Hopkinson House 88 Vauxhall Bridge Road London SW1V 2RW Data via plota.co.uk

25/06825/COFUL - Full Application for Council's Own Dev. Approved

Proposal

Use of the building to provide 31 self-contained residential units (24 x 2-bed, 6 x 3-bed and 1 x 4-bed) as Stage 2 Temporary Accommodation (Class C3); external alterations including to the existing ground floor entrances; formation of a bin store (on Osbert Street); alterations at roof level including installation of photovoltaic panels, lift over-runs, two plant enclosures; alterations to windows and new deck access at rear first to third floors; landscaping and cycle storage in the rear courtyard. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
23 Sept 2025
✓
Approved
6 May 2026

Approved on 6 May 2026 · Complex Delegated Decision · Last checked 19 Oct 2026

Documents 125

Statements & assessments 35

PDF ARBORICULTURAL METHOD STATEMENT Background Papers · 9 Jan 2026 View ↗ PDF ARBORICULTURAL IMPACT DRAWINGS Background Papers · 9 Jan 2026 View ↗ PDF ARBORICULTURAL IMPACT DRAWINGS Background Papers · 9 Jan 2026 View ↗ PDF REVISED AIR QUALITY ASSESSMENT Air quality assessment · 8 Jan 2026 View ↗ PDF ADDENDUM TRANSPORT STATEMENT Transport Statement · 9 Dec 2025 View ↗ PDF ENERGY STRATEGY Background Papers · 4 Dec 2025 View ↗ PDF ENERGY STRATEGY Background Papers · 4 Dec 2025 View ↗ PDF VSC WINDOW MAP Daylight and Sunlight assessment · 11 Nov 2025 View ↗ PDF AIR QUALITY ASSESSMENT Superseded document · 23 Sept 2025 View ↗ PDF ARBORICULTURAL IMPACT ASSESSMENT AND METHOD STATEMENT Superseded document · 23 Sept 2025 View ↗ PDF ARCHAEOLOGICAL ASSESSMENT Background Papers · 23 Sept 2025 View ↗ PDF BIOIVERSITY NET GAIN ASSESSMENT Biodiversity survey and report · 23 Sept 2025 View ↗ PDF THE STATUTORY BIODIVERSITY METRIC - HOPKINSON HOUSE (FULL) Background Papers · 23 Sept 2025 View ↗ PDF BREEAM PRE-ASSESSMENT Background Papers · 23 Sept 2025 View ↗ PDF CIRCULAR ECONOMY STATEMENT Background Papers · 23 Sept 2025 View ↗ PDF CIRCULAR ECONOMY STATEMENT - APPENDIX A Background Papers · 23 Sept 2025 View ↗ PDF DAYLIGHT AND SUNLIGHT REPORT Daylight and Sunlight assessment · 23 Sept 2025 View ↗ PDF ENERGY STATEMENT Energy Assessment · 23 Sept 2025 View ↗ PDF ENERGY STATEMENT SAP ANALYSIS Background Papers · 23 Sept 2025 View ↗ PDF FLOOD RISK ASSESSMENT Flood risk assessment · 23 Sept 2025 View ↗ PDF FLOOD WARNING AND MANAGEMENT PLAN Background Papers · 23 Sept 2025 View ↗ PDF HERITAGE IMPACT ASSESSMENT Heritage Statement · 23 Sept 2025 View ↗ PDF NOISE IMPACT ASSESSMENT Acoustic report · 23 Sept 2025 View ↗ PDF PRELIMINARY ECOLOGICAL APPRAISAL AND PRELIMINARY ROOT ASSESSMENT Background Papers · 23 Sept 2025 View ↗ PDF STATEMENT OF COMMUNITY INVOLVEMENT Background Papers · 23 Sept 2025 View ↗ PDF SUSTAINABLE DESIGN STATEMENT Background Papers · 23 Sept 2025 View ↗ PDF SUSTAINABLE DRAINAGE SYSTEMS AND APPENDICES Background Papers · 23 Sept 2025 View ↗ PDF WHOLE LIFE CARBON ASSESSMENT Background Papers · 23 Sept 2025 View ↗ PDF TRANSPORT STATEMENT Transport Statement · 23 Sept 2025 View ↗ PDF DESIGN AND ACCESS STATEMENT Design and Access Statement · 23 Sept 2025 View ↗ PDF FIRE STATEMENT Background Papers · 23 Sept 2025 View ↗ PDF LANDSCAPE DAS Design and Access Statement · 23 Sept 2025 View ↗ PDF DESIGN AND ACCESS STATEMENT Design and Access Statement · 23 Sept 2025 View ↗ PDF DESIGN AND ACCESS STATEMENT Design and Access Statement · 23 Sept 2025 View ↗ PDF PLANNING STATEMENT Planning Statement · 23 Sept 2025 View ↗

Plans & drawings 51

PDF DRAWING SCHEDULE Drawing · 20 Jan 2026 View ↗ PDF PROPOSED GROUND FLOOR PLAN Drawing · 12 Dec 2025 View ↗ PDF GANTRY ELEVATION Drawing · 7 Nov 2025 View ↗ PDF REVISED GROUND FLOOR PLAN Drawing · 6 Nov 2025 View ↗ PDF VAUXHALL BRIDGE ROAD PROPOSED ELEVATION Drawing · 10 Oct 2025 View ↗ PDF GROUND FLOOR PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF LOWER GROUND FLOOR PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF FIRST FLOOR PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF SECOND FLOOR PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF THIRD FLOOR PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF ROOF PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF SITE LOCATION PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF BLOCK PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF VAUXHALL BRIDGE ROAD EXISTING Drawing · 23 Sept 2025 View ↗ PDF ELEVATION OSBERT ST EXISTING Drawing · 23 Sept 2025 View ↗ PDF ELEVATION DOUGLAS ST EXISTING Drawing · 23 Sept 2025 View ↗ PDF NORTH WEST COURTYARD VAUXHALL BRIDGE ROAD EXISTING Drawing · 23 Sept 2025 View ↗ PDF NORTH WEST COURTYARD VAUXHALL BRIDGE ROAD EXISTING Drawing · 23 Sept 2025 View ↗ PDF SOUTH EAST COURTYARD DOUGLAS ST EXISTING Drawing · 23 Sept 2025 View ↗ PDF GROUND FLOOR PLAN PROPOSED Superseded document · 23 Sept 2025 View ↗ PDF LOWER GROUND FLOOR PLAN PROPOSED Drawing · 23 Sept 2025 View ↗ PDF FIRST FLOOR PLAN PROPOSED Drawing · 23 Sept 2025 View ↗ PDF SECOND FLOOR PLAN PROPOSED Drawing · 23 Sept 2025 View ↗ PDF THIRD FLOOR PLAN PROPOSED Drawing · 23 Sept 2025 View ↗ PDF ROOF PLAN PROPOSED Drawing · 23 Sept 2025 View ↗ PDF BLOCK PLAN PLANNING Drawing · 23 Sept 2025 View ↗ PDF ELEVATION VAUXHALL BRIDGE ROAD PROPOSED Background Papers · 23 Sept 2025 View ↗ PDF OSBERT STREET PROPOSED Drawing · 23 Sept 2025 View ↗ PDF DOUGLAS STREET ELEVATION PROPOSED Drawing · 23 Sept 2025 View ↗ PDF ELEVATION - NW COURTYARD VAUXHALL BRIDGE ROAD PROPOSED Drawing · 23 Sept 2025 View ↗ PDF ELEVATION - SW COURTYARD OSBERT STREET PROPOSED Drawing · 23 Sept 2025 View ↗ PDF ELEVATION - SE COURTYARD DOUGLAS STREET PROPOSED Drawing · 23 Sept 2025 View ↗ PDF TYPICAL BUILDING SECTIONS PROPOSED Drawing · 23 Sept 2025 View ↗ PDF GROUND FLOOR PLAN DEMOLITION Drawing · 23 Sept 2025 View ↗ PDF LOWER GROUND FLOOR PLAN DEMOLITION Drawing · 23 Sept 2025 View ↗ PDF FIRST FLOOR PLAN DEMOLITION Drawing · 23 Sept 2025 View ↗ PDF SECOND FLOOR PLAN DEMOLITION Drawing · 23 Sept 2025 View ↗ PDF THIRD FLOOR PLAN DEMOLITION Drawing · 23 Sept 2025 View ↗ PDF ROOF PLAN DEMOLITION Drawing · 23 Sept 2025 View ↗ PDF OSBERT ST ENTRANCE DOOR PROPOSED Drawing · 23 Sept 2025 View ↗ PDF OSBERT ST BIN STORE BAY STUDY PROPOSED Drawing · 23 Sept 2025 View ↗ PDF COURTYARD ENTRANCE DOOR PROPOSED Drawing · 23 Sept 2025 View ↗ PDF TYPICAL GANTRY BAY STUDY PROPOSED Drawing · 23 Sept 2025 View ↗ PDF TYPICAL STREET EXTERNAL WALL DETAIL PROPOSED Drawing · 23 Sept 2025 View ↗ PDF DRAWING ISSUE SHEET (P SERIES) Superseded document · 23 Sept 2025 View ↗ PDF LOCATION PLAN EXISTING Drawing · 23 Sept 2025 View ↗ PDF SOFT LANDSCAPE PROPOSAL Drawing · 23 Sept 2025 View ↗ PDF HARD LANDSCAPE PROPOSAL Drawing · 23 Sept 2025 View ↗ PDF LANDSCAPE MASTERPLAN Drawing · 23 Sept 2025 View ↗ PDF LANDSCAPE ILLUSTRATIVE ELEVATIONS Drawing · 23 Sept 2025 View ↗ PDF OPERATIONAL MANAGEMENT PLAN Background Papers · 23 Sept 2025 View ↗

Other documents 31

PDF S106 AGREEMENT Legal Agreement · 6 May 2026 View ↗ PDF DRAFT S106 UU Planning obligations · 10 Feb 2026 View ↗ PDF SUPPORTING DOCUMENTS APPENDIX V1 Background Papers · 20 Jan 2026 View ↗ PDF LANDSCAPE STRATEGY Background Papers · 12 Dec 2025 View ↗ PDF LANDSCAPE STRATEGY Background Papers · 12 Dec 2025 View ↗ PDF LANDSCAPE STRATEGY Background Papers · 12 Dec 2025 View ↗ PDF LANDSCAPE STRATEGY Background Papers · 12 Dec 2025 View ↗ PDF LANDSCAPE STRATEGY Background Papers · 12 Dec 2025 View ↗ PDF WHOLE LIFE CARBON Background Papers · 12 Dec 2025 View ↗ PDF WHOLE LIFE CARBON Background Papers · 12 Dec 2025 View ↗ PDF WHOLE LIFE CARBON Background Papers · 12 Dec 2025 View ↗ PDF WHOLE LIFE CARBON Background Papers · 12 Dec 2025 View ↗ PDF SAP CALCULATIONS Background Papers · 4 Dec 2025 View ↗ PDF REVISED WASTE & RECYCLING STRATEGY Background Papers · 6 Nov 2025 View ↗ PDF SITE NOTICE 21 OR 28 DAYS IF T&C APPL. Background Papers · 30 Sept 2025 View ↗ PDF ACK-GENERAL LETTER (G/P/C) Background Papers · 30 Sept 2025 View ↗ PDF ECNSLT-INTERNAL CONSULTS Background Papers · 30 Sept 2025 View ↗ PDF ECNSLT-INTERNAL CONSULTS Background Papers · 30 Sept 2025 View ↗ PDF CNSLT-LA SOCIETY Background Papers · 30 Sept 2025 View ↗ PDF ECNSLT-INTERNAL CONSULTS Background Papers · 30 Sept 2025 View ↗ PDF ECNSLT-INTERNAL CONSULTS Background Papers · 30 Sept 2025 View ↗ PDF BAT SURVEYS VERSION 3 Background Papers · 30 Sept 2025 View ↗ PDF ATTACHMENT SUMMARY Background Papers · 23 Sept 2025 View ↗ PDF HOPKINSON HOUSE - ARBTECH AIA 01 - 29-08-25 (A0) Superseded document · 23 Sept 2025 View ↗ PDF HOPKINSON HOUSE - ARBTECH TPP 01 - 29-08-25 (A0) Superseded document · 23 Sept 2025 View ↗ PDF APPENDIX B R001JBK - 250123 - HOPKINSON HOUSE - GLA CIRCULAR ECONOMY STATEMENTS Background Papers · 23 Sept 2025 View ↗ PDF EVIDENCE OF CONFIRMATION OF CAPACITY - THAMES WATER Background Papers · 23 Sept 2025 View ↗ PDF HOPKINSON HOUSE - WCC - SUDS PROFORMA Background Papers · 23 Sept 2025 View ↗ PDF HOPKINSON HOUSE GLA SPREADSHEET Background Papers · 23 Sept 2025 View ↗ PDF ENGAGEMENT WITH AND CONFIRMATION OF CHMHT RELOCATION Background Papers · 23 Sept 2025 View ↗ PDF HOPKINSON HOUSE APPLICATION COVER LETTER V2 23.09.2025 Background Papers · 23 Sept 2025 View ↗

All documents on the council site ↗

Site constraints 10

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Vincent Square conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Article 4 direction
Article 4 Basement Development Permitted Rights Removed. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area: City of Westminster APA 3.2
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Westminster AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 171 m away: Thames Tideway Tunnel
The site is 171 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 6 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
16 listed buildings within 150 m
Nearest: Lord High Admiral Public House, Grade II*, 36 m away · 2 Grade I, 12 Grade II*, 2 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 16 with distances
Historic England ↗
Also on the record
Inside the City of Westminster built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area596 m² (6,415 sq ft)
Energy ratingD (asset rating 96)
UseOffices and Workshop Businesses
HeatingHeating and Natural Ventilation

From the energy performance certificate lodged in July 2024, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Westminster - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Application for Council's Own Dev.
Postcode
SW1V 2RW
Received
23 Sept 2025
Validated
23 Sept 2025
Ward
Vincent Square
Case officer
Show
Target decision
8 May 2026
Decision
Application Permitted
Decision date
6 May 2026
Decision level
Complex Delegated Decision
Applicant
Show
Agent
Tibbalds Planning and Urban Design
Freehold owner
Show

How this decision compares

Decided in 225 days from validation, 149 days slower than Westminster's median of 76 for full applications. Approved, as 86% of full applications here are.

35%decided within 8 weeks
86%approved
2,206decided in the last year

Plota live figures for full applications decided by Westminster in the last twelve months, from validation. Westminster decision record →

Public comments

5comments received
1 objecting2 neutral2 supporting

40% support · above the UK average of 16%

603 neighbours consulted · Last counted 19 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14316471
Planning Portal ref
PP-14316471
Comments by
29 Oct 2025
Site or press notice
8 Oct 2025
Env. assessment
No
Westminster
Planning Authority Score
3.5/10
Below average
#221 of 296 overall
Relevant to this application:
Householder decisions

Westminster is slower than most councils at deciding householder applications: #258 of 296 on speed. Only 28% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Westminster is also one of the strictest councils - it refuses more householder applications than almost any other, with only 81% approved vs 90% nationally.

One of the strictest councils
only 81% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Westminster decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #201 of 296
81%
Householder approved
Below avg (90%) #277 of 296
44%
Decided in 8 weeks
Below avg (63%) #258 of 296
28%
Extended time limit
Below avg (41%) #46 of 296
83%
Minor dwellings approved
12 decided (1-9 homes)
67%
Major dwellings approved
3 decided (10+ homes)
81%
Change of use approved
133 decided
4,602
Total decisions
648 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.

Freehold owner and leaseholders: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.