Electricity transmission hub enabling works at HVDC Converter Station Arnish Isle Of Lewis

Summary of planning committee decision

Decided by Western Isles Planning Applications Board on 30 Sept 2026.

26/00103/MSCMApproved

What was proposed

The application sought approval of enabling works for a strategic electricity transmission hub, including earthworks, platforms, roads, drainage and landscaping.

“The Proposal 5.1 The application is a first application for approval of matters specified in conditions, this relating to the enabling works, for the approved Construction and Operation of a Strategic Electricity Transmission Hub Consisting of a 400kV AC Substation, an HVDC Converter Station, and the Associated Undertaking of Earthworks, the Formation of Platforms, Landscaping, Means of Access, Means of Enclosure, Site Drainage, Temporary Construction Compounds, Peatland…”

Officer report

Planning history

Planning permission in principle was granted in November 2025, following earlier application, scoping and proposal-of-application stages.

“Planning History 5.9 The Planning history directly associated with the Proposed Development is: • 24/00289/PAN – Proposal of Application Notice submitted and approved 06 August 2024.”

“24/00325/SCO_L – EIA Scoping Opinion – Scoping Opinion issued 26 November 2024. The methodology and scope of the Environmental Impact Assessment (EIA) was agreed. • 25/00061/PPPM – Planning Permission in Principle approved 28 November 2025. • Requests to discharge suspensive conditions pertaining to Planning Permission in Principle 25/00061/PPPM: o 26/00133/DISCON- Condition 4, approved 07/05/2026. o 26/00134/DISCON- Condition 5, approved 08/05/2026.”

Officer report

What officers recommended

Officers recommended approval with delegated authority for outstanding landscape information and conditions.

“The majority of the information provided in support of the application is sufficient to comply with the conditions of the enabling phase of the development specified in ref 25/00061/PPPM, Condition 3a. It is noted that further detail is required in terms of Condition 3a iii to secure the surfacing of the access bellmouths and to ensure full compliance with Condition 3a ix. as detailed within the Review undertaken by LUC, as appointed by the Comhairle.”

“It is recommended that the application be approved subject to: • the grant of delegated authority to the Chief Executive to determine the following outstanding information: ▪ the provision of an updated Landscape Mitigation strategy to address the findings of the commissioned independent Review by LUC, dated 03/09/2026 as summarised in paragraph 10.18 above , to the satisfaction of the Comhairle as Planning Authority.”

Officer report

Main issues considered

The assessment considered landscape, soils, drainage, noise, transport and compliance with the permission in principle and development plan.

“Approach 10.1 The key considerations in the determination of this application is the acceptability of the submitted information in relation to the details required by Condition 3a i.-xi. of the planning permission in principle (ref 25/00061/PPPM); compliance with the Environmental Impact Assessment submitted in support of the planning permission in principle; and whether the proposal complies with the relevant policy requirements of the Development Plan.”

Officer report

What consultees said

Consultees generally accepted the submitted information, while the landscape review sought further detail on planting, bunds, fencing and monitoring.

“The Review provides comment on sections of the LMS with the key findings that it is clear and comprehensive but further work is required to ensure it meets the full requirements of Condition 3a.”

“Cross sections and smaller scale detailed plans required to better understand the detail of the proposed stone wall, at the western entrance. The LMS should also request that a test panel of the stone wall is created and approved by the appointed Landscape Architect during the construction phase. There is also scope for further native woodlands scrub planting behind the stone wall, respecting any required visibility splays.”

Officer report

The committee’s recommendation

The Planning Applications Board recommended approval with delegated authority for updated landscape information, access details and conditions.

“(1) the grant of delegated authority to the Chief Executive to determine the following outstanding information:”

“(i) the provision of an updated Landscape Mitigation strategy to address the findings of the commissioned independent Review by LUC, dated 03/09/2026 as summarised in paragraph 10.18 of the Report, to the satisfaction of the Comhairle as Planning Authority;”

Minutes

The final decision

The Comhairle approved the application subject to delegated authority for updated landscape information and the stated conditions.

“At the Comhairle meeting on 1 October 2026, officers provided further information relevant to recommendation (1)(ii) above. The Comhairle then agreed that the application be approved subject to:”

“(1) the granting of delegated authority to the Chief Executive to determine the provision of an updated Landscape Mitigation strategy to address the findings of the commissioned independent Review by LUC, dated 03/09/2026 as summarised in paragraph 10.18 of the Report, to the satisfaction of the Comhairle as Planning Authority; and…”

Minutes

Councillors at the meeting

Source: Plota analysis of the council's minutes; parties from Democracy Club.

Sources

  • Western Isles Planning Applications Board minutes, 30 September 2026
  • Agenda and papers (council website)

Source: Plota analysis of Western Isles's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Date
Wednesday 30 September 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
8Independent 5SNP 21 otherShow councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

This committee's year

13 decisions in the 12 months to this meeting, 1 against officer advice.

Source: Plota analysis of the committee's minutes.