Planning decisions in Malvern Hills

How long Malvern Hills takes to decide a planning application and how many it approves, from the 44 decisions it made in the twelve months to August 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.

55 daysmedian from validation to decision (UK 52); 56 from receipt
68%decided within eight weeks (UK 73%), 76% within thirteen
74%approved (UK 89%): 25 approved, 9 refused, 3 withdrawn
219 of 321UK rank for speed, down 1 place on last year; 318 of 321 for approvals
05691 September 2025: 55 days, 159 decisionsSeptOctober 2025: 56 days, 142 decisionsOctNovember 2025: 55 days, 140 decisionsNovDecember 2025: 57 days, 100 decisionsDecJanuary 2026: 17 days, 9 decisionsJanFebruary 2026: 46 days, 12 decisionsFebMarch 2026: 58 days, 15 decisionsMarApril 2026: 102 days, 1 decisionsAprMay 2026: 124 days, 2 decisionsMayJune 2026: 163 days, 2 decisionsJunJuly 2026: 191 days, 2 decisionsJulAugust 2026: 207 days, 1 decisionsAug
Median days from validation to decision, by month of decision. Dashed line: UK median (52 days). Grid at 56 and 91 days, the eight and thirteen week targets.

By kind of application

KindMedian daysWithin 8 weeksApprovedDecisionsUK rank
Full applications (including householder) *5471%71%2195 of 302

Delegated or committee

RouteShareMedian daysApprovedDecisions
Delegated to officers98%5473%43
Planning committee2%169100%1

Where the register states how the decision was made.

Appeals

67 appeals against Malvern Hills decisions were decided by the Planning Inspectorate in the window, 744 for every 100 refusals; 37% were allowed. Every appeal in Malvern Hills.

By year

Year decidedMedian daysWithin 8 weeksApprovedDecisions
2016 *10719%96%58
2017 *3398%94%260
2018 *1599%91%241
2019 *3482%77%76
2020 *7036%70%50
2021 *6744%68%61
2022 *8723%59%66
2023 *7832%68%76
2024 *5257%100%116
2025 *5652%77%94
2026 so far5650%74%44

* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.

Built nightly from Malvern Hills's planning register. Ranks are among the 321 published councils. See planning applications in Malvern Hills, appeals, or get alerts for Malvern Hills.

About these figures

How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.