Barn conversion to dwelling at Barn Church Lane Tideswell
Summary of planning committee decision
Decided by Peak District Planning Committee on 10 Oct 2025.
What was proposed
The application sought a dwelling through changing, altering and extending an existing roadside barn in the Tideswell Conservation Area.
“This application seeks permission for the change of use and alterations and extension to an existing roadside barn on Church Lane, Tideswell, within the Tideswell Conservation Area. The barn is considered to be a non-designated heritage asset, albeit works have been carried out which are considered to have resulted in harm to its character.”
“The extensions and alteration of the barn and associated works are considered to harm to the character and appearance of the barn and Conservation Area. The development would not achieve the conservation or enhancement of a non-designated heritage asset, and would not meet one of the exceptions for new housing in the National Park.”
Officer report
The site and surroundings
The stone barn stands on the edge of Tideswell within the Conservation Area, near homes, further properties and allotments.
“The application relates to an existing stone barn located on the south west edge of Church Lane, on the edge of Tideswell and within Tideswell Conservation Area. The barn is formed of limestone with pitched roof.”
“Prior to works commencing, the barn had a natural gritstone roof, single lean-to on its north west elevation and single storey off-shot. The barn fronts the roadside. The nearest neighbouring properties are dwellings on Chantry Lane to the north side of Church Street. Further properties are north west on Church Lane with allotments to the north east.”
Officer report
Earlier permissions and enforcement
A 2015 conversion permission was followed by reconstruction beyond its terms, a withdrawn application and an enforcement case.
“21/0051: An enforcement case was opened on the site as the works to the building had gone beyond what was permitted by the 2015 planning permission.”
“Following a meeting in July 2024, the view from the Authority was that the extent of works carried out went beyond the 2015 permission as they included substantial re-building and construction of extensions significantly larger than the approved dimensions.”
Officer report
Why officers recommended refusal
Officers considered the proposal harmful to heritage and the Conservation Area, unacceptable in principle and unable to demonstrate a safe access.
“The proposed dwelling is not acceptable in principle as it does not achieve the conservation and / or enhancement of a non-designated heritage asset, and it does not meet any other exception for new housing in the National Park, contrary to Core Strategy Policy HC1 and Development Management Policy DMC10.”
“The proposed development would have an unacceptable design and would result in harm to the character and appearance of the non-designated barn and Tideswell Conservation Area. The harm to the Conservation Area would be less than substantial but would not be outweighed by any public benefits, and harm to the non-designated barn is not outweighed as part of the planning balance.”
Officer report
Consultation responses
Highways objected over inadequate visibility and safety, archaeology sought heritage and boundary information, ecology supported conditions, and the parish council supported the application.
“Derbyshire County Council (Highways): NP/DDD/0915/0863 approved drawing 1517-02 Rev C shows visibility splays mentioned in the HA response, but the submitted information provided for has not provided any visibility splays for assessment, although the supporting statement mentions that a safer access with better visibility in the direction of Tideswell is proposed.”
“Peak District National Park Authority Archaeology: 1) No heritage statement has been submitted and there is not a sufficient understanding of what the heritage value and significance of the structure is. In my comments to the previous application (0820/0726) I did request sufficient supporting heritage information.”
Officer report
Comments received
One letter did not object but raised concerns about open-market use, drainage, future agricultural development and protecting the greenfield site.
“One letter has been received which does not object to the application, but raises a number of matters of consideration and / or concern:”
“The reconstruction quality looks good and will likely maintain building character. • It is understood the barn would be for open market use rather than locally tied. • If an owner is not interested or able to farm the land associated with the barn, then conversion of agricultural buildings is the best alternative where these have merit.”
Officer report
What members discussed
Members discussed the proposal’s overall size, the extensions, the increased barn height and the Highways Authority’s consultation response.
“The Officer presented the report and outlined the reasons for refusal as detailed in the report. Some Members had visited the site the previous day. The following spoke under the public participation at meetings scheme: • Danny Hopkins- Applicant Members had concerns over the overall size of the proposed development and also queried the consultation response provided by the Highways Authority.”
Minutes
The committee’s decision
The committee amended the refusal reasons, then carried a motion to refuse the application.
“That the application be REFUSED for the following reasons:”
Minutes
The members' reasons
The resolution gives these reasons:
Minutes
- The proposal does not achieve the conservation and / or enhancement of a non-designated heritage asset, and it does not meet any other exception for new housing in the National Park, contrary to Core Strategy Policy HC1 and Development Management Policy DMC10.
Source: the council's minutes, quoted word for word.
Sources
- Peak District Planning Committee minutes, 10 October 2025
- Agenda and papers (council website)
Source: Plota analysis of Peak District's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Peak District Planning Committee
- Council
- Peak District
- Date
- Friday 10 October 2025
- Recommendation
- Officers recommended refusal
- Committee decided
- Refused
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Peak District committee decisions →
This committee's year
19 decisions in the 12 months to this meeting, 2 against officer advice.
Source: Plota analysis of the committee's minutes.