Land At Lambcote Hill Farm Swinford Road Walcote Leicestershire Data via plota.co.uk

25/00550/OUT - Outline Application Approved

Proposal

Hybrid planning application consisting of full planning application for the erection and operation of an energy storage system including associated infrastructure, engineering works, and formation of vehicular access from highway; and outline planning application (with all matters reserved) for the erection and operation of a transmission substation with associated infrastructure, engineering works and internal access arrangements Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
15 Aug 2025
✓
Approved
18 Jun 2026

Approved on 18 Jun 2026 · Committee · Last checked 13 Oct 2026

Planning committee

Decided by Harborough Planning Committee on 16 Jun 2026, in a recorded vote.

Approved by 8 votes to 0

As officers recommended.

  • Residents and local representatives raised concerns about countryside industrialisation, safety, traffic, noise, heritage, ecology and visual impact.
  • The committee voted unanimously to approve the application, subject to conditions and a revised Skylark Mitigation Strategy condition.
Read how the committee decided The proposal, site, officers’ assessment, public views, committee debate, vote and decision conditions. Includes the meeting recording, from 1:55:52 where this application was taken

Source: Plota analysis of Harborough's committee minutes of 16 Jun 2026.

Documents 144

Statements & assessments 52

PDF BNG METRIC 002A Supporting Information · 16 Jun 2026 View ↗ PDF BNG DESIGN STAGE REPORT Supporting Information · 16 Jun 2026 View ↗ PDF ECOLOGICAL IMPACT ASSESSMENT 004 B Supporting Information · 16 Jun 2026 View ↗ PDF LCC ECOLOGY Consultation Response · 15 Jun 2026 View ↗ PDF LCC ECOLOGY Consultation Response · 15 Jun 2026 View ↗ PDF HABITAT CONDITION ASSESSMENT SHEET Supporting Information · 10 Jun 2026 View ↗ PDF HABITAT CONDITION ASSESSMENT SHEET (INDIVIDUAL TREES) Supporting Information · 10 Jun 2026 View ↗ PDF LCC ECOLOGY Consultation Response · 5 Jun 2026 View ↗ PDF LEAD LOCAL FLOOD AUTHORITY Consultation Response · 4 Jun 2026 View ↗ PDF ECOLOGICAL IMPACT ASSESSMENT Supporting Information · 18 May 2026 View ↗ PDF FLOOD RISK ASSESSMENT * ONLINE DRAINAGE STRATEGY Supporting Information · 18 May 2026 View ↗ PDF DEFRA STATUTORY BIODIVERSITY METRIC Supporting Information · 18 May 2026 View ↗ PDF HABITAT CONDITION ASSESSMENT SHEETS Supporting Information · 18 May 2026 View ↗ PDF HABITAT CONDITION ASSESSMENT SHEETS (2) Supporting Information · 18 May 2026 View ↗ PDF BNG DESIGN STAGE REPORT Supporting Information · 18 May 2026 View ↗ PDF PLANNING, DESIGN AND ACCESS STATEMENT Supporting Information · 18 May 2026 View ↗ PDF LCC LEAD LOCAL FLOOD AUTHORITY Consultation Response · 2 Apr 2026 View ↗ PDF LCC ECOLOGY Consultation Response · 12 Mar 2026 View ↗ PDF LCC LEAD LOCAL FLOOD AUTHORITY Consultation Response · 12 Mar 2026 View ↗ PDF REVISED FLOOD RISK ASSESSMENT Supporting Information · 27 Feb 2026 View ↗ PDF ARBORICULTURAL IMPACT ASSESSMENT & METHOD STATEMENT FEB 2026 Supporting Information · 25 Feb 2026 View ↗ PDF HERITAGE STATEMENT FEBRUARY 2026 Heritage Report · 13 Feb 2026 View ↗ PDF BNG DESIGN REPORT REV B FEB 2026 Supporting Information · 13 Feb 2026 View ↗ PDF LVIA VISUAL ASSESSMENT TABLES UPDATE FEB 2026 Supporting Information · 13 Feb 2026 View ↗ PDF BIODIVERSITY METRIC - REV A Supporting Information · 13 Feb 2026 View ↗ PDF SUPERSEDED - FLOOD RISK ASSESSMENT Flood Risk Assessment · 13 Feb 2026 View ↗ PDF ECOLOGICAL IMPACT ASSESSMENT REV A FEBRUARY 2026 Ecology Survey · 13 Feb 2026 View ↗ PDF TRANSPORT ADDENDUM JAN 2026 Highways Report · 21 Jan 2026 View ↗ PDF FLOOD CONSUTLATION - DATE EXTENDED Correspondence · 29 Sept 2025 View ↗ PDF EMAIL WITH ECOLOGY RESPONSE Correspondence · 26 Sept 2025 View ↗ PDF LCC ECOLOGY Consultation Response · 26 Sept 2025 View ↗ PDF LCC LEAD LOCAL FLOOD AUTHORITY Consultation Response · 25 Sept 2025 View ↗ PDF VERIFICATION COMPLIANCE REPORT SWINFORD ENERGY PARK_VERS1.0 (1) Supporting Information · 15 Aug 2025 View ↗ PDF UXO RISK ASSESSMENT (20250123_10292_ENDERBY ENERGY LTD_SWINFORD ENERGY PARK_DETA Supporting Information · 15 Aug 2025 View ↗ PDF TRANSPORT STATEMENT (CRM.3098.002.TR.RP.002.A) Supporting Information · 15 Aug 2025 View ↗ PDF STATEMENT OF COMMUNITY INVOLVEMENT Supporting Information · 15 Aug 2025 View ↗ PDF PRELIMINARY ECOLOGICAL APPRAISAL - SUPERSEDED Ecology Survey · 15 Aug 2025 View ↗ PDF PLANNING, DESIGN & ACCESS STATEMENT (CRM.3098.002.PL.R.001) Design & Access Statement · 15 Aug 2025 View ↗ PDF NOISE IMPACT ASSESSMENT (REF. U1261-HIM-ZZ-RP-EN-0001_SWINFORD NIA_P02.1) Supporting Information · 15 Aug 2025 View ↗ PDF HERITAGE STATEMENT - SUPERSEDED Supporting Information · 15 Aug 2025 View ↗ PDF GEOENVIRONMENTAL PRELIMINARY RISK ASSESSMENT (CRM.3098.002.GE.R001) Supporting Information · 15 Aug 2025 View ↗ PDF FLOOD RISK ASSESSMENT & DRAINAGE STRATEGY - SUPERSEDED Flood Risk Assessment · 15 Aug 2025 View ↗ PDF ECONOMICS IMPACT ASSESSMENT Supporting Information · 15 Aug 2025 View ↗ PDF BNG METRIC - SUPERSEDED Supporting Information · 15 Aug 2025 View ↗ PDF BNG CONDITION ASSESSMENT - PROPOSED Supporting Information · 15 Aug 2025 View ↗ PDF BNG CONDITION ASSESSMENT - BASELINE Supporting Information · 15 Aug 2025 View ↗ PDF BIODIVERSITY NET GAIN CALCULATION (CRM.3098.002.EC.R.002) Supporting Information · 15 Aug 2025 View ↗ PDF ARBORICULTURAL SURVEY REPORT (3098.002.ENZ.XX.00.RP.AR.45.101.PL03) Supporting Information · 15 Aug 2025 View ↗ PDF ARBORICULTURAL IMPACT ASSESSMENT AND METHOD STATEMENT - SUPERSEDED Supporting Information · 15 Aug 2025 View ↗ PDF LVIA TOPOGRAPHY AND DRAINAGE PLAN - FIGURE 1 CRM3098002-ENZ-XX-XX-M2-L-0001 Supporting Information · 15 Aug 2025 View ↗ PDF LVIA VIEWPOINT ASSESSMENT TABLES SUPERSEDED Supporting Information · 15 Aug 2025 View ↗ PDF BNG DESIGN STAGE REPORT - SUPERSEDED Supporting Information · 15 Aug 2025 View ↗

Consultation & comments 47

PDF LCC ARCHAEOLOGY Consultation Response · 5 Jun 2026 View ↗ PDF NODE (COUNCIL'S LANDSCAPE ARCHITECT CONSULTANT) Consultation Response · 29 Apr 2026 View ↗ PDF CONSERVATION OFFICER Consultation Response · 20 Apr 2026 View ↗ PDF NATIONAL HIGHWAYS - FINAL Consultation Response · 10 Apr 2026 View ↗ PDF LCC HIGHWAYS Consultation Response · 24 Mar 2026 View ↗ PDF APPLICANT'S RESPONSE TO NATIONAL HIGHWAYS Supporting Information · 20 Mar 2026 View ↗ PDF APPLICANT'S RESPONSE TO LLFA Supporting Information · 19 Mar 2026 View ↗ PDF NATIONAL HIGHWAYS Consultation Response · 9 Mar 2026 View ↗ PDF LCC FORESTRY Consultation Response · 2 Mar 2026 View ↗ PDF HYDROLOGY/RESPONSE TO LLFA Supporting Information · 13 Feb 2026 View ↗ PDF NATIONAL HIGHWAYS COMMENT ON TECHNICAL ADDENDUM Consultation Response · 12 Feb 2026 View ↗ PDF NATIONAL GRID- FINAL Consultation Response · 16 Dec 2025 View ↗ PDF NATIONAL HIGHWAYS Consultation Response · 9 Dec 2025 View ↗ PDF TREE OFFICER Consultation Response · 3 Dec 2025 View ↗ PDF LCC FORESTRY ADDITIONAL COMMENT Consultation Response · 3 Dec 2025 View ↗ PDF SEVERN TRENT Consultation Response · 21 Oct 2025 View ↗ PDF FIRE OFFICER Consultation Response · 21 Oct 2025 View ↗ PDF LCC HIGHWAYS Consultation Response · 6 Oct 2025 View ↗ PDF NATIONAL GAS Consultation Response · 25 Sept 2025 View ↗ PDF HISTORIC ENGLAND Consultation Response · 24 Sept 2025 View ↗ PDF FROM APPLICANT RESPONSE TO NATIONAL GRID Supporting Information · 23 Sept 2025 View ↗ PDF WEST NORTHANTS COUNCIL Consultation Response · 22 Sept 2025 View ↗ PDF HDC ENVIRONMENTAL HEALTH OFFICER Consultation Response · 19 Sept 2025 View ↗ PDF STANFORD ON AVON PARISH Consultation Response · 18 Sept 2025 View ↗ PDF AGENT'S RESPONSE TO LETTER FROM MP Correspondence · 15 Sept 2025 View ↗ PDF AGENT RE HSE CONSULTATION RESPONSE Correspondence · 11 Sept 2025 View ↗ PDF NATIONAL GRID Consultation Response · 11 Sept 2025 View ↗ PDF NATIONAL GRID Consultation Response · 11 Sept 2025 View ↗ PDF NATIONAL GRID Consultation Response · 11 Sept 2025 View ↗ PDF NATIONAL GRID Consultation Response · 11 Sept 2025 View ↗ PDF NATURAL ENGLAND GENERAL ADVICE Consultation Response · 11 Sept 2025 View ↗ PDF NATURAL ENGLAND Consultation Response · 11 Sept 2025 View ↗ PDF HDC NEIGHBOURHOOD AND GREEN SPACES OFFICER Consultation Response · 10 Sept 2025 View ↗
PDF Objector’s name hidden Show Objection Comment · 10 Sept 2025 View ↗
PDF CONSULTATION RESPONSE Consultation Response · 10 Sept 2025 View ↗ PDF NATIONAL HIGHWAYS Consultation Response · 9 Sept 2025 View ↗ PDF NATIONAL GAS Consultation Response · 4 Sept 2025 View ↗ PDF HEALTH & SAFETY EXECUTIVE Consultation Response · 3 Sept 2025 View ↗ PDF ENVIRONMENT AGENCY Consultation Response · 2 Sept 2025 View ↗ PDF DESIGNING OUT CRIME OFFICER Consultation Response · 2 Sept 2025 View ↗ PDF ACTIVE ENGLAND Consultation Response · 1 Sept 2025 View ↗ PDF HDC ENVIRONMENTAL SERVICES Consultation Response · 1 Sept 2025 View ↗ PDF LCC PLANNING OBLIGATIONS Consultation Response · 29 Aug 2025 View ↗ PDF NATS SAFEGUARDING Consultation Response · 28 Aug 2025 View ↗ PDF ANGLIAN WATER Consultation Response · 28 Aug 2025 View ↗ PDF EAST MIDLANDS AIRPORT Consultation Response · 28 Aug 2025 View ↗ PDF NATIONAL GAS - HOLDING OBJECTION Consultation Response · 28 Aug 2025 View ↗

Other documents 33

PDF [VALUES VARY] - SUPERSEDED Supporting Information · 10 Jun 2026 View ↗ PDF [VALUES VARY] - SUPERSEDED Supporting Information · 10 Jun 2026 View ↗ PDF [VALUES VARY] - SUPERSEDED Supporting Information · 10 Jun 2026 View ↗ PDF INTERIM TRIAL TRENCHING REPORT V2 APRIL 2026 Archaeological Report · 8 Jun 2026 View ↗ PDF PO/AGENT RE FIREWATER STORAGE Correspondence · 2 Jun 2026 View ↗ PDF LANDSCAPE MITIGATION STRATEGY Supporting Information · 18 May 2026 View ↗ PDF ADDITIONAL HABITAT PHOTOGRAPHS Supporting Information · 18 May 2026 View ↗ PDF VIEWPOINT 1 PHOTOMONTAGES (UPDATED) Supporting Information · 18 May 2026 View ↗ PDF VOLUME CALCULATIONS (SURFACE WATER) Supporting Information · 19 Mar 2026 View ↗ PDF LANDSCAPE MITIGATION STRATEGY REV P03 Supporting Information · 13 Feb 2026 View ↗ PDF VIEWPOINT SHEETS (9-16) UPDATE Supporting Information · 13 Feb 2026 View ↗ PDF VIEWPOINT SHEETS (1-8) UPDATE Supporting Information · 13 Feb 2026 View ↗ PDF SWINFORD LANDSCAPE UPDATE COVERING NOTE FEB 2026 Supporting Information · 13 Feb 2026 View ↗ PDF OHL OVERLAY 2 FROM APPLICANT Supporting Information · 9 Dec 2025 View ↗ PDF AGREEMENT IN PRINCIPLE NATIONAL HIGHWAYS (ABNORMAL LOAD) Supporting Information · 27 Nov 2025 View ↗ PDF AGRICULTURAL LAND CLASSIFICATION REPORT (P252137) Supporting Information · 15 Aug 2025 View ↗ PDF LVIA VIEWPOINT SHEETS - SUPERSEDED-XX-DR-L-00-001-00 Supporting Information · 15 Aug 2025 View ↗ PDF LVIA FIGURE 2.1 CRM3098002-ENZ-XX-XX-M2-L-0002.1-ZTV (WITHOUT SUBSTATION) Supporting Information · 15 Aug 2025 View ↗ PDF LVIA FIGURE 2 CRM3098002-ENZ-XX-XX-M2-L-0002-ZTV (WITH SUBSTATION) Supporting Information · 15 Aug 2025 View ↗ PDF LVIA CONTEXTUAL VIEWPOINT SHEETS - FIGURE 18-22 SUPERSEDED Supporting Information · 15 Aug 2025 View ↗ PDF LVIA REPORT - CRM3098002.001.LA.R.001.01 Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 8 PROPOSED YEAR 15 Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 8 PROPOSED Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 8 EXISTING Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 7 PROPOSED YEAR 15 Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 7 PROPOSED Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 7 EXISTING Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 3 PROPOSED YEAR 15 Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 3 PROPOSED Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINE VP 3 EXISTING Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINES KEY Supporting Information · 15 Aug 2025 View ↗ IMG WIRELINES KEY (INCLUDING PLANTING) Supporting Information · 15 Aug 2025 View ↗ PDF LANDSCAPE MITIGATION STRATEGY SUPERSEDED Supporting Information · 15 Aug 2025 View ↗

All documents on the council site ↗

Site constraints 2

Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Radon affected area, class 5
An estimated 10 to 30% of homes reach the radon action level. Indicative for the 1 km square, which takes the highest class found in it; a radon test gives the answer for a building.
From the British Geological Survey and UK Health Security Agency indicative atlas. Under building regulations, as the BRE guide BR 211 (2023) sets out, new buildings and extensions need basic radon protection from class 3 in England and Wales and from class 2 in Scotland, and full protection from class 5. The class at the site itself, from the detailed BGS map, decides which.
UKHSA radon ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Looking for land for battery storage?

Plota Sites searches every land parcel in England and Wales: 9,119 sites fit this search. On and off the market, free to search.

Land for battery storage
Work with planning data?

Every application in Harborough - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Harborough
Application type
Outline Application
Received
15 Aug 2025
Validated
15 Aug 2025
Ward
Misterton
Parish
Westrill And Starmore
Case officer
Show
Target decision
14 Nov 2025
Decision
Approve
Decision date
18 Jun 2026
Decision level
Committee
Applicant
Show

How this decision compares

Decided in 307 days from validation, 251 days slower than Harborough's median of 56 for outline applications. Approved, as 26% of outline applications here are.

52%decided within 8 weeks
26%approved
24%go to committee

Plota live figures for outline applications decided by Harborough in the last twelve months, from validation. Harborough decision record →

Public comments

10comments received
4 objecting6 supporting

60% support · above the UK average of 16%

33 neighbours consulted · Last counted 13 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Comments by
4 Jun 2026
Committee
16 Jun 2026
Statutory expiry
14 Nov 2025
Env. assessment
No
Harborough
Planning Authority Score
4.2/10
Below average
#187 of 296 overall
Relevant to this application:
Major dwellings

Harborough is slower than most councils at deciding householder applications: #230 of 296 on speed. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Harborough decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #131 of 296
92%
Householder approved
Above avg (90%) #155 of 296
51%
Decided in 8 weeks
Below avg (63%) #230 of 296
38%
Extended time limit
Below avg (41%) #128 of 296
74%
Minor dwellings approved
96 decided (1-9 homes)
67%
Major dwellings approved
12 decided (10+ homes)
76%
Change of use approved
50 decided
814
Total decisions
90 refused in the year to March 2026