220 Ranelagh Road Ipswich Suffolk IP2 0AQ Data via plota.co.uk

26/00836/TALF - Works to Trees covered by TPO Pending Consideration

Proposal

Works to trees protected by TPO 3 of 2023: T1-6 (Robinia) - fell to near ground level; T7 (Maple) - crown lift to approx. 2.5m; T8 & T9 (Robinia) - crown lift to approx. 2.5m. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
9 Nov 2026
✓
Validated
10 Nov 2026
Decision
Expected by 5 Jan 2027

Under consideration

No decision has been issued yet. Plota predicts a decision around 16 Dec 2026, from Ipswich's recent tree and landscaping works.

Comments are open until 1 Dec 2026

Comment on this application ↗

Site constraints 5

In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From rivers and the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
Local nature reserve 221 m away: Alderman Canal West
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
National infrastructure project 918 m away: Ipswich Rail Chord
The site is 918 m from the project boundary. Railway, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Ipswich built-up area; Flood defence 40 m away (natural high ground).
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 12 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area3,169 m² (34,111 sq ft)
Energy ratingC (asset rating 62)
UseRetail/Financial and Professional Services
HeatingAir Conditioning

From the energy performance certificate lodged in March 2026, the latest held for this property, matched to this application by its address. The building may have changed since. View the certificate

Work with planning data?

Every application in Ipswich - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Ipswich
Application type
Works to Trees covered by TPO
Postcode
IP2 0AQ
Received
9 Nov 2026
Validated
10 Nov 2026
Ward
GIPPING
Case officer
Show
Target decision
5 Jan 2027
Applicant
Show

Decision outlook

Day 13 of the 56-day target. Ipswich usually decides tree and landscaping works by day 36.

Day 1343 days to the 56-day target
97%decided within 8 weeks
99%approved
176decided in the last year

Plota live figures for tree and landscaping works decided by Ipswich in the last twelve months, from validation. Ipswich decision record →

Consultation & key dates

Consultation
10 Nov 2026
Comments by
1 Dec 2026
Site or press notice
17 Nov 2026
Ipswich
Planning Authority Score
7.6/10
Good
#38 of 296 overall
Relevant to this application:
Householder decisions

Ipswich is faster than most councils at deciding householder applications: #67 of 296 on speed. Householder applications are more likely to be approved here than most councils, with a 98% approval rate vs 90% nationally.

More permissive than most councils
98% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Ipswich decision statistics
Based on MHCLG data, the year to March 2026
94%
Overall approval rate
Above avg (87%) #40 of 296
98%
Householder approved
Above avg (90%) #18 of 296
76%
Decided in 8 weeks
Above avg (63%) #67 of 296
38%
Extended time limit
Below avg (41%) #129 of 296
81%
Minor dwellings approved
27 decided (1-9 homes)
100%
Major dwellings approved
5 decided (10+ homes)
82%
Change of use approved
62 decided
429
Total decisions
27 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use