Land In The North West Part Of The St Johns Innovation Park Cowley Road Milton Cambridge Cambridgeshire Data via plota.co.uk

20/03523/COND24 - Condition request Decided

Proposal

Submission of details required by condition 24 (surface water drainage) of planning permission Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Dec 2025
✓
Discharge Condition in Part
29 Jan 2026

Discharge Condition in Part on 29 Jan 2026 · Delegated (Condition) · Last checked 2 Oct 2026

Documents 27

Statements & assessments 17

PDF DRAINAGE Consultee Comments · 15 Jan 2026 View ↗ PDF LOCAL LEAD FLOOD AUTHORITY COMMENTS Consultee Comments · 9 Jan 2026 View ↗ PDF FLOOD RISK ASSESSMENT Application Survey / Assessment / Statement · 22 Dec 2025 View ↗ PDF DRAINAGE REPORT (PAGE 1-50) Application Information · 22 Dec 2025 View ↗ PDF DRAINAGE REPORT (PAGE 51-100) Application Information · 22 Dec 2025 View ↗ PDF DRAINAGE REPORT (PAGE 101-150) Application Information · 22 Dec 2025 View ↗ PDF DRAINAGE REPORT (PAGE 151-187) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART1 (PAGE 1-50) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART1 (PAGE 51-100) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART1 ( PAGE 101-150) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART2 (PAGE 1-50) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART1 ( PAGE 151-200) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART1 (PAGE 201-230) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART2 (PAGE 51-100) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART2 (PAGE 101-150) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART2 (PAGE 151-200) Application Information · 22 Dec 2025 View ↗ PDF SJIP GEO AND CONTAMINATION (R02)-PART2 (PAGE 201-230) Application Information · 22 Dec 2025 View ↗

All documents on the council site ↗

Associated applications 5

Site constraints 2

National infrastructure project: Cambridge Waste Water Treatment Plant Relocation
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: A14 Cambridge to Huntingdon Improvement Scheme (decided, about 476 m); East West Rail - Bedford to Cambridge and Western improvements (at pre-application, about 549 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Cambridge (Cambridge) built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Cambridge - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Cambridge
Application type
Condition request
Received
22 Dec 2025
Validated
22 Dec 2025
Ward
Milton & Waterbeach
Parish
Milton CP
Case officer
Show
Target decision
16 Feb 2026
Decision
Discharge Condition in Part
Decision date
29 Jan 2026
Decision level
Delegated (Condition)
Agent
Savills (UK) Ltd

Public comments

No public comments yet.

Last counted 2 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
16 Feb 2026
Env. assessment
No
Cambridge
Planning Authority Score
8.3/10
Excellent
#18 of 296 overall
Relevant to this application:
Householder decisions

Cambridge is one of the fastest councils in England for householder decisions: #21 of 296 on speed. Only 26% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly more likely to be approved here (94%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Cambridge decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #108 of 296
94%
Householder approved
Above avg (90%) #100 of 296
86%
Decided in 8 weeks
Above avg (63%) #21 of 296
26%
Extended time limit
Below avg (41%) #34 of 296
74%
Minor dwellings approved
86 decided (1-9 homes)
80%
Major dwellings approved
5 decided (10+ homes)
80%
Change of use approved
41 decided
1,014
Total decisions
100 refused in the year to March 2026