Land Adjacent to Holly Bank Division Lane Lytham St Annes FY4 5EB Data via plota.co.uk

25/0708 - Permission in Principle Refused

Proposal

Permission in principle for erection of one dwelling Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
28 Nov 2025
✓
Validated
8 Dec 2025
✗
Refused
6 Feb 2026
Appeal
Not lodged

Refused on 6 Feb 2026 · Delegated · Last checked 3 Oct 2026

Site constraints 6

Green belt: Blackpool
Inappropriate development needs very special circumstances.
Green belt policy allows a short list of exceptions, such as limited extensions and replacement buildings. Anything else needs very special circumstances that clearly outweigh the harm. Some green belt land can count as grey belt, where it does not strongly serve the green belt's purposes. The council decides this in its green belt assessment or on each application, so we do not mark it here.
Read the government guidance ↗
In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
National infrastructure project about 156 m away: Morgan and Morecambe Offshore Wind Farms Transmission Assets
The site is about 156 m from the project boundary. Electricity line, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Inside the Blackpool built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 2, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Fylde - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Fylde
Application type
Permission in Principle
Postcode
FY4 5EB
Received
28 Nov 2025
Validated
8 Dec 2025
Ward
Wrea Green with Westby
Parish
Westby with Plumptons
Case officer
Show
Decision
Refused
Decision date
6 Feb 2026
Decision level
Delegated
Applicant
Show
Agent
PWA Planning

How this decision compares

Decided in 60 days from validation, 54 days faster than Fylde's median of 114 for outline applications. Refused, as 40% of outline applications here are.

10%decided within 8 weeks
60%approved
20%go to committee

Plota live figures for outline applications decided by Fylde in the last twelve months, from validation. Fylde decision record →

Consultation & key dates

Consultation
18 Dec 2025
Comments by
4 Jan 2026
Site or press notice
18 Dec 2025
Fylde
Planning Authority Score
5.3/10
Average
#130 of 296 councils
Relevant to this application:
Householder decisions

Fylde ranks #184 out of 296 councils for householder decision speed. 49% of applications have the time limit extended, above the 41% national average. Householder applications are more likely to be approved here than most councils, with a 98% approval rate vs 90% nationally.

More permissive than most councils
98% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Fylde decision statistics
Based on MHCLG data, the year to March 2026
96%
Overall approval rate
Above avg (87%) #11 of 296
98%
Householder approved
Above avg (90%) #17 of 296
60%
Decided in 8 weeks
Below avg (63%) #184 of 296
49%
Extended time limit
Above avg (41%) #220 of 296
79%
Minor dwellings approved
43 decided (1-9 homes)
100%
Major dwellings approved
9 decided (10+ homes)
100%
Change of use approved
28 decided
422
Total decisions
16 refused in the year to March 2026