Brody House, Strype Street, London E1 7LQ Data via plota.co.uk

PA/26/01740/NC - Full Planning Permission Registered

Proposal

Removal of the existing non-compliant cladding materials, replacement with compliant insulated render and cladding materials, replacement windows and associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 15 Oct 2026
✓
Consultation
9 Nov 2026
Decision
Expected by 10 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision around 10 Dec 2026, from Tower Hamlets's recent extensions.

Comments are open until 30 Nov 2026

Comment on this application ↗

Documents 17

All documents on the council site ↗

Site constraints 11

Wentworth Street conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Heritage at risk: Wentworth Street, Bethnal Green
On the register of historic places assessed as at risk.
A designated building, monument, park or conservation area assessed as at risk from neglect, decay or development. Proposals that secure its future are looked on favourably.
Historic England ↗
Archaeological priority area: Tower Hamlets APA 2.12
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
National infrastructure project about 824 m away: Thames Tideway Tunnel
The site is about 824 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 300 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
19 listed buildings within 150 m of the postcode pin; Inside the Tower Hamlets built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Town centre about 70 m away: Wentworth Street.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 7 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
E1 7LQ
Received
around 15 Oct 2026
Validated
15 Oct 2026
Ward
Spitalfields and Banglatown
Case officer
Show
Target decision
10 Dec 2026
Decision level
Delegated
Applicant
Show
Agent
Ingleton Wood
Leaseholder
Show

Decision outlook

Day 39 of the 56-day target. Tower Hamlets usually decides extensions by day 56.

Day 3917 days to the 56-day target
66%decided within 8 weeks
90%approved
402decided in the last year

Plota live figures for extensions decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Neighbours
9 Nov 2026
Consultation
9 Nov 2026
Comments by
30 Nov 2026
Site or press notice
19 Nov 2026
Statutory expiry
10 Dec 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 overall
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications: #207 of 296 on speed. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026