St Peter's Vicarage, St Peter's Terrace,London, SW6 7JS Data via plota.co.uk

REGISTERED P/2026/02846/TPO - Work to TPO'd Tree
Date received
30 Oct 2026
Date validated
4 Nov 2026
Postcode
SW6 7JS
Type
Work to TPO'd Tree

Description

Pruning of a London Plane Tree (T5) and Lime Tree (T6), subject to Tree Preservation Order . Data via plota.co.uk

Last checked

Decision outlook

Plota predicts a decision around 30 Dec 2026, from Hammersmith and Fulham's recent tree and landscaping works.

Day 2 of the 56-day target. Hammersmith and Fulham usually decides tree and landscaping works by day 56.

Day 254 days to the 56-day target
75%decided within 8 weeks
96%approved
75decided in the last year

Plota live figures for tree and landscaping works decided by Hammersmith and Fulham in the last twelve months, from validation. Hammersmith and Fulham decision record →

Site constraints 7

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Central Fulham conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Air quality management area: Hammersmith and Fulham AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 620 m away: Thames Tideway Tunnel
The site is about 620 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
1 listed building within 150 m of the postcode pin; Inside the Hammersmith and Fulham built-up area; Public transport access: PTAL 2 (poor), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 5 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Hammersmith and Fulham - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service
Hammersmith and Fulham
Planning Authority Score
3.7/10
Below average
#210 of 296 councils
Relevant to this application:
Householder decisions

Hammersmith and Fulham is one of the slowest councils in England for householder decisions, ranking #281 out of 296. The council extends the time limit on 63% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 99% approval rate vs 90% nationally.

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Hammersmith and Fulham decision statistics
Based on MHCLG data, the year to March 2026
95%
Overall approval rate
Above avg (87%) #20 of 296
99%
Householder approved
Above avg (90%) #4 of 296
33%
Decided in 8 weeks
Below avg (63%) #281 of 296
63%
Extended time limit
Above avg (41%) #275 of 296
97%
Minor dwellings approved
209 decided (1-9 homes)
100%
Major dwellings approved
1 decided (10+ homes)
92%
Change of use approved
37 decided
1,321
Total decisions