10 Victoria Street London SW1H 0NN Data via plota.co.uk

25/07754/EIASCR - EIA Screening Opinion Approved

Proposal

Request for a screening opinion under Regulation 6 of the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (as amended) for the demolition of existing buildings to ground floor, retention of basement, and erection of replacement building of up to 13 storeys (plus two storeys of basement), to provide 25,000 sqm building comprising active ground floor Class E uses and upper floor Class E offices (site includes 10-18 and 20 Victoria Street). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
27 Oct 2025
✓
Approved
13 Feb 2026

Approved on 13 Feb 2026 · Delegated Decision · Last checked 17 Oct 2026

Site constraints 14

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
2 Article 4 directions
Article 4 Basement Development Permitted Rights Removed · Article 4 Direction Class E To C3 In Central Activities Zone. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area: City of Westminster APA 2.8
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Westminster AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 382 m away: Thames Tideway Tunnel
The site is 382 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 547 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Conservation area 33 m away: Broadway And Christchurch Gardens; Registered park or garden 126 m away: Palace of Westminster, Westminster Abbey and St. Margaret's Church; 9 listed buildings within 150 m; Inside the City of Westminster built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Town centre 38 m away: Victoria Street.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area6,058 m² (65,208 sq ft)
Energy ratingE (asset rating 117)
UseOffices and Workshop Businesses
HeatingAir Conditioning

From the energy performance certificate lodged in April 2023, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Westminster - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
EIA Screening Opinion
Postcode
SW1H 0NN
Received
27 Oct 2025
Validated
27 Oct 2025
Ward
St James's
Case officer
Show
Target decision
17 Nov 2025
Decision
Not required
Decision date
13 Feb 2026
Decision level
Delegated Decision
Applicant
Show
Agent
Montagu Evans

How this decision compares

Decided in 109 days from validation, 89 days slower than Westminster's median of 20 for eia screening and scoping opinions. Approved, as 97% of eia screening and scoping opinions here are.

86%decided within 8 weeks
97%approved
2,099decided in the last year

Plota live figures for eia screening and scoping opinions decided across the UK in the last twelve months, from validation; too few recent eia screening and scoping opinions in Westminster to go on. Westminster decision record →

Public comments

No public comments yet.

Last counted 17 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Env. assessment
No
Westminster
Planning Authority Score
3.5/10
Below average
#221 of 296 overall
Relevant to this application:
Householder decisions

Westminster is slower than most councils at deciding householder applications: #258 of 296 on speed. Only 28% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Westminster is also one of the strictest councils - it refuses more householder applications than almost any other, with only 81% approved vs 90% nationally.

One of the strictest councils
only 81% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Westminster decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #201 of 296
81%
Householder approved
Below avg (90%) #277 of 296
44%
Decided in 8 weeks
Below avg (63%) #258 of 296
28%
Extended time limit
Below avg (41%) #46 of 296
83%
Minor dwellings approved
12 decided (1-9 homes)
67%
Major dwellings approved
3 decided (10+ homes)
81%
Change of use approved
133 decided
4,602
Total decisions
648 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use