Kellarton House, Wootton Road, Tiptoe, Lymington SO41 6FT Data via plota.co.uk

26/01230FULL - Full Application Allocation

Proposal

Single storey side extension; new doors, windows and railings to create balcony Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
2 Nov 2026
Decision
Expected by 13 Jan 2027

Under consideration

No decision has been issued yet. Plota predicts a decision around 22 Dec 2026, from New Forest (Park)'s recent extensions.

Site constraints 10

Aerodrome safeguarding zoneHord004
Nutrient neutrality catchment: Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
New Forest National Park
The park authority decides applications here. Great weight to conserving the landscape; major development restricted.
Landscape, scenic beauty and wildlife carry great weight, and major development is only allowed in exceptional circumstances.
2 Article 4 directions
Article 4 Direction Np New Forest Campsite · Article 4 Direction Np New Forest Recreational Campsite. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project: Navitus Bay Wind Park
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
1 listed building within 150 m
Nearest: Ye Olde Forge Cottage, Grade II, 13 m away
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Historic England ↗
Aerodrome safeguarding zoneCouncil record
Recorded by the council for this site.
Council site ↗
Hord004Council record
Recorded by the council for this site.
Council site ↗
Also on the record
Radon affected area, class 3; Inside the Tiptoe built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 19 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area209 m² (2,250 sq ft)
Energy ratingD (64 out of 100), could reach C
PropertyDetached house, 9 habitable rooms
Built1976 to 1982
HeatingBoiler and radiators, mains gas
WallsCavity wall, filled cavity

From the energy performance certificate lodged in May 2013, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in New Forest (Park) - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Application
Postcode
SO41 6FT
Received
2 Nov 2026
Parish
Hordle Parish Council
Target decision
13 Jan 2027
Applicant
Show
Agent
CMCdesign

Decision outlook

Day 21 of the 56-day target. New Forest (Park) usually decides extensions by day 50.

Day 2135 days to the 56-day target
74%decided within 8 weeks
90%approved
73%go to committee

Plota live figures for extensions decided by New Forest (Park) in the last twelve months, from validation. New Forest (Park) decision record →

Consultation & key dates

Alt. reference
PP-15335090
New Forest (Park)
Planning Authority Score
3.3/10
Poor
#226 of 296 overall
Relevant to this application:
Householder decisions

New Forest (Park) is slower than most councils at deciding householder applications: #254 of 296 on speed. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
New Forest (Park) decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #136 of 296
92%
Householder approved
Above avg (90%) #160 of 296
45%
Decided in 8 weeks
Below avg (63%) #254 of 296
44%
Extended time limit
Above avg (41%) #180 of 296
75%
Minor dwellings approved
28 decided (1-9 homes)
50%
Major dwellings approved
4 decided (10+ homes)
83%
Change of use approved
18 decided
487
Total decisions
55 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.