Meridian Water Former Gas Holder Site Leeside Road London N18 Data via plota.co.uk

26/02995/NMA - App for Non-Material Amendments Approved

Proposal

Non material amendment to Ref: (Plot Z02-01/ Phase 1 only), to allow minor amendments in relation to doors, louvre's and parapet height adjustments. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
15 Jul 2026
✓
Consultation
28 Jul 2026
✓
Approved
8 Sept 2026

Approved on 8 Sept 2026 · Delegated Decision · Last checked 9 Sept 2026

Associated applications 4

  • Part of

    OutlineApprovedcouncil archive

    Conditions 4, 9, 11, 15, 23, 27, 29, 31, 32, 35, 36, 37 discharged

Site constraints 10

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Article 4 direction
Borough wide. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area: River valley deposits with high prehistoric and palaeonvironmental potential.
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Enfield AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 42 m away: North London (Electricity Line) Reinforcement
The site is 42 m from the project boundary. Electricity line, decided. The project page says whether consent was granted. Also within 2 km: North London Heat and Power Project (decided, 683 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Inside the Enfield built-up area; Public transport access: PTAL 2 (poor), TfL 2023, for the 100 m square; Flood defence 48 m away (natural high ground, designed for a 1 in 1000 year flood); Green belt 77 m away: London.
Not affected
No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Enfield - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Enfield
Application type
App for Non-Material Amendments
Received
15 Jul 2026
Validated
15 Jul 2026
Ward
Upper Edmonton
Case officer
Show
Target decision
12 Aug 2026
Decision
Granted
Decision date
8 Sept 2026
Decision level
Delegated Decision
Agent
DP9 Limited

Public comments

No public comments yet.

Last counted 9 Sept 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15056404
Planning Portal ref
PP-15056404
Consultation
28 Jul 2026
Comments by
18 Aug 2026
Statutory expiry
12 Aug 2026
Env. assessment
No
Enfield
Planning Authority Score
6.9/10
Good
#65 of 296 councils
Relevant to this application:
Householder decisions

Enfield is one of the fastest councils in England for householder decisions, ranking #15 out of 296. Only 5% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Enfield is also one of the strictest councils - it refuses more householder applications than almost any other, with only 83% approved vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Enfield decision statistics
Based on MHCLG data, the year to March 2026
78%
Overall approval rate
Below avg (87%) #271 of 296
83%
Householder approved
Below avg (90%) #260 of 296
90%
Decided in 8 weeks
Above avg (63%) #15 of 296
5%
Extended time limit
Below avg (41%) #1 of 296
60%
Minor dwellings approved
265 decided (1-9 homes)
63%
Major dwellings approved
8 decided (10+ homes)
72%
Change of use approved
322 decided
1,939
Total decisions
433 refused in the year to March 2026