Holiday Inn Express London City, 275 Old Street, Hackney, London, EC1V 9LN Data via plota.co.uk

2025/0112 - Full Planning Permission Approved

Proposal

Redevelopment to provide a part-1, part-2, part-3 storey extension comprising additional hotel bedrooms (Use Class C1), refurbishment of the building including alterations to external elevations and reconfiguration of the ground floor and introduction of a cafe (Use Class E) with associated cycle parking and landscaping. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Jan 2025
✓
Validated
11 Feb 2025
✓
Approved
24 Nov 2025
✓
Appeal allowed
24 Nov 2025

Approved on 24 Nov 2025 · Delegated · Last checked 1 Oct 2026

Documents 36

All documents on the council site ↗

Licence at this address

  • Licence Holiday Inn Premises licence · in force since 24 Nov 2005 Licensed hours: alcohol until midnight (Sun 23:30)

Licensed hours are what the licence permits, not opening times.

Site constraints 10

3 Article 4 directions
Whole of the London Borough of Hackney · Tech City (CAZ North) · Exemption Area (part 1). Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area: Hackney APA 2.11 Shoreditch
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Hackney AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
14 listed buildings within 150 m
Nearest: 8 and 10, Pitfield Street N1, Grade II, 37 m away · 1 Grade II*, 13 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 14 with distances
Historic England ↗
Conservation area 15 m away: South Shoreditch
The edge of the area; work outside it can still affect its setting.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
National infrastructure project 1.9 km away: Thames Tideway Tunnel; Inside the Hackney built-up area; Public transport access: PTAL 6a (excellent), TfL 2023, for the 100 m square; Town centre 10 m away: Shoreditch.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Hackney - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Hackney
Application type
Full Planning Permission
Postcode
EC1V 9LN
Received
22 Jan 2025
Validated
11 Feb 2025
Ward
Hoxton East and Shoreditch Ward
Case officer
Show
Target decision
13 Jun 2025
Decision
Allowed at Appeal
Decision date
24 Nov 2025
Decision level
Delegated
Appeal
Allowed · 24 Nov 2025 · Written Representations · Inspectorate case 3368258 ↗

How this decision compares

Decided in 286 days from validation, 199 days slower than Hackney's median of 87 for commercial and major works. Approved, as 78% of commercial and major works here are.

18%decided within 8 weeks
78%approved
8%go to committee

Plota live figures for commercial and major works decided by Hackney in the last twelve months, from validation. Hackney decision record →

Consultation & key dates

Statutory expiry
13 Jun 2025
Hackney
Planning Authority Score
2.4/10
Poor
#256 of 296 overall
Relevant to this application:
Householder decisions

Hackney is slower than most councils at deciding householder applications: #220 of 296 on speed. Hackney is also one of the strictest councils - it refuses more householder applications than almost any other, with only 84% approved vs 90% nationally.

One of the strictest councils
only 84% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Hackney decision statistics
Based on MHCLG data, the year to March 2026
82%
Overall approval rate
Below avg (87%) #248 of 296
84%
Householder approved
Below avg (90%) #257 of 296
53%
Decided in 8 weeks
Below avg (63%) #220 of 296
46%
Extended time limit
Above avg (41%) #201 of 296
75%
Minor dwellings approved
204 decided (1-9 homes)
100%
Major dwellings approved
4 decided (10+ homes)
50%
Change of use approved
2 decided
1,323
Total decisions
241 refused in the year to March 2026