PA/26/00952/S - Non-material amendment (TCPA S96a) Approved

Proposal

Non-material amendment to planning permission (dated, 29/05/2025) comprising alterations to fenestration, balconies, louvre panels and spandrels. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
2 Jun 2026
✓
Approved
14 Jul 2026

Approved on 14 Jul 2026 · Delegated · Last checked 19 Jul 2026

Documents 19

All documents on the council site ↗

Associated applications 6

Site constraints 8

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Archaeological priority area: Tower Hamlets APA 3.1
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 8 m away: Thames Tideway Tunnel
The site is about 8 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: Silvertown Tunnel (decided, about 1887 m); London Strategic Heat Main Project (at pre-application, about 1626 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
1 listed building within 150 m of the postcode pin; Inside the Tower Hamlets built-up area; Public transport access: PTAL 5 (very good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Non-material amendment (TCPA S96a)
Postcode
E14 8JH
Received
2 Jun 2026
Validated
2 Jun 2026
Ward
Canary Wharf
Case officer
Show
Target decision
30 Jun 2026
Decision
Permit
Decision date
14 Jul 2026
Decision level
Delegated
Applicant
Show
Agent
Rolfe Judd Planning

Consultation & key dates

Statutory expiry
30 Jun 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions