Land North West Of West Hartford Fire Station West Hartford Business Park West Hartford Cramlington Northumberland Data via plota.co.uk

25/04509/OUT - Outline Application Approved at committee

Approved at planning committee on 5 May 2026, subject to a legal agreement. The council issues its decision notice once the agreement is signed.

Proposal

Outline permission (all matters reserved apart from access) for employment, research, battery storage, and training centre use (b2, b8, e(g) and sui generis), petrol station (Sui Generis use), and ancillary retail (E(a) use), coffee shop/drive-thru (E(b) and sui generis use), gym (E(d) use), with associated ground mounted solar PV (Sui Generis use) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
16 Dec 2025
✓
Consultation
22 Apr 2026
✓
Committee
5 May 2026
Decision notice
Not issued yet

Under consideration

No decision has been issued yet. Plota predicted a decision soon after comments close on 30 Apr 2026; it is now day 342.

The consultation period closed on 30 Apr 2026.

Planning committee

Decided by Northumberland (County) Strategic Planning Committee on 5 May 2026. The council has not yet issued its decision notice.

Approved unanimously

As officers recommended.

  • Officers advised approval because the employment-led scheme could deliver economic and infrastructure benefits, with impacts managed through conditions and mitigation.
  • Residents raised concerns about flooding, traffic, noise, landscape, wildlife, retail uses and the need for the development; one response supported a petrol station and coffee shop.
  • The committee voted unanimously to grant permission, subject to amended conditions and a legal agreement.
Read how the committee decided The proposed development, officers’ assessment, consultation responses, public views, committee discussion, conditions and decision.

Source: Plota analysis of Northumberland (County)'s committee minutes of 5 May 2026.

Documents 49

Consultation & comments 42

PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 20 Apr 2026 View ↗ PDF HIGHWAYS Consultee Response · 17 Apr 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 16 Apr 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 15 Apr 2026 View ↗ PDF LANDSCAPE ARCHITECT Consultee Response · 10 Apr 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 2 Apr 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 2 Apr 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 2 Apr 2026 View ↗ PDF PUBLIC HEALTH Consultee Response · 1 Apr 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 31 Mar 2026 View ↗ PDF LANDSCAPE ARCHITECT Consultee Response · 27 Mar 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 26 Mar 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 25 Mar 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 3 Mar 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 3 Mar 2026 View ↗ PDF COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 22 Feb 2026 View ↗ PDF COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 15 Feb 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 10 Feb 2026 View ↗ PDF HIGHWAYS ADDITIONAL Consultee Response · 6 Feb 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 6 Feb 2026 View ↗ PDF COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 6 Feb 2026 View ↗ PDF COMMENT (NEUTRAL) SUBMITTED ONLINE General Comment · 5 Feb 2026 View ↗ PDF COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 4 Feb 2026 View ↗ PDF COMMENT (SUPPORT) SUBMITTED ONLINE Support Comment · 30 Jan 2026 View ↗ PDF COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 27 Jan 2026 View ↗ PDF NATIONAL HIGHWAYS Consultee Response · 27 Jan 2026 View ↗
PDF Objector’s name hidden Show Objection · 22 Jan 2026 View ↗
PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 22 Jan 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 22 Jan 2026 View ↗ PDF COMMENT (NEUTRAL) SUBMITTED ONLINE General Comment · 21 Jan 2026 View ↗ PDF LLFA Consultee Comment · 16 Jan 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 14 Jan 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 13 Jan 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 8 Jan 2026 View ↗
PDF Commenter’s name hidden Show Representation · 8 Jan 2026 View ↗
PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 7 Jan 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 5 Jan 2026 View ↗ PDF CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 5 Jan 2026 View ↗ PDF THE COAL AUTHORITY Consultee Response · 31 Dec 2025 View ↗ PDF NORTHUMBRIAN WATER LTD Consultee Response · 30 Dec 2025 View ↗ PDF NATIONAL GRID Consultee Response · 24 Dec 2025 View ↗ PDF ACTIVE TRAVEL ENGLAND Consultee Response · 19 Dec 2025 View ↗

All documents on the council site ↗

Site constraints 3

Coal mining development high risk area
Recorded coal mining features at or near the surface. Most planning applications here need a coal mining risk assessment.
From the Mining Remediation Authority, formerly the Coal Authority. The development high risk area marks recorded coal mining features at or near the surface: mine shafts and adits, shallow workings, mine gas and former opencast sites. Most planning applications there need a coal mining risk assessment; householder applications, changes of use and some minor works are exempt. Mine entry positions come from old plans and can be out by several metres, and unrecorded workings can exist anywhere in the coalfield.
Coal mining risk assessments ↗
Agricultural land, grade 3b, surveyed
Not best and most versatile land (grades 1, 2 and 3a). Source: Natural England's post-1988 ALC field survey (Leeds). Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Survey report ↗
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Looking for land for battery storage?

Plota Sites searches every land parcel in England and Wales: 9,119 sites fit this search. On and off the market, free to search.

Land for battery storage
Work with planning data?

Every application in Northumberland (County) - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Outline Application
Received
16 Dec 2025
Validated
16 Dec 2025
Ward
Cramlington North West
Parish
Cramlington
Case officer
Show
Target decision
30 Nov 2026
Decision level
Delegated Decision
Agent
DPP Planning

Decision outlook

Day 342, past the statutory target. 50% of outline applications in Northumberland (County) are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 22 Nov 2026.

Day 342286 days past the 56-day target
50%decided within 8 weeks
30%approved
12decided in the last year

Plota live figures for outline applications decided by Northumberland (County) in the last twelve months, from validation. Northumberland (County) decision record →

Public comments

10comments received
6 objecting3 neutral1 supporting

60% object · below the UK average of 74%

1,306 neighbours consulted · Last counted 14 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14513144
Planning Portal ref
PP-14513144
Neighbours
22 Apr 2026
Consultation
22 Apr 2026
Comments by
30 Apr 2026
Site or press notice
16 Jan 2026
Committee
5 May 2026
Statutory expiry
13 Jan 2026
Env. assessment
No
Northumberland (County)
Planning Authority Score
3.8/10
Below average
#207 of 296 overall
Relevant to this application:
Major dwellings

Northumberland (County) is #167 of 296 councils on householder decision speed. 47% of applications have the time limit extended, above the 41% national average. Householder applications are slightly more likely to be approved here (91%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Northumberland (County) decision statistics
Based on MHCLG data, the year to March 2026
88%
Overall approval rate
Above avg (87%) #158 of 296
91%
Householder approved
Above avg (90%) #178 of 296
62%
Decided in 8 weeks
Below avg (63%) #167 of 296
47%
Extended time limit
Above avg (41%) #210 of 296
80%
Minor dwellings approved
223 decided (1-9 homes)
89%
Major dwellings approved
36 decided (10+ homes)
86%
Change of use approved
71 decided
2,013
Total decisions
233 refused in the year to March 2026