West Market Building London Central Markets London EC1A 9PS Data via plota.co.uk

25/01221/LBC - Listed Building Consent Approved

Proposal

Installation and display of four LED resin coated screens of 5.75m height, 3.5m width, and 0.04m depth, on the facade of the Poultry Market Building in West Poultry Avenue, and associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
4 Sept 2025
✓
Consultation
22 Sept 2025
✓
Approved
13 Nov 2025

Approved on 13 Nov 2025 · Delegated Decision · Last checked 16 Nov 2026

Documents 22

All documents on the council site ↗

Associated applications 3

Site constraints 10

31 listed buildings within 150 m of the postcode pin
Nearest: East building of Central Market, Grade II*, the postcode pin is inside its outline · 1 Grade I, 4 Grade II*, 26 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 31 with distances
Historic England ↗
Smithfield conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: City of London AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 563 m away: Thames Tideway Tunnel
The site is about 563 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 759 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
Also on the record
Wider setting of protected view 1A.2 Alexandra Palace viewing terrace to St Paul's Cathedral; Inside the City and County of the City of London built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Town centre about 60 m away: Farringdon.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in City of London - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Listed Building Consent
Postcode
EC1A 9PS
Received
4 Sept 2025
Validated
4 Sept 2025
Ward
Farringdon Without
Case officer
Show
Target decision
30 Oct 2025
Decision
Approved
Decision date
13 Nov 2025
Decision level
Delegated Decision
Applicant
Show
Agent
Newmark

How this decision compares

Decided in 70 days from validation, about the council's usual 73 days. Approved, as 100% of listed building works here are.

27%decided within 8 weeks
100%approved
149decided in the last year

Plota live figures for listed building works decided by City of London in the last twelve months, from validation. City of London decision record →

Public comments

No public comments yet.

Last counted 16 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14288418
Planning Portal ref
PP-14288418
Consultation
22 Sept 2025
Comments by
21 Oct 2025
Site or press notice
25 Sept 2025
Committee
13 Nov 2025
Statutory expiry
30 Oct 2025
Env. assessment
No
City of London
Planning Authority Score
6.7/10
Good
#71 of 296 councils
Relevant to this application:
Other decisions

City of London is one of the fastest councils in England for householder decisions, ranking #1 out of 296. The council extends the time limit on 84% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 100% approval rate vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
City of London decision statistics
Based on MHCLG data, the year to March 2026
97%
Overall approval rate
Above avg (87%) #3 of 296
100%
Householder approved
Above avg (90%) #1 of 296
100%
Decided in 8 weeks
Above avg (63%) #1 of 296
84%
Extended time limit
Above avg (41%) #296 of 296
50%
Minor dwellings approved
4 decided (1-9 homes)
91%
Change of use approved
22 decided
460
Total decisions
14 refused in the year to March 2026