School House Sir John Lillie Primary School Lillie Road London SW6 7LN Data via plota.co.uk

2025/02918/FR3 - Full Regulation 3 - LBHF is Developer REGISTERED: Pending recommendation

Proposal

Conversion and refurbishment of existing School Keepers Lodge to create 2no. self-contained residential flats; replacement of all single glazed windows with double glazed windows to match existing; formation of a new external gateway with new fence to match existing along the Lillie Road frontage; relocation of the side fence of the rear garden of the Lodge in order to enlarge the existing School Car Park; installation of new timber fences and a new steel mesh fence in order to isolate the new entrances into the residential building and safeguard the School access from Lillie Road. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
20 Oct 2025
✓
Validated
4 Dec 2025
Decision
Target date was 29 Jan 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 6 Nov 2026; it is now day 337.

The consultation period closed on 29 Jan 2026.

Site constraints 5

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Air quality management area: Hammersmith and Fulham AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 414 m away: Thames Tideway Tunnel
The site is 414 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Hammersmith and Fulham built-up area; Public transport access: PTAL 3 (moderate), TfL 2023, for the 100 m square.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Hammersmith and Fulham - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Regulation 3 - LBHF is Developer
Postcode
SW6 7LN
Received
20 Oct 2025
Validated
4 Dec 2025
Ward
Munster
Case officer
Show
Applicant
Show
Agent
Mike Raubenheimer / Bryan Packman Marcel

Decision outlook

Day 337, past the statutory target. 62% of full applications in Hammersmith and Fulham are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 2 Nov 2026.

Day 337281 days past the 56-day target
28%decided within 8 weeks
98%approved
758decided in the last year

Plota live figures for full applications decided by Hammersmith and Fulham in the last twelve months, from validation. Hammersmith and Fulham decision record →

Consultation & key dates

Consultation
5 Dec 2025
Comments by
29 Jan 2026
Site or press notice
17 Dec 2025
Hammersmith and Fulham
Planning Authority Score
3.7/10
Below average
#210 of 296 councils
Relevant to this application:
Householder decisions

Hammersmith and Fulham is one of the slowest councils in England for householder decisions, ranking #281 out of 296. The council extends the time limit on 63% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 99% approval rate vs 90% nationally.

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Hammersmith and Fulham decision statistics
Based on MHCLG data, the year to March 2026
95%
Overall approval rate
Above avg (87%) #20 of 296
99%
Householder approved
Above avg (90%) #4 of 296
33%
Decided in 8 weeks
Below avg (63%) #281 of 296
63%
Extended time limit
Above avg (41%) #275 of 296
97%
Minor dwellings approved
209 decided (1-9 homes)
100%
Major dwellings approved
1 decided (10+ homes)
92%
Change of use approved
37 decided
1,321
Total decisions
60 refused in the year to March 2026