Paragon Automotive Kiln Lane Stallingborough North East Lincolnshire DN41 8DQ Data via plota.co.uk

DM/1010/25/FUL - Full Application Approved

Proposal

Remove temporary spray booth, erect single storey extension to rear of existing bodyshop/workshop to include internal reconfiguration and external seating area, erect new detached pre-delivery inspection building to include covered canopy, office, storage and associated staff facilities, installation of covered cycle shelter, watercourse crossing and associated works Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 18 Dec 2025
✓
Consultation
5 Jan 2026
✓
Approved
17 Apr 2026

Approved on 17 Apr 2026 · Delegated Decision · Last checked 3 Oct 2026

Documents 74

Statements & assessments 26

PDF ECOLOGY COMMENT Consultee Comment - No Details · 14 Apr 2026 View ↗ PDF DRAINAGE MAX OUTFLOW DETAILS Supporting Documents · 20 Mar 2026 View ↗ PDF CONSTRUCTION METHOD STATEMENT Supporting Documents · 20 Mar 2026 View ↗ PDF DRAINAGE CATCHMENT Supporting Documents · 20 Mar 2026 View ↗ PDF TRANSPORT STATEMENT Amended Document · 23 Feb 2026 View ↗ PDF CONSTRUCTION METHOD STATEMENT Supporting Documents · 11 Feb 2026 View ↗ PDF PILING/FOUNDATIONS STATEMENT Supporting Documents · 11 Feb 2026 View ↗ PDF DRAINAGE OFFICER COMMENT Consultee Comment - No Details · 8 Jan 2026 View ↗ PDF HERITAGE OFFICER COMMENT Consultee Comment - No Details · 5 Jan 2026 View ↗ PDF NORTH EAST LINDSEY DRAINAGE BOARD COMMENT Consultee Comment - No Details · 23 Dec 2025 View ↗ PDF RIGHTS OF WAY - HIGHWAYS AND TRANSPORT COMMENT Consultee Comment - No Details · 22 Dec 2025 View ↗ PDF PLANNING STATEMENT INCLUDING STATEMENT OF COMMUNITY ENGAGEMENT Supporting Documents · 18 Dec 2025 View ↗ PDF FLOOD RISK ASSESSMENT Flood Risk Assessment · 17 Dec 2025 View ↗ PDF BNG METRIC Biodiversity Net Gain · 1 Dec 2025 View ↗ PDF EXTERNAL LIGHTING STATEMENT Supporting Documents · 1 Dec 2025 View ↗ PDF NOISE IMPACT ASSESSMENT - TECHNICAL NOTE Supporting Documents · 1 Dec 2025 View ↗ PDF PRELIMINARY RISK ASSESSMENT (TIER 1) Supporting Documents · 1 Dec 2025 View ↗ PDF PRELIMINARY RISK ASSESSMENT (TIER 1) Supporting Documents · 1 Dec 2025 View ↗ PDF PRELIMINARY RISK ASSESSMENT (TIER 1) Supporting Documents · 1 Dec 2025 View ↗ PDF PRELIMINARY RISK ASSESSMENT (TIER 1) Supporting Documents · 1 Dec 2025 View ↗ PDF TRANSPORT STATEMENT Superseded Documents · 1 Dec 2025 View ↗ PDF AIR QUALITY ASSESSMENT Supporting Documents · 1 Dec 2025 View ↗ PDF BNG SUMMARY REPORT Biodiversity Net Gain · 1 Dec 2025 View ↗ PDF DESIGN & ACCESS STATEMENT Design & Access Statement · 1 Dec 2025 View ↗ PDF ENERGY STATEMENT Supporting Documents · 1 Dec 2025 View ↗ PDF ECOLOGY WALKOVER ASSESSMENT STATEMENT Supporting Documents · 1 Dec 2025 View ↗

Plans & drawings 25

PDF TRAFFIC MANAGEMENT PLAN Supporting Documents · 20 Mar 2026 View ↗ PDF PROPOSED ELEVATIONS Proposed Elevations · 18 Dec 2025 View ↗ PDF PROPOSED FLOOR PLAN Proposed Plans · 18 Dec 2025 View ↗ PDF EXISITING FLOOR PLAN Existing Plans · 18 Dec 2025 View ↗ PDF PROPOSED 3D INDICATIVE VISUAL Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED 3D INDICATIVE VISUAL Proposed Plans · 1 Dec 2025 View ↗ PDF EXISTING ROOF PLAN Existing Plans · 1 Dec 2025 View ↗ PDF PROPOSED ROOF PLAN Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED FLOOR PLAN - PRE-DELIVERY INSPECTION BUILDING Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED ELEVATIONS - PRE-DELIVERY INSPECTION BUILDING Proposed Elevations · 1 Dec 2025 View ↗ PDF PROPOSED ROOF PLAN - PRE-DELIVERY INSPECTION BUILDING Proposed Plans · 1 Dec 2025 View ↗ PDF SITE LOCATION PLAN Site Location Plan · 1 Dec 2025 View ↗ PDF EXISTING SITE PLAN Existing Plans · 1 Dec 2025 View ↗ PDF PROPOSED SITE PLAN Block Plan · 1 Dec 2025 View ↗ PDF EXISTING ELEVATIONS Existing Elevations · 1 Dec 2025 View ↗ PDF PROPOSED EXTERNAL SURFACE TREATMENT PLAN Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED BOUNDARY TREATMENTS Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED EXTERNAL WORK DETAILS Additional Information/Plans · 1 Dec 2025 View ↗ PDF PROPOSED CROSSING POINT DETAILS Plans & Elevations- Proposed · 1 Dec 2025 View ↗ PDF PROPOSED 3D INDICATIVE VISUALS Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED 3D INDICATIVE VISUAL Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED 3D INDICATIVE VISUAL Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED SECTIONS - PRE-DELIVERY INSPECTION BUILDING Proposed Plans · 1 Dec 2025 View ↗ PDF PROPOSED LIGHTING PHILOSOPHY LAYOUT Proposed Plans · 1 Dec 2025 View ↗ PDF CONSTRUCTION PHASE HEALTH & SAFETY PLAN Supporting Documents · 1 Dec 2025 View ↗

All documents on the council site ↗

Site constraints 4

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Also on the record
National infrastructure project 1182 m away: Immingham Green Energy Terminal; Inside the Immingham built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area4,528 m² (48,739 sq ft)
Energy ratingC (asset rating 59)
UseB2 to B7 General Industrial and Special Industrial Groups
HeatingHeating and Natural Ventilation

From the energy performance certificate lodged in August 2015, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in North East Lincs - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Application
Postcode
DN41 8DQ
Received
around 18 Dec 2025
Validated
18 Dec 2025
Ward
Immingham
Parish
Stallingborough Parish Council
Case officer
Show
Target decision
17 Apr 2026
Decision
Approved with Conditions
Decision date
17 Apr 2026
Decision level
Delegated Decision
Agent
WSP

How this decision compares

Decided in 120 days from validation, 64 days slower than North East Lincs's median of 56 for full applications. Approved, as 95% of full applications here are.

55%decided within 8 weeks
95%approved
10%go to committee

Plota live figures for full applications decided by North East Lincs in the last twelve months, from validation. North East Lincs decision record →

Public comments

No public comments yet.

65 neighbours consulted · Last counted 3 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-13351828
Planning Portal ref
PP-13351828
Consultation
5 Jan 2026
Comments by
1 Feb 2026
Site or press notice
8 Jan 2026
Statutory expiry
19 Mar 2026
Env. assessment
No
North East Lincs
Planning Authority Score
5.3/10
Average
#132 of 296 councils
Relevant to this application:
Householder decisions

North East Lincs ranks #151 out of 296 councils for householder decision speed. 52% of applications have the time limit extended, above the 41% national average. Householder applications are more likely to be approved here than most councils, with a 97% approval rate vs 90% nationally.

More permissive than most councils
97% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
North East Lincs decision statistics
Based on MHCLG data, the year to March 2026
95%
Overall approval rate
Above avg (87%) #22 of 296
97%
Householder approved
Above avg (90%) #35 of 296
64%
Decided in 8 weeks
Above avg (63%) #151 of 296
52%
Extended time limit
Above avg (41%) #235 of 296
95%
Minor dwellings approved
43 decided (1-9 homes)
87%
Major dwellings approved
15 decided (10+ homes)
82%
Change of use approved
22 decided
467
Total decisions
24 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.