Planning decisions in Ceredigion
How long Ceredigion takes to decide a planning application and how many it approves, from the 840 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
55 daysmedian from validation to decision (UK 54); 56 from receipt
63%decided within eight weeks (UK 66%), 77% within thirteen
86%approved (UK 90%): 683 approved, 108 refused, 37 withdrawn
241 of 388UK rank for speed, down 130 places on last year; 312 of 388 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 70 | 45% | 82% | 229 | 254 of 359 |
| Discharge of conditions | 48 | 79% | 98% | 204 | 87 of 310 |
| Householder applications | 56 | 62% | 88% | 143 | 127 of 200 |
| Amendments | 30 | 71% | 93% | 75 | 60 of 356 |
| Lawful development certificates | 49 | 77% | 74% | 47 | 125 of 348 |
| Prior approvals | 19 | 100% | 71% | 47 | 20 of 340 |
| Listed building consent | 141 | 18% | 89% | 46 | 304 of 307 |
| Advertisement consent * | 43 | 100% | 88% | 18 | 10 of 320 |
| Outline applications * | 114 | 45% | 33% | 15 | 97 of 110 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 97% | 54 | 86% | 805 |
| Planning committee | 3% | 148 | 96% | 26 |
Where the register states how the decision was made. 9 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 55 | 58% | 94% | 359 |
| 2017 * | 84 | 22% | 100% | 71 |
| 2018 * | 53 | 59% | 92% | 272 |
| 2019 * | 174 | 2% | 98% | 54 |
| 2020 * | 31 | 66% | 87% | 102 |
| 2021 * | 130 | 0% | 91% | 37 |
| 2022 * | 57 | 49% | 87% | 72 |
| 2023 * | 43 | 61% | 88% | 60 |
| 2025 | 55 | 57% | 84% | 394 |
| 2026 so far | 57 | 50% | 87% | 574 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- TYNANT, Talybont, Ceredigion, SY24 5DNErection of a poultry unit including silos and all associated worksdue 22 Dec 2023
- Abermad Mansion Llanfarian, Aberystwyth, SY23 4ESConvert a Grade II* Listed building from a nursing home into residential accommodation.due 14 Oct 2025
- 11 Laura Place, Aberystwyth, Ceredigion, SY23 2AUProposal to affix a small connectorised block terminal (CBT) near to existing copper block on the wall of 11 Laura Place, Aberystwyth SY23 2due 26 Nov 2025
- YNYS EDWIN, Eglwys Fach, Machynlleth, Ceredigion, SY20 8TARefurbish and conversion of farmhouse. Demolition of workshop and dutch barndue 9 Dec 2025
- Plot 42, Dolymeillion, Land At Dolymeillion, Llanilar, Aberystwyth, SY24 4ANProposed new dwelling on vacant plotdue 21 Jan 2026
- Land Adj To Gwelfro Bryn Road, Aberaeron, Ceredigion, SA46 0JLProposed Open Market Dwellingdue 13 Feb 2026
- HIGHBURY HOUSE HOTEL Pendre, Cardigan, Ceredigion, SA43 1JUDischarge of condition 16 from planning permission A240436 (fire protection measures)due 23 Mar 2026
- Land Next To Parc Y Llyn Ferwig, SA43 1QAOutline Planning Application with all matters reserved for residential developmentdue 19 Apr 2026
Decided in the last three weeks
- Land North And West Of New Mill Road , New Mill Road, SA43 1NENon-Material Amendment of Planning Permission A240851.Approved26 Oct 2026
- WELSH ASSEMBLY GOVERNMENT OFFICE Rhodfa Padarn, Llanbadarn Fawr, Aberystwyth, Ceredigion, SY23 3URInstallation of Battery Energy Storage System (BESS) units, together with associated infrastructure, security enclosure and ancillary works.Approved23 Oct 2026
- RHEIDOL VIEW, Ponterwyd, Aberystwyth, Ceredigion, SY23 3JYSinlge storey side extension and first floor extension above existing kitchenApproved23 Oct 2026
- Plot 11, Station Road, Cardigan, SA43 3ADConstruction storage building (use class B8)Approved23 Oct 2026
- FFYNNON NEWYDD, Llwyndafydd, Llandysul, Ceredigion, SA44 6LAModification of S106 Agreement D1/909/90 Dated 24th June 1991Approved23 Oct 2026
- 3 Portland Road, Aberystwyth, Ceredigion, SY23 2NLInternal alterations to the ground floor shop and the conversion / change of use of the floor s above to provide 2 no. self contained resideApproved23 Oct 2026
- Car Park, Parc Y Llyn Retail Park Llanbadarn Fawr, Aberystwyth, SY23 3TLNon-material amendment to planning application A250432 (Condition 2 - substitute the approved elevation drawing with an updated drawing)Approved22 Oct 2026
- Glan Y Mor High Street, Borth, Ceredigion, Borth, SY24 5JDDischarge of condition 3 of planning permission A210849.Approved22 Oct 2026
Built nightly from Ceredigion's planning register. Ranks are among the 388 published councils. See planning applications in Ceredigion, or get alerts for Ceredigion.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.