25/AP/2967 - Minor application Awaiting decision

Proposal

Roof extension (new third floor) including roof terrace associated privacy screening, green roof and plant. Change of use of the upper floors to residential (Class C3) to create 2 new dwellings including associated amenity space, cycle and refuse storage. Alterations at ground floor level including the installation of rear access door. Alterations to rear fenestration. (revised description) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
13 Oct 2025
✓
Validated
14 Oct 2025
Decision
Target date was 14 Jan 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 24 Nov 2026; it is now day 406.

Documents 46

Statements & assessments 19

PDF DAYLIGHT AND SUNLIGHT REPORT Daylight/Sunlight assessment · 13 Oct 2025 View ↗ PDF NOISE IMPACT ASSESSMENT Noise impact assessment · 13 Oct 2025 View ↗ PDF LONDON PLAN FIRE STATEMENT Fire Statement · 13 Oct 2025 View ↗ PDF BIODIVERSITY METRIC CALCULATION TOOL Biodiversity BNG Metrics · 13 Oct 2025 View ↗ PDF BIODIVERSITY NET GAIN ASSESSMENT Biodiversity survey / ecology assessment · 13 Oct 2025 View ↗ PDF FLOOD RISK ASSESSMENT - PART 4 Flood risk assessment · 13 Oct 2025 View ↗ PDF FLOOD RISK ASSESSMENT - PART 3 Flood risk assessment · 13 Oct 2025 View ↗ PDF FLOOD RISK ASSESSMENT - PART 1 Flood risk assessment · 13 Oct 2025 View ↗ PDF FLOOD RISK ASSESSMENT - PART 2 Flood risk assessment · 13 Oct 2025 View ↗ PDF PLANNING AND HERITAGE STATEMENT Heritage statement · 13 Oct 2025 View ↗ PDF DESIGN, APPEARANCE AND ACCESS STATEMENT Design and Access statement · 13 Oct 2025 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT - PART 2 Viability report · 13 Oct 2025 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT - PART 3 Viability report · 13 Oct 2025 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT - PART 4 Viability report · 13 Oct 2025 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT - PART 5 Viability report · 13 Oct 2025 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT - PART 6 Viability report · 13 Oct 2025 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT - PART 7 Viability report · 13 Oct 2025 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT - PART 8 Viability report · 13 Oct 2025 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT - PART 1 Viability report · 13 Oct 2025 View ↗

Plans & drawings 17

PDF 2404 00 00 110 REV PL03 PROPOSED SITE PLAN Plan - Proposed · 6 May 2026 View ↗ PDF 2404 00 00 100 REV PL04 PROPOSED GROUND FLOOR Plan - Proposed · 6 May 2026 View ↗ PDF 2404 00 00 201 REV PL04 PROPOSED SECTION A-A Plan - Proposed · 6 May 2026 View ↗ PDF 2404 02 00 301 REV PL03 PROPOSED ELEVATIONS Plan - Proposed · 6 May 2026 View ↗ PDF BIKE STORE LAYOUT REV.01 BIKE STORE LAYOUT Plan - Proposed · 29 Dec 2025 View ↗ PDF 2404 00 00 111 REV PL01 PROPOSED SITE PLAN Plan - Superseded · 13 Oct 2025 View ↗ PDF 2404 00 00 110 REV PL01 PROPOSED SITE PLAN Plan - Superseded · 13 Oct 2025 View ↗ PDF 2404 02 00 301 REV PL02 FABRIC REMOVAL ELEVATIONS Plan - Superseded · 13 Oct 2025 View ↗ PDF 2404 00 00 120 REV PL04 PROPOSED APARTMENT PLAN Plan - Proposed · 13 Oct 2025 View ↗ PDF 2404 00 00 301 REV PL03 PROPOSED ELEVATIONS Plan - Superseded · 13 Oct 2025 View ↗ PDF 2404 00 00 101 REV PL03 PROPOSED FIRST FLOOR PLAN Plan - Proposed · 13 Oct 2025 View ↗ PDF 2404 01 00 100 REV PL03 PROPOSED GROUND FLOOR PLAN Plan - Superseded · 13 Oct 2025 View ↗ PDF 2404 00 00 104 REV PL03 PROPOSED ROOF PLAN Plan - Proposed · 13 Oct 2025 View ↗ PDF 2404 00 00 102 REV PL02 PROPOSED SECOND FLOOR PLAN Plan - Proposed · 13 Oct 2025 View ↗ PDF 2404 00 00 201 REV PL03 PROPOSED SECTION AA Plan - Superseded · 13 Oct 2025 View ↗ PDF 2404 00 00 202 REV PL02 PROPOSED SECTIONS BB AND CC Plan - Proposed · 13 Oct 2025 View ↗ PDF 2404 00 00 103 REV PL02 PROPOSED THIRD FLOOR PLAN Plan - Proposed · 13 Oct 2025 View ↗

All documents on the council site ↗

Site constraints 16

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Bermondsey Street conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Article 4 direction
Central Activities Zone. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Southwark AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 21 m away: Thames Tideway Tunnel
The site is 21 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 16 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Scheduled monument 93 m away: Abbey buildings, Bermondsey
Its setting is a consideration for work nearby.
Nationally important archaeology protected by the Secretary of State. Work that affects the monument or its setting is rarely permitted.
Historic England ↗
19 listed buildings within 150 m
Nearest: 173, Bermondsey Street, Grade II, 26 m away · 1 Grade II*, 16 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 19 with distances
Historic England ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Wider setting of protected view 2A.1 Parliament Hill summit to St Paul's Cathedral; 3A.1 Kenwood viewing gazebo to St Paul's Cathedral; Radon affected area, class 2; Heritage at risk 74 m away: Church of St Mary Magdalene, Bermondsey Street, Bermondsey; Inside the Southwark built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Town centre 3 m away: London Bridge.
Not affected
Not green belt

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £2,900,000 in December 2017. Other property, freehold.

22 December 2017£2,900,000Recorded as a transfer outside a standard sale

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area369 m² (3,972 sq ft)
Energy ratingA (asset rating 15)
UseRestaurants and Cafes/Drinking Establishments/Takeaways
HeatingAir Conditioning

From the energy performance certificate lodged in October 2025, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Southwark - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Southwark
Application type
Minor application
Postcode
SE1 3TQ
Received
13 Oct 2025
Validated
14 Oct 2025
Ward
London Bridge & West Bermondsey
Parish
Bermondsey And Rotherhithe
Case officer
Show
Target decision
14 Jan 2026
Agent
Montagu Evans LLP
Freehold owner
Show

Decision outlook

Day 406, past the statutory target. 76% of full applications in Southwark are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 17 Nov 2026.

Day 406350 days past the 56-day target
55%decided within 8 weeks
88%approved
541decided in the last year

Plota live figures for full applications decided by Southwark in the last twelve months, from validation. Southwark decision record →

Public comments

6comments received
6 objecting

100% object · above the UK average of 74%

122 neighbours consulted · Last counted 17 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
8 Dec 2025
Env. assessment
No
Southwark
Planning Authority Score
7/10
Good
#64 of 296 overall
Relevant to this application:
Change of use

Southwark is faster than most councils at deciding householder applications: #54 of 296 on speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Southwark decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #93 of 296
95%
Householder approved
Above avg (90%) #92 of 296
78%
Decided in 8 weeks
Above avg (63%) #54 of 296
37%
Extended time limit
Below avg (41%) #122 of 296
92%
Minor dwellings approved
259 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
82%
Change of use approved
38 decided
1,622
Total decisions
132 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.

Freehold owner: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.