Land South Of Sutton Stop, Coventry, CV6 6DF Data via plota.co.uk

PL/2024/0001542/RESM - RESM Application for approval of reserved matters following outline approval (major) Approved

Proposal

Submission of reserved matters under condition No.1, details of appearance, landscaping, layout and scale of 262no dwellings pursuant to outline planning permission granted on 03/03/2023 under appeal ref. APP/ for the erection of up to 262 dwellings, including the demolition of 294 and 296 Grange Road to provide new vehicular access, new public open space, drainage, landscaping, car parking areas and other works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
13 Aug 2024
✓
Approved
7 Oct 2025

Approved on 7 Oct 2025 · Delegated decision · Last checked 30 Sept 2026

Documents 284

Statements & assessments 90

PDF AMENDED REPORT - Arboricultural Impact Assessment, dated July 2024 - Report Ref.24-050.DR.AIA001 (P06) Tree survey/arboricultural implications · 30 Sept 2025 View ↗ PDF AMENDED REPORT - Arboricultural Method Statement, dated July 2024 - Report Ref.24-050.DR.AMS001 (P04) Tree survey/arboricultural implications · 30 Sept 2025 View ↗ PDF AMENDED DRAWING - Tree Protection Plan (3 of 4) - Drawing No.BEA-24-050-11 Rev P09 Tree survey/arboricultural implications · 30 Sept 2025 View ↗ PDF AMENDED DRAWING - Tree Protection Plan (2 of 4) - Drawing No.BEA-24-050-10 Rev P09 Tree survey/arboricultural implications · 30 Sept 2025 View ↗ PDF AMENDED DRAWING - Tree Protection Plan (1 of 4) - Drawing No.BEA-24-050-09 Rev P09 Tree survey/arboricultural implications · 30 Sept 2025 View ↗ PDF AMENDED DRAWING - Tree Protection Plan (4 of 4) - Drawing No.BEA-24-050-12 Rev P09 Tree survey/arboricultural implications · 30 Sept 2025 View ↗ PDF SUPERSEDED REPORT - Arboricultural Method Statement, dated July 2024 - Report Ref.24-050.DR.AMS001 (P03) Tree survey/arboricultural implications · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (4 of 4) - Drawing No.BEA-24-050-12 Rev P08 Tree survey/arboricultural implications · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (3 of 4) - Drawing No.BEA-24-050-11 Rev P08 Tree survey/arboricultural implications · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (2 of 4) - Drawing No.BEA-24-050-10 Rev P08 Tree survey/arboricultural implications · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (1 of 4) - Drawing No.BEA-24-050-09 Rev P08 Tree survey/arboricultural implications · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Tree Retention & Removal Plan - Drawing No.BEA-24-050-08 Rev P08 Tree survey/arboricultural implications · 18 Sept 2025 View ↗ PDF SUPERSEDED REPORT - Arboricultural Impact Assessment, dated July 2024 - Report Ref.24-050.DR.AIA001 (P05) Tree survey/arboricultural implications · 18 Sept 2025 View ↗ PDF EXCEL SPREADSHEET - Storm Network 2 Pipeline Schedule, as submitted 8th August 2025 Drainage · 12 Aug 2025 View ↗ PDF EXCEL SPREADSHEET - Storm Network 1 Pipeline Schedule, as submitted 8th August 2025 Drainage · 12 Aug 2025 View ↗ PDF EXCEL SPREADSHEET - Foul Network 3 Pipeline Schedule, as submitted 8th August 2025 Drainage · 12 Aug 2025 View ↗ PDF EXCEL SPREADSHEET - Foul Network 2 Pipeline Schedule, as submitted 8th August 2025 Drainage · 12 Aug 2025 View ↗ PDF EXCEL SPREADSHEET - Foul Network 1 Pipeline Schedule, as submitted 8th August 2025 Drainage · 12 Aug 2025 View ↗ PDF SUPERSEDED REPORT - Design and Access Statement - Design Response Statement, dated July 2025 Design and access statement · 12 Aug 2025 View ↗ PDF AMENDED REPORT - Storm Network 2, FSR Hydraulic Calculations, dated 1st August 2025 - Report Ref.NETWORK2.PFD Drainage · 12 Aug 2025 View ↗ PDF AMENDED REPORT - Storm Network 2, FEH22 Hydraulic Calculations, dated 1st August 2025 - Report Ref.NETWORK2.PFD Drainage · 12 Aug 2025 View ↗ PDF AMENDED REPORT - Storm Network 1, FSR Hydraulic Calculations, dated 1st August 2025 - Report Ref.NETWORK1.PFD Drainage · 12 Aug 2025 View ↗ PDF AMENDED REPORT - Storm Network 1, FEH 22 Hydraulic Calculations, dated 1st August 2025 - Report Ref.NETWORK1.PFD Drainage · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Proposed Contour Layout - Drawing No.0460-106 Rev G Drainage · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Flood Routing Layout - Drawing No.0460-105 Rev F Drainage · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Drainage Area Layout - Drawing No.0460-104 Rev F Drainage · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Drainage and Levels Appraisal Layout - Drawing No.0460-4 Rev K Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (4 of 4) - Drawing No.BEA-24-050-12 Rev P05 Tree survey/arboricultural implications · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (3 of 4) - Drawing No.BEA-24-050-11 Rev P05 Tree survey/arboricultural implications · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (2 of 4) - Drawing No.BEA-24-050-10 Rev P05 Tree survey/arboricultural implications · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (1 of 4) - Drawing No.BEA-24-050-09 Rev P05 Tree survey/arboricultural implications · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Retention & Removal Plan - Drawing No.BEA-24-050-08 Rev P05 Tree survey/arboricultural implications · 12 Aug 2025 View ↗ PDF AMENDED REPORT - Landscape and Ecological Management Plan (LEMP), dated August 2025 Biodiversity/Ecology survey and report · 12 Aug 2025 View ↗ PDF AMENDED REPORT - Ventilation Strategy, as submitted 16th April 2025 Ventilation/extraction statement · 17 Apr 2025 View ↗ PDF SUPERSEDED EXCEL SPREADSHEET - Storm Network 2 Pipeline Schedule, as submitted April 2025 Drainage · 17 Apr 2025 View ↗ PDF SUPERSEDED EXCEL SPREADSHEET - Foul Network 1 Pipeline Schedule, as submitted April 2025 Drainage · 17 Apr 2025 View ↗ PDF SUPERSEDED EXCEL SPREADSHEET - Foul Network 2 Pipeline Schedule, as submitted April 2025 Drainage · 17 Apr 2025 View ↗ PDF SUPERSEDED EXCEL SPREADSHEET - Foul Network 1 Pipeline Schedule, as submitted April 2025 Drainage · 17 Apr 2025 View ↗ PDF SUPERSEDED REPORT - Design and Access Statement - Design Response Statement, dated April 2025 (remainder) Design and access statement · 17 Apr 2025 View ↗ PDF SUPERSEDED REPORT - Design and Access Statement - Design Response Statement, dated April 2025 (Pages 1 - 20) Design and access statement · 17 Apr 2025 View ↗ PDF AMENDED REPORT - Hydraulic Calculations - Storm Network 1 - 1, 30, 100YR + 40%, 15th April 2025 - Report Ref.NETWORK1.PFD Drainage · 17 Apr 2025 View ↗ PDF AMENDED REPORT - Noise Impact Assessment, dated 3rd April 2025 - Report Ref.2062746-RSKA-RP-001 Rev P01 Noise impact assessment · 17 Apr 2025 View ↗ PDF SUPERSEDED REPORT - Landscape and Ecological Management Plan (LEMP), dated April 2025 Biodiversity/Ecology survey and report · 17 Apr 2025 View ↗ PDF AMENDED DRAWING - Tree Pit for Medium Tree Species in Car Park Rootspace 600 - Drawing No.GBU-STANDARD-3208 Rev A Tree survey/arboricultural implications · 17 Apr 2025 View ↗ PDF SUPERSEDED REPORT - Construction Management Plan, dated 11th July 2024 - Report Ref. Rev A Transport assessment · 17 Apr 2025 View ↗ PDF SUPERSEDED REPORT - Arboricultural Method Statement, dated July 2024 - Report Ref.24-050.DR.AMS001 (P02) Tree survey/arboricultural implications · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (4 of 4) - Drawing No.BEA-24-050-12 Rev P03 Tree survey/arboricultural implications · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (3 of 4) - Drawing No.BEA-24-050-11 Rev P03 Tree survey/arboricultural implications · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (2 of 4) - Drawing No.BEA-24-050-10 Rev P03 Tree survey/arboricultural implications · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (1 of 4) - Drawing No.BEA-24-050-09 Rev P03 Tree survey/arboricultural implications · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Tree Retention & Removal Plan - Drawing No.BEA-24-050-08 Rev P03 Tree survey/arboricultural implications · 17 Apr 2025 View ↗ PDF SUPERSEDED REPORT - Arboricultural Impact Assessment, dated July 2024 - Report Ref.24-050.DR.AIA001 (P03) Tree survey/arboricultural implications · 17 Apr 2025 View ↗ PDF SUPERSEDED REPORT - Affordable Housing Statement, dated 16th April 2025 - Report Ref.P8125 Affordable housing statement · 17 Apr 2025 View ↗ PDF AMENDED REPORT - Construction Environmental Management Plan (CEMP), dated April 2025 Biodiversity/Ecology survey and report · 17 Apr 2025 View ↗ PDF AMENDED REPORT - BIA Report, dated 16th April 2025 Final Rev A Biodiversity/Ecology survey and report · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Flood Routing Layout - Drawing No.0460-105 Rev D Drainage · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Drainage Area Layout - Drawing No.0460-104 Rev D Drainage · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Drainage and Levels Appraisal Layout - Drawing No.0460-4 Rev G Drainage · 17 Apr 2025 View ↗ PDF SUPERSEDED REPORT - Storm Network 2, 100YR + 40%, dated 22nd November 2024 - Report Ref.NETWORK2.PFD Drainage · 3 Dec 2024 View ↗ PDF AMENDED REPORT - Flood Risk Assessment, dated May 2024 - Report Ref.13669-R100 Issue 1 Drainage · 3 Dec 2024 View ↗ PDF EXCEL WORKSHEETS - Biodiversity Metric as submitted 22.10.24 Biodiversity impact assessment · 24 Oct 2024 View ↗ PDF SUPERSEDED REPORT - Landscape and Ecological Management Plan, dated 26th September 2024 FINAL Landscaping plan/details · 24 Oct 2024 View ↗ PDF REPORT - Stage 1 Road Safety Audit Response Report, dated 21.08.24 Transport assessment · 28 Aug 2024 View ↗ PDF REPORT - Road Safety Audit Stage 1, dated 2nd July 2024 - Report Ref.18569 Rev 0 Transport assessment · 28 Aug 2024 View ↗ PDF EXCEL SPREADSHEET - Storm Network 2 Pipeline Schedule Drainage · 28 Aug 2024 View ↗ PDF EXCEL SPREADSHEET - Storm Network 1 Pipeline Schedule Drainage · 28 Aug 2024 View ↗ PDF EXCEL SPREADSHEET - Foul Network 2 Pipeline Schedule Drainage · 28 Aug 2024 View ↗ PDF EXCEL SPREADSHEET - Foul Network 1 Pipeline Schedule Drainage · 28 Aug 2024 View ↗ PDF SUPERSEDED REPORT - Landscape and Ecological Management Plan, dated 7th August 2024 Draft Landscaping plan/details · 20 Aug 2024 View ↗ PDF SUPERSEDED REPORT - BIA Report, dated 9th August 2024 Final Biodiversity impact assessment · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 - Drainage Plan - Drawing No.LRC-LE-GEN-XX-DR-CE-108 S1 Rev P7 Detail drawing · 20 Aug 2024 View ↗ PDF REPORT - Design Response Statement, dated July 2024 Design and access statement · 14 Aug 2024 View ↗
PDF Commenter’s name hidden Show Statement of community involvement · 14 Aug 2024 View ↗
PDF SUPERSEDED REPORT - Affordable Housing Statement, dated 31st July 2024 - Report Ref.P8125 Affordable housing statement · 14 Aug 2024 View ↗ PDF REPORT - Supporting Planning Statement, dated 9th August 2024 - Report Ref.P8125 Planning statement · 14 Aug 2024 View ↗ PDF DRAWING - Topographical Survey - Drawing No.1215/2503/1 Rev A Topographical plan · 14 Aug 2024 View ↗ PDF REPORT - Storm Network 2 - Design Settings - 2 in 100, dated 02.08.2024 - Report Ref.NETWORK2.PFD Drainage · 14 Aug 2024 View ↗ PDF REPORT - Storm Network 2 - Design Settings - 2 in 30, dated 02.08.2024 - Report Ref.NETWORK2.PFD Drainage · 14 Aug 2024 View ↗ PDF REPORT - Storm Network 1 - Design Settings - 1 in 100, dated 02.08.2024 - Report Ref.NETWORK1.PFD Drainage · 14 Aug 2024 View ↗ PDF REPORT - Storm Network 1 - Design Settings - 1 in 30, dated 02.08.2024 - Report Ref.NETWORK1.PFD Drainage · 14 Aug 2024 View ↗ PDF REPORT - Flood Assessment, dated 20th May 2024 - Report Ref. 13669-R100 Issue 1 Flood risk assessment · 14 Aug 2024 View ↗ PDF SUPERSEDED REPORT - Arboricultural Method Statement, dated July 2024 - Report Ref.24-050.DR.AMS001 (P01) Tree survey/arboricultural implications · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 - Drainage Plan - Drawing No.LRC-LE-GEN-XX-DR-CE-108 S1 Rev P5 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (4 of 4) - Drawing No.BEA-24-050-12 Rev P02 Tree survey/arboricultural implications · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (3 of 4) - Drawing No.BEA-24-050-11 Rev P02 Tree survey/arboricultural implications · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (2 of 4) - Drawing No.BEA-24-050-10 Rev P02 Tree survey/arboricultural implications · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Tree Protection Plan (1 of 4) - Drawing No.BEA-24-050-09 Rev P02 Tree survey/arboricultural implications · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Tree Retention & Removal Plan - Drawing No.BEA-24-050-08 Rev P02 Tree survey/arboricultural implications · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Drainage and Levels Appraisal Layout - Drawing No.0460-4 Rev C Drainage · 14 Aug 2024 View ↗ PDF SUPERSEDED REPORT - Arboricultural Impact Assessment, dated July 2024 - Report Ref.24-050.DR.AIA001 (P02) Tree survey/arboricultural implications · 14 Aug 2024 View ↗

Plans & drawings 178

PDF AMENDED DRAWING - Management Company Plan - Drawing No.SBA109-11 Rev C Detail drawing · 2 Oct 2025 View ↗ PDF AMENDED DRAWING - Build Route - Phasing Plan - Drawing No.Sutton-Build-Route-Phasing-Plan Rev G Detail drawing · 30 Sept 2025 View ↗ PDF Final Drawing Submission List - 30.09.25 Supporting information · 30 Sept 2025 View ↗ PDF AMENDED DRAWING - Section 38 Layout - Overview - Drawing No.0460-103 Rev H Detail drawing · 30 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Build Route - Phasing Plan - Drawing No.SUTTON-BUILD ROUTE_PHASING PLAN Rev F Detail drawing · 30 Sept 2025 View ↗ PDF Drawing Submission List - 26.09.25 Supporting information · 30 Sept 2025 View ↗ PDF AMENDED REPORT - Construction Management Plan, dated 16th September 2025 - Report Rev B Supporting information · 23 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Build Route - Phasing Plan - Drawing No.Sutton-Build-Route-Phasing-Plan Rev E Detail drawing · 23 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Section 38 Layout - Overview - Drawing No.0460-103 Rev F - need changes to adopted routes Detail drawing · 23 Sept 2025 View ↗ PDF Updated drawing list as submitted 19th September 2025 Supporting information · 23 Sept 2025 View ↗ PDF AMENDED DRAWING - Detailed Soft Landscape Proposals (6 of 6) - Drawing No.BEA-24-050-20 Rev P07 Landscaping plan/details · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Detailed Soft Landscape Proposals (5 of 6) - Drawing No.BEA-24-050-19 Rev P07 Landscaping plan/details · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Detailed Soft Landscape Proposals (4 of 6) - Drawing No.BEA-24-050-18 Rev P07 Landscaping plan/details · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Detailed Soft Landscape Proposals (3 of 6) - Drawing No.BEA-24-050-17 Rev P07 Landscaping plan/details · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Detailed Soft Landscape Proposals (2 of 6) - Drawing No.BEA-24-050-16 Rev P07 Landscaping plan/details · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Detailed Soft Landscape Proposals (1 of 6) - Drawing No.BEA-24-050-15 Rev P07 Landscaping plan/details · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Section 38 Layout - Phase 3 - Drawing No.0460-108 Rev B Detail drawing · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Section 38 Layout - Phase 2 - Drawing No.0460-108 Rev B Detail drawing · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Section 38 Layout - Phase 1 - Drawing No.0460-107 Rev B Detail drawing · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Section 38 Layout - Overview - Drawing No.0460-103 Rev E Detail drawing · 18 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Management Company Plan - Drawing No.SBA109-11 Rev B Detail drawing · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Presentation Layout - Drawing No.JIG047-050 Rev H Layout plans · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Public Open Space Areas - Drawing No.JIG047-015 Rev F Detail drawing · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Parking Dispersion Layout - Drawing No.JIG047-014 Rev E Detail drawing · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Tenure Dispersion Layout - Drawing No.JIG047-013 Rev E Detail drawing · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Materials & Enclosures Layout - Drawing No.JIG047-012 Rev E Detail drawing · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - Planning Layout - Drawing No.JIG047-011 Rev M Layout plans · 18 Sept 2025 View ↗ PDF AMENDED DRAWING - PROW Plan - Proposed - Drawing No.PROW-002 Rev C Detail drawing · 10 Sept 2025 View ↗ PDF AMENDED DRAWING - PROW Plan - Existing - Drawing No.PROW-001 Rev C Detail drawing · 10 Sept 2025 View ↗ PDF AMENDED DRAWING - Streetscenes Sheet 1 - Drawing No.JIG047-300 Rev C Street scene/context plans · 10 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Presentation Layout - Drawing No.JIG047-050 Rev G Layout plans · 10 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Public Open Space Areas - Drawing No.JIG047-015 Rev E Detail drawing · 10 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Parking Dispersion Layout - Drawing No.JIG047-014 Rev D Detail drawing · 10 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Tenure Dispersion Layout - Drawing No.JIG047-013 Rev D Detail drawing · 10 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Materials & Enclosures Layout - Drawing No.JIG047-012 Rev D Detail drawing · 10 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Planning Layout - Drawing No.JIG047-011 Rev L Layout plans · 10 Sept 2025 View ↗ PDF SUPERSEDED DRAWING - Section 38 Layout - Overview - Drawing No.0460-103 Rev D Detail drawing · 15 Aug 2025 View ↗ PDF AMENDED DRAWING - Kerbing and Surface Finishes Layout - Drawing No.0460-101 Rev M Detail drawing · 15 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Kerbing and Surface Finishes Layout - Drawing No.0460-101 Rev L Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Temporary Construction Access Tracking - Sheet 1 - Drawing No.0460-14 Rev A Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Pond Cross Section Detail - Drawing No.0460-11 Rev H Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Adoptable Highway Area Layout - Drawing No.0460-10 Rev J Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Appraisal Site Cross Sections Sheet 2 - Drawing No.0460- 9 Rev B Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Appraisal Site Cross Sections Sheet 1 - Drawing No.0460-8 Rev B Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Appraisal Site Cross Sections Layout - Drawing No.0460-7 Rev C Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Pedestrian Visibility Splays Layout - Drawing No.0460-6 Rev J Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - MPV Tracking Layout - Drawing No.0460-3 Rev M Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Fire Appliance Tracking Layout - Drawing No.0460-2 Rev M Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Refuse Vehicle Tracking Layout - Drawing No.0460-1 Rev N Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED REPORT - Schedule of Updated Drawings and Documents, dated 6th August 2025 Amended Report · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Sutton Edge Character Area - House Types, as submitted 8th August 2025 Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (6 of 6) - Drawing No.BEA-24-050-20 Rev P04 Landscaping plan/details · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (5 of 6) - Drawing No.BEA-24-050-19 Rev P04 Landscaping plan/details · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (4 of 6) - Drawing No.BEA-24-050-18 Rev P04 Landscaping plan/details · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (3 of 6) - Drawing No.BEA-24-050-17 Rev P04 Landscaping plan/details · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (2 of 6) - Drawing No.BEA-24-050-16 Rev P04 Landscaping plan/details · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (1 of 6) - Drawing No.BEA-24-050-15 Rev P04 Landscaping plan/details · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Housetype Pack, dated August 2025 INC Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Build Route - Phasing Plan - Drawing No.Sutton-Build-Route-Phasing-Plan Rev C Detail drawing · 12 Aug 2025 View ↗ PDF AMENDED DRAWING - Streetscenes Sheet 2 - Drawing No.JIG047-301 Rev C Street scene/context plans · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Streetscenes Sheet 1 - Drawing No.JIG047-300 Rev B Street scene/context plans · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Presentation Layout - Drawing No.JIG047-050 Rev F Layout plans · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Public Open Space Areas - Drawing No.JIG047-015 Rev D Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Parking Dispersion Layout - Drawing No.JIG047-014 Rev C Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Tenure Dispersion Layout - Drawing No.JIG047-013 Rev C Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Materials & Enclosures Layout - Drawing No.JIG047-012 Rev C Detail drawing · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Planning Layout - Drawing No.JIG047-011 Rev K Layout plans · 12 Aug 2025 View ↗ PDF SUPERSEDED DRAWING - Build Route - Phasing Plan - Drawing No.Sutton-Build-Route-Phasing-Plan Rev B Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Managed Area Plan - Drawing No.SUTTON-MCP-001 Rev A Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - PROW Plan - Proposed - Drawing No.PROW-002 Rev A Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - PROW Plan - Existing - Drawing No.PROW-001 Rev* - SAME REF AS ORIGINAL SUBMISSION Existing Plans · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Streetscenes Sheet 2 - Drawing No.JIG047-301 Rev A Street scene/context plans · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Streetscenes Sheet 1 - Drawing No.JIG047-300 Rev A Street scene/context plans · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Presentation Layout - Drawing No.JIG047-050 Rev E Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Public Open Space Areas - Drawing No.JIG047-015 Rev C Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Parking Dispersion Layout - Drawing No.JIG047-014 Rev B Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Tenure Dispersion Layout - Drawing No.JIG047-013 Rev B Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Materials & Enclosures Layout - Drawing No.JIG047-012 Rev B Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Planning Layout - Drawing No.JIG047-011 Rev G Layout plans · 17 Apr 2025 View ↗ PDF SUPERSEDED Housetype Portfolio Part 4 Additional plans · 17 Apr 2025 View ↗ PDF SUPERSEDED Housetype Portfolio Part 3 Additional plans · 17 Apr 2025 View ↗ PDF SUPERSEDED Housetype Portfolio Part 2 Additional plans · 17 Apr 2025 View ↗ PDF SUPERSEDED Housetype Portfolio Part 1 Additional plans · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (6 of 6) - Drawing No.BEA-24-050-20 Rev P01 Landscaping plan/details · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (5 of 6) - Drawing No.BEA-24-050-19 Rev P01 Landscaping plan/details · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (4 of 6) - Drawing No.BEA-24-050-18 Rev P01 Landscaping plan/details · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (3 of 6) - Drawing No.BEA-24-050-17 Rev P01 Landscaping plan/details · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (2 of 6) - Drawing No.BEA-24-050-16 Rev P01 Landscaping plan/details · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Proposals (1 of 6) - Drawing No.BEA-24-050-15 Rev P01 Landscaping plan/details · 17 Apr 2025 View ↗ PDF AMENDED REPORT - Long Term Landscape Management Plan, dated 11th April 2025 - Report Ref.24050/DP/LMP001 Landscaping plan/details · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Proposed Contour Layout - Drawing No.0460-106 Rev E Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Kerbing and Surface Finishes Layout - Drawing No.0460-101 Rev H Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Pond Cross Section Detail - Drawing No.0460-11 Rev G Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Adoptable Highway Area Layout - Drawing No.0460-10 Rev G Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Appraisal Site Cross Sections Sheet 2 - Drawing No.0460- 9 Rev A Section plans · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Appraisal Site Cross Sections Sheet 1 - Drawing No.0460-8 Rev A Section plans · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Appraisal Site Cross Sections Layout - Drawing No.0460-7 Rev A Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Pedestrian Visibility Splays Layout - Drawing No.0460-6 Rev G Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - MPV Tracking Layout - Drawing No.0460-3 Rev J Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Fire Appliance Tracking Layout - Drawing No.0460-2 Rev J Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Refuse Vehicle Tracking Layout - Drawing No.0460-1 Rev J Detail drawing · 17 Apr 2025 View ↗ PDF SUPERSEDED DRAWING - Sutton Edge Frontage - Drawing No.JIG047 - TEMP Detail drawing · 4 Mar 2025 View ↗ PDF SUPERSEDED DRAWING - EMAP11 & EMAP12 Traditional Brick Planning Drawing - Drawing No.JIG047-201 Rev A Detail drawing · 4 Mar 2025 View ↗ PDF SUPERSEDED DRAWING - Adoptable Street Tree Distribution - Drawing No.JIG047-018 Detail drawing · 4 Mar 2025 View ↗ PDF SUPERSEDED DRAWING - GF Apartment Amenity - Drawing No.JIG047- Detail drawing · 4 Mar 2025 View ↗ PDF SUPERSEDED DRAWING - Planning Layout - Drawing No.JIG047-011 Rev B Layout plans · 31 Jan 2025 View ↗ PDF SUPERSEDED DRAWING - Planning Layout - Drawing No.JIG047-011 Rev A Layout plans · 2 Dec 2024 View ↗ PDF AMENDED DRAWING - Formal POS Sketches, as submitted 29th November 2024 Detail drawing · 2 Dec 2024 View ↗ PDF SUPERSEDED DRAWING - Public Open Space Areas - Drawing No.JIG047-015 Rev A Detail drawing · 2 Dec 2024 View ↗ PDF Road Safety Audit Stage 1 dated 25th October 2024 Additional plans · 28 Oct 2024 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Strategy - Drawing No.BEA-24-050-013 Rev P05 Landscaping plan/details · 24 Oct 2024 View ↗ PDF Drawing Submission list, dated 13th August 2024 Supporting information · 28 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 Construction Details - Drawing No.LRC-LE-GEN-XX-DR-CE-111 S1 Rev P2 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 Road Markings - Drawing No.LRC-LE-GEN-XX-DR-CE-110 S1 Rev P7 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - Existing Utilities Cross Section - Drawing No.LRC-LE-GEN-XX-DR-CE-109 S1 Rev P6 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 - Proposed Levels - Drawing No.LRC-LE-GEN-XX-DR-CE-600 S1 Rev P7 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 - Kerbing Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-106 S1 Rev P7 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 - Construction Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-105 S1 Rev P7 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 Site Clearance - Drawing No.LRC-LE-GEN-XX-DR-CE-104 S1 Rev P7 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 Swept Path Analysis - Drawing No.LRC-LE-GEN-XX-DR-CE-103 S1 Rev P7 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-102 S1 Rev P6 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 Geometry Alignment - Drawing No.LRC-LE-GEN-XX-DR-CE-101 S1 Rev P6 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 General Arrangement - Drawing No.LRC-LE-GEN-XX-DR-CE-100 S1 Rev P7 Detail drawing · 20 Aug 2024 View ↗ PDF AMENDED DRAWING - S278 Location Plan - Drawing No.LRC-LE-GEN-XX-DR-CE-001 S1 Rev P2 Location plan · 20 Aug 2024 View ↗ PDF SUPERSEDED Housetype pack Proposed Plans · 14 Aug 2024 View ↗ PDF REPORT - Ventilation Strategy, as submitted 13th August 2024 - contains drawing - DRAWING - Purge Ventilation - Drawing No.EM-ME21-11-24 Rev A Supporting information · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 Road Markings - Drawing No.LRC-LE-GEN-XX-DR-CE-110 S1 Rev P5 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - PROW Plan - Proposed - Drawing No.PROW-002 Rev* Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Phasing Plan - Drawing No.SUTTON-PP-001 Rev* Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Managed Area Plan - Drawing No.SUTTON-MCP-001 Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Location Plan - Drawing No.LOC-001 Rev* Location plan · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Streetscenes Sheet 2 - Drawing No.JIG047-301 Rev - Street scene/context plans · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Streetscenes Sheet 1 - Drawing No.JIG047-300 Rev - Street scene/context plans · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 Construction Details - Drawing No.LRC-LE-GEN-XX-DR-CE-111 S1 Rev P1 Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - PROW Plan - Existing - Drawing No.PROW-001 Rev* Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Construction Management Plan (CMP) and Construction Environmental Management Plan (CEMP) - Drawing No.SUTTON-CEMP-001 Rev* Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road Construction Details - Drawing No.LRC-LE-GEN-XX-DR-CE-208 S4 Rev A Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road Proposed Road Markings Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-207 S4 Rev A Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road Proposed Kerbing Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-206 S4 Rev B Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road Proposed Construction Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-205 S4 Rev B Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road Site Clearance - Drawing No.LRC-LE-GEN-XX-DR-CE-204 S4 Rev B Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road Vehicle Tracking - Drawing No.LRC-LE-GEN-XX-DR-CE-203 S4 Rev A Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road S278 Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-202 S4 Rev A Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road Geometry Alignment - Drawing No.LRC-LE-GEN-XX-DR-CE-201 S4 Rev A Detail drawing · 14 Aug 2024 View ↗ PDF DRAWING - Longford Road Proposed General Arrangement - Drawing No.LRC-LE-GEN-XX-DR-CE-200 S4 Rev D Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Existing Utilities Cross Section - Drawing No.LRC-LE-GEN-XX-DR-CE-109 S1 Rev P4 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 - Proposed Levels - Drawing No.LRC-LE-GEN-XX-DR-CE-600 S1 Rev P5 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 - Kerbing Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-106 S1 Rev P5 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 - Construction Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-105 S1 Rev P5 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 Site Clearance - Drawing No.LRC-LE-GEN-XX-DR-CE-104 S1 Rev P5 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 Swept Path Analysis - Drawing No.LRC-LE-GEN-XX-DR-CE-103 S1 Rev P5 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 Layout - Drawing No.LRC-LE-GEN-XX-DR-CE-102 S1 Rev P4 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Kerbing and Surface Finishes Layout - Drawing No.0460-101 Rev A Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 Geometry Alignment - Drawing No.LRC-LE-GEN-XX-DR-CE-101 S1 Rev P4 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 General Arrangement - Drawing No.LRC-LE-GEN-XX-DR-CE-100 S1 Rev P5 Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Presentation Layout - Drawing No.JIG047-050 Rev D Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Public Open Space Areas - Drawing No.JIG047-015 Rev - Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Parking Dispersion Layout - Drawing No.JIG047-014 Rev - Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Detailed Soft Landscape Strategy (Composite Plan) - Drawing No.BEA-24-050-13 Rev P05 Landscaping plan/details · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Tenure Dispersion Layout - Drawing No.JIG047-013 Rev - Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Materials & Enclosures Layout - Drawing No.JIG047-012 Rev - Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Pond Cross Section Detail - Drawing No.0460-11 Rev - Section plans · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Planning Layout - Drawing No.JIG047-011 Rev - Layout plans · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Adoptable Highway Area Layout - Drawing No.0460-10 Rev B Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Appraisal Site Cross Sections Sheet 2 - Drawing No.0460- 9 Rev - Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Appraisal Site Cross Sections Sheet 1 - Drawing No.0460-8 Rev - Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Appraisal Site Cross Sections Layout - Drawing No.0460-7 Rev - Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Soft Landscape Strategy (5 of 5) - Drawing No.BEA-24-050-07 Rev P02 Landscaping plan/details · 14 Aug 2024 View ↗ PDF DRAWING - Pedestrian Visibility Splays Layout - Drawing No.0460-6 Rev B Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Soft Landscape Strategy (4 of 5) - Drawing No.BEA-24-050-06 Rev P02 Landscaping plan/details · 14 Aug 2024 View ↗ PDF DRAWING - Appraisal Iscopachyte Layout - Drawing No.0460-5 Rev A Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Soft Landscape Strategy (3 of 5) - Drawing No.BEA-24-050-05 Rev P02 Landscaping plan/details · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Soft Landscape Strategy (2 of 5) - Drawing No.BEA-24-050-04 Rev P02 Landscaping plan/details · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - MPV Tracking Layout - Drawing No.0460-3 Rev E Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Fire Appliance Tracking Layout - Drawing No.0460-2 Rev E Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Refuse Vehicle Tracking Layout - Drawing No.0460-1 Rev E Detail drawing · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - S278 Location Plan - Drawing No.LRC-LE-GEN-XX-DR-CE-001 S1 Rev P2 Location plan · 14 Aug 2024 View ↗ PDF SUPERSEDED DRAWING - Soft Landscape Strategy (1 of 5) - SUPERSEDED Drawing No.BEA-24-050-03 Rev P02 Landscaping plan/details · 14 Aug 2024 View ↗

All documents on the council site ↗

Associated applications 9

Site constraints 8

5 listed buildings within 150 m of the postcode pin
Nearest: The Greyhound Inn, Grade II, the postcode pin is inside its outline · 5 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 5 with distances
Historic England ↗
Hawksbury Junction Conservation Area conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Air quality management area: Coventry City-Wide AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Also on the record
National infrastructure project: The Grand Union Canal Transfer, at pre-application; Coalfield, development low risk area; Inside the Hawkesbury built-up area; Priority habitat about 39 m away: Deciduous woodland; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 4, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Coventry - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Coventry
Application type
RESM Application for approval of reserved matters following outline approval (major)
Postcode
CV6 6DF
Received
13 Aug 2024
Validated
13 Aug 2024
Ward
Longford
Case officer
Show
Target decision
7 Oct 2025
Decision
Granted Conditions
Decision date
7 Oct 2025
Decision level
Delegated decision
Applicant
Show
Agent
Harris Lamb

Consultation & key dates

Statutory expiry
7 Oct 2025
Coventry
Planning Authority Score
7.7/10
Good
#35 of 296 councils
Relevant to this application:
Major dwellings

Coventry is one of the fastest councils in England for householder decisions, ranking #13 out of 296. Only 13% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly more likely to be approved here (90%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Coventry decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #219 of 296
90%
Householder approved
Above avg (90%) #189 of 296
91%
Decided in 8 weeks
Above avg (63%) #13 of 296
13%
Extended time limit
Below avg (41%) #7 of 296
72%
Minor dwellings approved
114 decided (1-9 homes)
89%
Major dwellings approved
28 decided (10+ homes)
74%
Change of use approved
100 decided
1,131
Total decisions
186 refused in the year to March 2026