St Cuthberts House Sidmouth Road Gateshead NE9 6US Data via plota.co.uk

Proposal

Change of Use from a Care Home (Use Class C2) and 2no. Residential Units (Use Class C3) to a Day Nursery (Use Class E (f)); widening of vehicle access; construction of link infill extension on east elevation, a new aluminium framed double glazed screen with doors and a raise platform on the west elevation, metal steps at the eastern part of the site; and retrospective demolition of single storey offshoot on eastern elevation, outbuildings, garages and a conservatory and the levelling and hardcoring of land at the northern part of the site. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
16 Feb 2026
✓
Validated
15 Sept 2026
Decision
Expected by 10 Nov 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 24 Nov 2026 and 26 Dec 2026, from Gateshead's recent changes of use.

Comments are open until 28 Oct 2026

Comment on this application ↗

Site constraints 5

Coal mining development high risk area
Recorded coal mining features at or near the surface. Most planning applications here need a coal mining risk assessment. Nearest recorded mine shaft: about 3 m from the postcode pin (reference 425559-007).
From the Mining Remediation Authority, formerly the Coal Authority. The development high risk area marks recorded coal mining features at or near the surface: mine shafts and adits, shallow workings, mine gas and former opencast sites. Most planning applications there need a coal mining risk assessment; householder applications, changes of use and some minor works are exempt. Mine entry positions come from old plans and can be out by several metres, and unrecorded workings can exist anywhere in the coalfield.
Coal mining risk assessments ↗
National infrastructure project about 826 m away: A1 Birtley to Coal House Improvement Scheme
The site is about 826 m from the project boundary. Highway, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Conservation area about 19 m away: Chowdene CA
The edge of the area; work outside it can still affect its setting.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Also on the record
Radon affected area, class 2; Inside the Gateshead built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £200,000 in March 1996. Detached house, freehold.

1 March 1996£200,000

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Work with planning data?

Every application in Gateshead - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Gateshead
Application type
Full Application
Postcode
NE9 6US
Received
16 Feb 2026
Validated
15 Sept 2026
Ward
Chowdene
Case officer
Show
Target decision
10 Nov 2026
Decision level
Delegated Items
Applicant
Show
Agent
Hedley Planning Services

Decision outlook

Day 24 of the 56-day target. Gateshead usually decides changes of use by day 99.

Day 2475 days to the predicted decision (day 99)
32%decided within 8 weeks
84%approved
17%go to committee

Plota live figures for changes of use decided by Gateshead in the last twelve months, from validation. Gateshead decision record →

Public comments

1comment received
1 neutral

19 neighbours consulted · Last counted 1 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Comments by
28 Oct 2026
Statutory expiry
10 Nov 2026
Env. assessment
No
Gateshead
Planning Authority Score
2.4/10
Poor
#255 of 296 councils
Relevant to this application:
Change of use

Gateshead is one of the slowest councils in England for householder decisions, ranking #289 out of 296. The council extends the time limit on 67% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly more likely to be approved here (94%) than the national average (90%).

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Gateshead decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #130 of 296
94%
Householder approved
Above avg (90%) #107 of 296
26%
Decided in 8 weeks
Below avg (63%) #289 of 296
67%
Extended time limit
Above avg (41%) #282 of 296
58%
Minor dwellings approved
24 decided (1-9 homes)
100%
Major dwellings approved
4 decided (10+ homes)
70%
Change of use approved
37 decided
482
Total decisions
54 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.