HVDC Converter Station Arnish Isle Of Lewis Data via plota.co.uk

26/00103/MSCM - Matters Specified in Conditions Major Approved

Proposal

Approval of Matters Specified in Condition 3a i - 3a xi - (Enabling Works) pursuant to Planning Permission Ref: for the Proposed Construction and Operation of a Strategic Electricity Transmission Hub Consisting of a 400kV AC Substation, an HVDC Converter Station, etc (National Development) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
13 Mar 2026
✓
Validated
30 Mar 2026
✓
Consultation
27 Apr 2026
✓
Approved
29 Oct 2026

Approved on 29 Oct 2026 · Committee/Comhairle Decision · Last checked 3 Nov 2026

Planning committee

Decided by Western Isles Planning Applications Board on 30 Sept 2026.

Approved

As officers recommended.

  • Officers advised approval because the details were acceptable overall, with further landscape information required before the decision notice.
  • No neighbour representations were received, while consultees raised no objection and found the information acceptable in their areas.
  • The committee recommended approval and the Comhairle approved the application subject to delegated authority and conditions.
Read how the committee decided The proposal, site and history, officers’ assessment, consultation responses, committee discussion and final decision.

Source: Plota analysis of Western Isles's committee minutes of 30 Sept 2026.

Documents 66

Other documents 22

PDF NOTICE OF COMMENCEMENT Other · 2 Nov 2026 View ↗ PDF 4NO DWGS - VEGETATION RETAINED/REMOVED, FENCING/WALLS AND TRACKS LANDSCAPE MITIGATION STRATEGY PART 1 Approved · 29 Oct 2026 View ↗ PDF 3NO DWGS - SUDS, FENCING, FEATURE WALL LANDSCAPE MITIGATION STRATEGY PART 5 Approved · 29 Oct 2026 View ↗ PDF MINUTES FROM PAB MEETING 30.09.2026 Committee Minutes · 19 Oct 2026 View ↗ PDF SPECIFIED MATTER 3A IX LANDSCAPE MITIGATION STRATEGY MAIN REPORT Other · 30 Sept 2026 View ↗ PDF SPECIFIED MATTER 3A IX LANDSCAPE MITIGATION STRATEGY MAIN REPORT PART 2 Other · 30 Sept 2026 View ↗ PDF SPECIFIED MATTER 3A IX LANDSCAPE MITIGATION STATEGY PART 3 - APPEDICES Other · 30 Sept 2026 View ↗ PDF SPECIFIED MATTER 3A IX LANDSCAPE MITIGATION STRATEGY PART 4 - APPEDICES Other · 30 Sept 2026 View ↗ PDF SPECIFIED MATTER 3A IX- LANDSCAPE MITIGATION STRATEGY PART 5 - APPENDICES Other · 30 Sept 2026 View ↗ PDF APPENDIX 1 Report - Committee · 28 Sept 2026 View ↗ PDF APPENDIX 2 Report - Committee · 28 Sept 2026 View ↗ PDF APPENDIX 3 Report - Committee · 28 Sept 2026 View ↗ PDF LANDSCAPE MITIGATION STRATEGY REVIEW Supporting Information · 3 Sept 2026 View ↗ PDF APPLICANTS AGREEMENT TO EXTENSION OF TIME Other · 11 Aug 2026 View ↗ PDF REQUEST FOR EXTENSION OF TIME Other · 10 Aug 2026 View ↗ PDF 3A III - SSEN COVER LETTER RE ROADS 13 JULY Other · 13 Jul 2026 View ↗ PDF 3A IX - LANDSCAPE MITIGATION STRATEGY 1 OF 2 Supporting Information · 1 Jul 2026 View ↗ PDF 3A IX - LANDSCAPE MITIGATION STRATEGY 2 OF 2 Supporting Information · 1 Jul 2026 View ↗ PDF SG ADVERT Other · 2 Apr 2026 View ↗ PDF APPLICATION COVER LETTER AMSC Application · 30 Mar 2026 View ↗ PDF REG 15 COVER LETTER Application · 24 Mar 2026 View ↗ PDF REG 15 CETRIFICATE CORRECTION Application · 24 Mar 2026 View ↗

All documents on the council site ↗

Associated applications 14

Work with planning data?

Every application in Western Isles - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Matters Specified in Conditions Major
Postcode
HS2 9JY
Received
13 Mar 2026
Validated
30 Mar 2026
Ward
Ste�rnabhagh A Tuath
Parish
North Lochs
Case officer
Show
Target decision
29 Jul 2026
Decision
Application Permitted with conditions
Decision date
29 Oct 2026
Decision level
Committee/Comhairle Decision
Applicant
Show

How this decision compares

Decided in 213 days from validation, 174 days slower than Western Isles's median of 39 for utility and infrastructure works. Approved, as 100% of utility and infrastructure works here are.

59%decided within 8 weeks
100%approved
52decided in the last year

Plota live figures for utility and infrastructure works decided by Western Isles in the last twelve months, from validation. Western Isles decision record →

Public comments

No public comments yet.

22 neighbours consulted · Last counted 3 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
100741450-001
Neighbours
31 Mar 2026
Consultation
27 Apr 2026
Comments by
18 May 2026
Site or press notice
2 Apr 2026
Committee
1 Oct 2026
Statutory expiry
29 Jul 2026
Env. assessment
No