Land To The West Of The A645 Camblesforth North Yorkshire Data via plota.co.uk

26/03325/DISCON - Discharge of Conditions Approved

Proposal

Discharge of condition 15 (gas) of approval Erection of 29 dwellings and associated infrastructure Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Jun 2026
✓
Consultation
7 Aug 2026
✓
Approved
1 Sept 2026

Approved on 1 Sept 2026 · Chief Planner · Last checked 1 Sept 2026

Associated applications 5

Site constraints 4

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Public footpath 16 m away
Matters where it crosses or adjoins the site: obstructing a path without a diversion order is an offence, and work cannot start until the order is confirmed.
Compiled from highway authority data, not the legal definitive map. A few authorities have not published, so no path shown is not proof there is none.
National infrastructure project 65 m away: Helios Renewable Energy Project
The site is 65 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Thorpe Marsh Gas Pipeline (decided, 1.1 km); Drax Bioenergy with Carbon Capture and Storage Project (decided, 1.5 km); Yorkshire and Humber CCS Cross Country Pipeline (decided, 1.5 km); White Rose Carbon Capture and Storage Project (decided, 1.6 km); East Yorkshire Solar Farm (decided, 1.7 km); East Coast Hydrogen Humber Pipeline (at pre-application, 374 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Selby - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Selby
Application type
Discharge of Conditions
Received
22 Jun 2026
Validated
22 Jun 2026
Ward
Camblesforth & Carlton
Parish
Camblesforth
Case officer
Show
Target decision
17 Aug 2026
Decision
Confirmation of discharge of conditions
Decision date
1 Sept 2026
Decision level
Chief Planner
Applicant
Show
Agent
Stantec

Public comments

No public comments yet.

Last counted 1 Sept 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15021615
Planning Portal ref
PP-15021615
Consultation
7 Aug 2026
Comments by
31 Aug 2026
Statutory expiry
17 Aug 2026
Env. assessment
No