The Baptist Church 49 Old Street Upton Upon Severn Worcester WR8 0HN Data via plota.co.uk

M/24/01740/LB - Listed Building Consent Approved

Proposal

Single storey extension to kitchen, new ramp and hand rails to main and side entrances, Internal alterations to original chapel; installation of internal platform lift and internal alterations to existing toilet block within modern wing Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
12 Dec 2024
✓
Validated
31 Jul 2025
✓
Approved
28 Nov 2025

Approved on 28 Nov 2025 · Delegated · Last checked 14 Oct 2026

Documents 31

All documents on the council site ↗

Site constraints 6

62 listed buildings within 150 m of the postcode pin
Nearest: 35, Old Street, Grade II, about 1 m from the postcode pin · 62 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 62 with distances
Historic England ↗
Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Also on the record
Scheduled monument about 209 m away: Upton cross in old churchyard; SSSI about 377 m away: Upton Ham SSSI; Inside the Upton upon Severn built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Not green belt

Checked on 1 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Malvern Hills - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Listed Building Consent
Postcode
WR8 0HN
Received
12 Dec 2024
Validated
31 Jul 2025
Ward
Upton & Ripple Ward
Parish
Upton-upon-Severn CP
Case officer
Show
Decision
Approval
Decision date
28 Nov 2025
Decision level
Delegated
Applicant
Show
Agent
Brown Matthews Architects Ltd

How this decision compares

Decided in 120 days from validation, 49 days slower than Malvern Hills's median of 71 for listed building works. Approved, as 90% of listed building works here are.

36%decided within 8 weeks
90%approved
46decided in the last year

Plota live figures for listed building works decided by Malvern Hills in the last twelve months, from validation. Malvern Hills decision record →

Consultation & key dates

Consultation
5 Aug 2025
Comments by
13 Sept 2025
Malvern Hills
Planning Authority Score
5.5/10
Average
#120 of 296 councils
Relevant to this application:
Other decisions

Malvern Hills is faster than most councils at deciding householder applications, ranking #45 out of 296. Householder applications are slightly less likely to be approved here (87%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Malvern Hills decision statistics
Based on MHCLG data, the year to March 2026
82%
Overall approval rate
Below avg (87%) #251 of 296
87%
Householder approved
Below avg (90%) #232 of 296
79%
Decided in 8 weeks
Above avg (63%) #45 of 296
37%
Extended time limit
Below avg (41%) #121 of 296
57%
Minor dwellings approved
148 decided (1-9 homes)
88%
Major dwellings approved
17 decided (10+ homes)
86%
Change of use approved
35 decided
744
Total decisions
131 refused in the year to March 2026