search.

Land for battery storage
Work with planning data?

Every application in North Northamptonshire - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service
North Northamptonshire
Planning Authority Score
1.3/10
Poor
#285 of 296 councils
Relevant to this application:
Householder decisions

North Northamptonshire is one of the slowest councils in England for householder decisions, ranking #279 out of 296. The council extends the time limit on 64% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly less likely to be approved here (88%) than the national average (90%).

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
North Northamptonshire decision statistics
Based on MHCLG data, the year to March 2026
88%
Overall approval rate
Above avg (87%) #157 of 296
88%
Householder approved
Below avg (90%) #220 of 296
35%
Decided in 8 weeks
Below avg (63%) #279 of 296
64%
Extended time limit
Above avg (41%) #277 of 296
74%
Minor dwellings approved
100 decided (1-9 homes)
81%
Major dwellings approved
21 decided (10+ homes)
91%
Change of use approved
75 decided
1,096
Total decisions
132 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.