HALFWAY, Bethania, Llanon, Ceredigion, SY23 5NJ Data via plota.co.uk

A260543 - Full Planning In Progress

Proposal

Installation of ground-mounted solar photovoltaic development Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
12 Aug 2026
✓
Validated
25 Sept 2026
Decision
Expected by 20 Nov 2026

This application is under consideration - no decision has been issued yet. Plota predicts a decision between 20 Nov 2026 and 19 Dec 2026, from Ceredigion's recent full applications.

Site constraints 1

Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. A site survey can differ.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Not affected
Outside flood zones 2 and 3 · No scheduled monument at the site

Checked on 30 September 2026. Historic England, the Environment Agency, Natural England and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Ceredigion - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Ceredigion
Application type
Full Planning
Postcode
SY23 5NJ
Received
12 Aug 2026
Validated
25 Sept 2026
Case officer
Show
Target decision
20 Nov 2026
Decision level
Dirprwyedig / Delegated
Applicant
Show

Decision outlook

Day 10 of the 56-day target. Ceredigion usually decides full applications by day 58.

Day 1048 days to the predicted decision (day 58)
50%decided within 8 weeks
80%approved
9%go to committee

Plota live figures for full applications decided by Ceredigion in the last twelve months, from validation. Ceredigion decision record →

Consultation & key dates

Statutory expiry
20 Nov 2026