International Quarter London North Celebration Avenue Stratford London E20 1DB Data via plota.co.uk

Proposal

Full planning permission for the continued temporary use of the site for a period of 5 years for mixed-use meanwhile uses comprising Use Classes E, F1 and F2, and Sui Generis uses, including community, training, café, transport hub and associated activities, together with the retention and erection of associated temporary structures and infrastructure including shipping containers, portacabins, signage, hoarding and access gates. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Jun 2026
✓
Approved
14 Aug 2026

Approved on 14 Aug 2026 · Delegated decision · Last checked 21 Aug 2026

Documents 22

All documents on the council site ↗

Site constraints 8

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. A site survey can differ.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Air quality management area: Newham AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: Stratford
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
National infrastructure project 926 m away: Thames Tideway Tunnel
The site is 926 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Radon affected area, class 2; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Newham - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Newham
Application type
Full Planning Permission
Postcode
E20 1DB
Received
22 Jun 2026
Validated
22 Jun 2026
Ward
Stratford Olympic Park
Parish
Stratford Community Forum
Case officer
Show
Decision
Approve
Decision date
14 Aug 2026
Decision level
Delegated decision
Applicant
Show
Agent
Deloitte

How this decision compares

Decided in 53 days from validation, about the council's usual 56 days. Approved, as 40% of changes of use here are.

67%decided within 8 weeks
40%approved
121decided in the last year

Plota live figures for changes of use decided by Newham in the last twelve months, from validation. Newham decision record →

Public comments

2comments received
1 neutral1 supporting

Last counted 21 Aug 2026

Read the comments on the council site ↗

Consultation & key dates

Env. assessment
No
Newham
Planning Authority Score
3.7/10
Below average
#211 of 296 councils
Relevant to this application:
Householder decisions

Newham ranks #191 out of 296 councils for householder decision speed. Householder applications are slightly less likely to be approved here (87%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Newham decision statistics
Based on MHCLG data, the year to March 2026
83%
Overall approval rate
Below avg (87%) #239 of 296
87%
Householder approved
Below avg (90%) #233 of 296
59%
Decided in 8 weeks
Below avg (63%) #191 of 296
39%
Extended time limit
Below avg (41%) #140 of 296
51%
Minor dwellings approved
67 decided (1-9 homes)
100%
Major dwellings approved
2 decided (10+ homes)
59%
Change of use approved
51 decided
989
Total decisions
170 refused in the year to March 2026