33 Canada Square, London E14 Data via plota.co.uk

PA/25/02251/NC - Full Planning Permission Approved

Proposal

Refurbishment of the existing facade, including re-finishing of the aluminium cladding elements, enhancements to the north entrance and introduction of a new south-west corner entrance, enhancements to street-level elevations including the addition of a living wall on part of the southern elevation, provision of new retail kiosks and flexible office/restaurant at ground and Levels 15-17, erection of a single-storey roof pavilion with terrace and plant, and associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 24 Dec 2025
✓
Consultation
3 Feb 2026
✓
Approved
27 Mar 2026

Approved on 27 Mar 2026 · Delegated · Last checked 8 Oct 2026

Documents 44

Plans & drawings 32

PDF DS006-TPB-DA-05-LXX-DR-04221 EXISTING TYPICAL GENERAL ARRANGEMENT ELEVATION - NORTH Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04222 EXISTING TYPICAL GENERAL ARRANGEMENT ELEVATION - SOUTH Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04224 EXISTING TYPICAL GENERAL ARRANGEMENT ELEVATION - WEST Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04331 EXISTING TYPICAL GENERAL ARRANGEMENT SECTION A-A Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04332 EXISTING TYPICAL GENERAL ARRANGEMENT SECTION B-B Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-MZ1-DR-04102 EXISTING UPPER GROUND LEVEL GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF LOCATION PLAN OS Extract · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L00-DR-04211 PROPOSED LEVEL 00 GENERAL ARRANGEMENT ELEVATION - NORTH Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L00-DR-04212 PROPOSED LEVEL 00 GENERAL ARRANGEMENT ELEVATION - SOUTH Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L00-DR-04101 PROPOSED LEVEL 00 GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L15-DR-04101 PROPOSED LEVEL 15 GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L16-DR-04101 PROPOSED LEVEL 16 GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L17-DR-04201 PROPOSED LEVEL 17 GENERAL ARRANGEMENT ENLARGED ELEVATIONS Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L17-DR-04202 PROPOSED LEVEL 17 GENERAL ARRANGEMENT ENLARGED ELEVATIONS 2 Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L18-DR-04101 PROPOSED LEVEL 18 GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-PL1-DR-04101 PROPOSED LOWER GROUND GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-ROF-DR-04101 PROPOSED ROOF LEVEL GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L00-DR-04110 PROPOSED SITE PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04203 PROPOSED TYPICAL GENERAL ARRANGEMENT ELEVATION - EAST Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04201 PROPOSED TYPICAL GENERAL ARRANGEMENT ELEVATION - NORTH Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04202 PROPOSED TYPICAL GENERAL ARRANGEMENT ELEVATION - SOUTH Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04204 PROPOSED TYPICAL GENERAL ARRANGEMENT ELEVATION - WEST Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04302 PROPOSED TYPICAL GENERAL ARRANGEMENT SECTION A-A Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04301 PROPOSED TYPICAL GENERAL ARRANGEMENT SECTION B-B Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-MZ1-DR-04101 PROPOSED UPPER GROUND LEVEL GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS6001-TPB-DA-05-L00-DR-04102 EXISTING GROUND LEVEL GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS6001-TPB-DA-05-L15-DR-04102 EXISTING LEVEL 15 GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS6001-TPB-DA-05-L16-DR-04102 EXISTING LEVEL 16 GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-L17-DR-04102 EXISTING LEVEL 17 GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-PL1-DR-04102 EXISTING LOWER GROUND GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-ROF-DR-04102 EXISTING ROOF LEVEL GENERAL ARRANGEMENT PLAN Current Plan · 24 Dec 2025 View ↗ PDF DS006-TPB-DA-05-LXX-DR-04102 EXISTING SITE PLAN Current Plan · 24 Dec 2025 View ↗

All documents on the council site ↗

Associated applications 2

Site constraints 11

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Article 4 direction
Canary Wharf. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area: Tower Hamlets APA 3.1
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: Canary Wharf
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
National infrastructure project 430 m away: Thames Tideway Tunnel
The site is 430 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: Silvertown Tunnel (decided, 1462 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
1 listed building within 150 m
Nearest: Quay Walls,copings and Butresses to Import Dock and Export Dock, Grade I, 23 m away
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Historic England ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Inside the Tower Hamlets built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Designated open space 43 m away.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Received
around 24 Dec 2025
Validated
24 Dec 2025
Ward
Canary Wharf
Case officer
Show
Target decision
27 Mar 2026
Decision
Permit
Decision date
27 Mar 2026
Decision level
Delegated
Applicant
Show
Agent
Savills

How this decision compares

Decided in 93 days from validation, 37 days slower than Tower Hamlets's median of 56 for full applications. Approved, as 85% of full applications here are.

60%decided within 8 weeks
85%approved
557decided in the last year

Plota live figures for full applications decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Comments by
27 Feb 2026
Site or press notice
3 Feb 2026
Statutory expiry
18 Feb 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions