Development Site W of Nar Ouse Way King's Lynn Norfolk Data via plota.co.uk

25/01783/DISC_A - Discharge of Planning condition_A Decided

Proposal

DISCHARGE OF CONDITIONS 4,6,7,13,20,21 AND 25 FOR PHASE ONE ONLY and CONDITIONS 3 & 24 FOR THE WHOLE SITE ATTACHED TO PLANNING PERMISSION 25/01783/FM - Application for the phased development comprising the change of use of the land to an Active Travel Hub, alongside the construction of a single storey hub building, surface car park, pedestrian infrastructure, access, landscaping and ancillary works Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
2 Sept 2026
✓
Validated
7 Sept 2026
✓
Consultation
23 Sept 2026
✓
Discharge of Condition final letter
5 Nov 2026

Discharge of Condition final letter on 5 Nov 2026 · Discharge of Condition · Last checked 6 Nov 2026

Documents 65

Other documents 22

PDF CORRESPONDENCE Correspondence · 4 Nov 2026 View ↗ PDF SCIENTIFIC OFFICER CORRESPONDENCE Correspondence · 29 Oct 2026 View ↗ PDF AGENT CORRESPONDENCE Correspondence · 26 Oct 2026 View ↗ PDF AGENT CORRESPONDENCE Correspondence · 26 Oct 2026 View ↗ PDF DISC TEAM CORRESPONDENCE Correspondence · 22 Oct 2026 View ↗ PDF AGENT CORRESPONDENCE Correspondence · 19 Oct 2026 View ↗ PDF AGENT CORRESPONDENCE Correspondence · 12 Oct 2026 View ↗ PDF DOWNHAM IDB CORRESPONDENCE Correspondence · 7 Oct 2026 View ↗ PDF NCC HIGHWAY EMAIL Correspondence · 30 Sept 2026 View ↗ PDF DISC TEAM CORRESPONDENCE Correspondence · 28 Sept 2026 View ↗ PDF PUBLIC OPEN SPACE CORRESPONDENCE Correspondence · 28 Sept 2026 View ↗ PDF DISC TEAM CORRESPONDENCE Correspondence · 24 Sept 2026 View ↗ PDF CSNN CORRESPONDENCE Correspondence · 23 Sept 2026 View ↗ PDF DISC TEAM CORRESPONDENCE Correspondence · 18 Sept 2026 View ↗ PDF AGENT CORRESPONDENCE Correspondence · 17 Sept 2026 View ↗ PDF DISC TEAM CORRESPONDENCE Correspondence · 14 Sept 2026 View ↗ PDF AGENT & DISC TEAM CORRESPONDENCE Correspondence · 4 Sept 2026 View ↗ PDF AGENT CORRESPONDENCE Correspondence · 4 Sept 2026 View ↗ PDF AGENT CORRESPONDENCE Correspondence · 4 Sept 2026 View ↗ PDF UPDATED CALCULATIONS Report · 3 Sept 2026 View ↗ PDF CONSTRUCTION ZONES & MANAGEMENT, TRAFFIC MANAGEMENT & WELFARE SETUP Report · 3 Sept 2026 View ↗ PDF PRE-COMMENCEMENT CONDITIONS COVERING LETTER Correspondence · 3 Sept 2026 View ↗

All documents on the council site ↗

Associated applications 3

Site constraints 5

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
National infrastructure project about 1.1 km away: Kings Lynn B Connection Project
The site is about 1.1 km from the project boundary. Electricity line, decided. The project page says whether consent was granted. Also within 2 km: Palm Paper 3 CCGT Power station Kings Lynn (decided, about 1.1 km).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
SSSI about 232 m away: River Nar SSSI; Inside the King's Lynn built-up area.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Kings Lynn - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Kings Lynn
Application type
Discharge of Planning condition_A
Received
2 Sept 2026
Validated
7 Sept 2026
Ward
South And West Lynn
Parish
King's Lynn
Case officer
Show
Target decision
20 Nov 2026
Decision
Discharge of Condition final letter
Decision date
5 Nov 2026
Decision level
Discharge of Condition
Applicant
Show
Agent
DHA Planning
Freehold owner
Show

Public comments

No public comments yet.

Last counted 6 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15195538
Planning Portal ref
PP-15195538
Consultation
23 Sept 2026
Comments by
14 Oct 2026
Statutory expiry
2 Nov 2026
Env. assessment
No
Kings Lynn
Planning Authority Score
8.4/10
Excellent
#17 of 296 overall
Relevant to this application:
Change of use

Kings Lynn is one of the fastest councils in England for householder decisions: #20 of 296 on speed. Only 27% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Kings Lynn decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #133 of 296
95%
Householder approved
Above avg (90%) #82 of 296
87%
Decided in 8 weeks
Above avg (63%) #20 of 296
27%
Extended time limit
Below avg (41%) #41 of 296
76%
Minor dwellings approved
261 decided (1-9 homes)
85%
Major dwellings approved
26 decided (10+ homes)
89%
Change of use approved
44 decided
1,216
Total decisions
131 refused in the year to March 2026

Freehold owner: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.