Tower Bridge Business Complex 100 Clements Road Aka Biscuit Factory And Bermondsey Campus Site Keetons Road… Data via plota.co.uk

25/AP/3297 - Variation Approved

Proposal

Non-material amendments to conditions 1 (approved plans), 3 (air source heat pumps), 4 (fire safety), and 6 (wheelchair unit) of the Block V reserved matters approval ref. 'Application for approval of reserved matters (access, appearance, landscaping, layout and scale) for Building V submitted pursuant to hybrid planning permission ref. dated 12.03.2024 for the redevelopment of the Biscuit Factory and Campus Site. The proposal is for a 10 storey building including 82 residential units (as 9,379sqm (GEA) of residential floorspace - Use Class C3) and 350sqm (GEA) of flexible Class A1/A3/A4/D1 floorspace in two unit at ground floor together with associated cycle parking, landscaping, public realm, plant and associated works'. The proposed amendments to Block V include: Revisions to the ground floor layout and its cycle stores. Addition of wind mitigation screens to west elevation balconies. Removal of one lift. Alterations to the flat layouts. Removing the roof plant screening and resizing of the plant room on level 8 terrace. Alterations to elevations such as to the curtain wall cill, window and cladding panel arrangements, external door widths, cladding panels changed to glazing, and window transom height. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
11 Nov 2025
✓
Validated
17 Dec 2025
✓
Approved
17 Apr 2026

Approved on 17 Apr 2026 · Source Team · Last checked 3 Oct 2026

Documents 47

Decision & officer reports 24

PDF 2363-5PA-PL-VZ-DR-A-400 REV C BLOCK V PROPOSED LEVEL 00 Decision - Plans · 13 Mar 2026 View ↗ PDF 2363-5PA-03-V08-DR-A-126 GA PLAN LEVEL 08 Decision - Plans · 13 Feb 2026 View ↗ PDF 2363-PRP-03-V08-DR-L-303 (REV C1) LEVEL 8 LANDSCAPE Decision - Plans · 13 Feb 2026 View ↗ PDF 2363-5PA-PL-VZ-DR-A-300 REV B PROPOSED NORTH ELEVATION - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-301 REV B PROPOSED EAST ELEVATION - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-302 REV B PROPOSED WEST ELEVATION - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-303 REV B PROPOSED SOUTH ELEVATION - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-362 REV A PROPOSED BAY STUDY UPPER LEVEL - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-401 REV B PROPOSED LEVEL 01 PLAN - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-402 REV B PROPOSED LEVEL 02 PLAN - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-403 REV B PROPOSED LEVEL 03-07 PLAN - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-408 REV B PROPOSED LEVEL 08 PLAN - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-409 REV B PROPOSED LEVEL 09 PLAN - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-410 REV B PROPOSED LEVEL 10 PLAN - BLOCK V Decision - Plans · 17 Dec 2025 View ↗ PDF LSQ-BPS_HTA-L_BV_DR-9000 REV PL5 LANDSCAPE MASTERPLAN GA - LEVEL 00 - BLOCK V Decision - Plans · 11 Nov 2025 View ↗ PDF VENTILATION STATEMENT Decision - Plans · 11 Nov 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-450 REV A PROPOSED SITE PLAN - BLOCK V Decision - Plans · 11 Nov 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-350 REV A PROPOSED COLOURED NORTH ELEVATION - BLOCK V Decision - Plans · 11 Nov 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-351 REV A PROPOSED COLOURED EAST ELEVATION - BLOCK V Decision - Plans · 11 Nov 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-352 REV A PROPOSED COLOURED SOUTH ELEVATION - BLOCK V Decision - Plans · 11 Nov 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-353 REV A PROPOSED COLOURED WEST ELEVATION - BLOCK V Decision - Plans · 11 Nov 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-360 REV A PROPOSED BAY STUDY - BLOCK V Decision - Plans · 11 Nov 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-370 REV A PROPOSED SECTION AA - BLOCK V Decision - Plans · 11 Nov 2025 View ↗ PDF 2363-5PA-PL-VZ-DR-A-371 REV A PROPOSED SECTION BB - BLOCK V Decision - Plans · 11 Nov 2025 View ↗

Statements & assessments 17

PDF APPENDIX 9.1 - PART_L_2021_GLA_CARBON_EMISSION_REPORTING_SPREADSHEET Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.2 BE LEAN SAP REPORTS Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.3 BE LEAN BRUKL REPORTS - TBP BLOCK V- RETAIL UNIT 2_BRUKL Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.3 BE LEAN BRUKL REPORTS - TBP BLOCK V_BRUKL Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.4 TM59- PART O OVERHEATING RESULTS Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.5 BE CLEAN SAP REPORTS Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.6 BE CLEAN BRUKL REPORTS - TBP BLOCK V- RETAIL UNIT 2_BRUKL Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.6 BE CLEAN BRUKL REPORTS - TBP BLOCK V_BRUKL Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.7 BE GREEN SAP REPORTS Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.8 BE GREEN BRUKL REPORTS - TBP BLOCK V- RETAIL UNIT 2_BRUKL Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.8 BE GREEN BRUKL REPORTS - TBP BLOCK V_BRUKL Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.9 DWELLING SELECTION SAP ASSESSMENTS Energy statement · 12 Nov 2025 View ↗ PDF APPENDIX 9.10 APARTMENT PEAS Energy statement · 12 Nov 2025 View ↗ PDF NON MATERIAL AMENDMENT REPORT Design and Access statement · 11 Nov 2025 View ↗ PDF FIRE SAFETY STRATEGY Fire Statement · 11 Nov 2025 View ↗ PDF ROOFTOP PLANT NOISE ASSESSMENT Noise impact assessment · 11 Nov 2025 View ↗ PDF ENERGY STATEMENT Energy statement · 11 Nov 2025 View ↗

All documents on the council site ↗

Associated applications 18

Site constraints 7

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Article 4 direction
Site allocation NSP13: Biscuit Factory and Campus. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 311 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Air quality management area: Southwark AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Also on the record
Radon affected area, class 2; Inside the Southwark built-up area; Public transport access: PTAL 4 (good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Southwark - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Southwark
Application type
Variation
Postcode
SE16 4DG
Received
11 Nov 2025
Validated
17 Dec 2025
Ward
North Bermondsey
Parish
Bermondsey And Rotherhithe
Case officer
Show
Target decision
1 May 2026
Decision
Agreed - for App Types VLA and VNMC
Decision date
17 Apr 2026
Decision level
Source Team
Agent
DP9 Ltd

Public comments

No public comments yet.

Last counted 3 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
13 Jan 2026
Env. assessment
No
Southwark
Planning Authority Score
7/10
Good
#64 of 296 councils
Relevant to this application:
Householder decisions

Southwark is faster than most councils at deciding householder applications, ranking #54 out of 296. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Southwark decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #93 of 296
95%
Householder approved
Above avg (90%) #92 of 296
78%
Decided in 8 weeks
Above avg (63%) #54 of 296
37%
Extended time limit
Below avg (41%) #122 of 296
92%
Minor dwellings approved
259 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
82%
Change of use approved
38 decided
1,622
Total decisions
132 refused in the year to March 2026