Planning decisions in Gwynedd
How long Gwynedd takes to decide a planning application and how many it approves, from the 656 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
93 daysmedian from validation to decision (UK 52); 113 from receipt
30%decided within eight weeks (UK 71%), 49% within thirteen
88%approved (UK 90%): 552 approved, 77 refused, 11 withdrawn
362 of 364UK rank for speed, down 350 places on last year; 261 of 364 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 162 | 14% | 84% | 179 | 345 of 347 |
| Householder applications | 78 | 31% | 93% | 164 | 189 of 195 |
| Discharge of conditions | 53 | 52% | 100% | 70 | 185 of 285 |
| Amendments | 56 | 56% | 89% | 53 | 293 of 332 |
| Lawful development certificates * | 99 | 26% | 62% | 27 | 329 of 329 |
| Listed building consent * | 224 | 0% | 100% | 27 | 254 of 254 |
| Tree works * | 66 | 33% | 80% | 20 | 303 of 311 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 95% | 88 | 89% | 509 |
| Planning committee | 5% | 290 | 69% | 26 |
Where the register states how the decision was made. 121 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 32 | 78% | 88% | 62 |
| 2017 * | 47 | 70% | 89% | 57 |
| 2018 * | 42 | 63% | 88% | 44 |
| 2019 * | 86 | 9% | 100% | 35 |
| 2020 * | 46 | 63% | 91% | 78 |
| 2021 * | 107 | 0% | 100% | 33 |
| 2022 * | 48 | 51% | 85% | 41 |
| 2023 * | 34 | 67% | 86% | 37 |
| 2025 | 198 | 2% | 89% | 228 |
| 2026 so far | 99 | 28% | 88% | 502 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- Station House, MINFFORDD STATION, Minffordd, Penrhyndeudraeth, Gwynedd, LL48 6HFDymchwel estyniad un llawr ochr modern a chodi estyniad deulawr newydd / Demolish existing modern single storey extension and erect new twodue 3 Nov 2025
- Cyngor Gwynedd, BRYNREFAIL SCHOOL Ffordd Crawia, Llanrug, Caernarfon, Gwynedd, LL55 4ADCais ôl-weithredol i adeiladu adeilad un llawr newydd i’w ddefnyddio fel canolfan gymunedol ar flaen maes yr ysgol ar ôl dymchwel yr adeiladdue 11 Nov 2025
- DERWIN FAWR, Pant Glas, Garndolbenmaen, Gwynedd, LL51 9LZCyfnewid tri tyrbin gwynt presennol gyda tyrbinau newydd gyda diamedr o 30m, ar dyrrau 30m (i ganol y rotwr) gyda uchder blaen 45m, gyda syldue 24 Nov 2025
- Rear Of Porth Y Llechen, Y Felinheli, LL56 4JGGwaith i goed sy'n destun Gorchymyn Diogelu Coed. Work to trees protected by a Tree Preservation Order.due 26 Nov 2025
- Cefn Lleuar Cefn Lleuar, Llanllyfni, Caernarfon, LL54 6STStorfa tail. Manure storedue 1 Dec 2025
- Woodland To The Rear Of Plas Tanrallt, Pwllheli, LL53 5EEGwaith i goed sydd yn destun gorchymyn gwarchod coed sydd yn eistedd mewn ardal gadwraeth. / Work on trees that are subject to a tree preserdue 4 Dec 2025
- B & Q PLC Caernarfon Road, Bangor, Gwynedd, LL57 4SUGosod arwyddion ffasgia wedi'u goleuo a heb eu goleuo. Gan gynnwys arwydd totem newydd gyda'r geiriad 'B&Q' yn unig wedi ei oleuo. Illuminatdue 9 Dec 2025
- YSTUMLLECH, Trefor, Caernarfon, Gwynedd, LL54 5PTAdeiladu sied 12m x 8m (3m at y bondo) i storio offer amaethyddol sy'n gysylltiedig â chadwraeth y tir. Hefyd, adeiladu mynedfa newydd o'r fdue 9 Dec 2025
Decided in the last three weeks
- 21 Dôl Beuno, Bontnewydd, Caernarfon, Gwynedd, LL55 2UEDymchwel adeilad allanol a chodi estyniad deulawr cefn Demolish outbuilding and construct a two storey rear extensionApproved30 Sept 2026
- LYNFOD, Waunfawr, Caernarfon, Gwynedd, LL55 4YSCais ar gyfer adeiladu estyniad deulawr yng nghefn yr eiddo ynghyd a porth i flaen yr eiddo. Two-storey extension to the rear of the propertApproved30 Sept 2026
- CARTREF BACH Panorama Road, Barmouth, Gwynedd, LL42 1DQAdeiladu annedd newydd a dymchwel yr un presennol. The erection of a new dwelling and demolition of the existing.Approved30 Sept 2026
- TYDDYN BERTH, Chwilog, Pwllheli, Gwynedd, LL53 6RQCais am borth i gysylltu'r eiddo preswyl i adeilad allanol presennol a chreu anecs i greu ardal byw i berson anabl cofresredig / Extension oApproved30 Sept 2026
- METHODIST CHAPEL, Glan Yr Afon, Corwen, Gwynedd, LL21 0HBCodi sied bren er storio coed tan wrth gefn y safle ac addasu'r mynedfa gerbydol a ganiateir eisoes / Erection of timber storage shed for fiApproved29 Sept 2026
- Arfordir Bae Caernarfon, GwyneddCais am farn gwmpasu o dan Reol 14, Rhan 4 o Reoliadau Cynllunio Gwlad a Thref [Asesiad Effaith Amgylcheddol] [Cymru] 2017. Mae'r datblygiadApproved29 Sept 2026
- GIMLET ROCK CARAVAN PARK Morfa'r Garreg, Pwllheli, Gwynedd, LL53 5AYGosod pontŵn arnofiol a llwybr i gerddwyr ar sylfaeni pyst dur. Installation of a floating pontoon and pedestrian gangway supported by steelApproved28 Sept 2026
- BRO ABER Lôn Garmon, Abersoch, Gwynedd, LL53 7UQCais llawn i godi dau dŷ deulawr fforddiadwy gyda datblygiadau cysylltiedig gan gynnwys creu mynedfeydd cerbydol, mannau parcio a thirlunioApproved28 Sept 2026
Built nightly from Gwynedd's planning register. Ranks are among the 364 published councils. See planning applications in Gwynedd, or get alerts for Gwynedd.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.