ONeills Stables Barmby Road Asselby East Riding Of Yorkshire DN14 7HF Data via plota.co.uk

26/02797/PLF - Full Planning Permission Pending Consideration

Proposal

Change of use of land to gypsy and traveller site with static and touring caravans, construction of vehicular access, erection of access gates, kennels and shed, installation of ground mounted solar panel array, manure pad and associated hardstanding (retrospective application) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
15 Oct 2026
✓
Validated
10 Nov 2026
Decision
Expected by 5 Jan 2027

Under consideration

No decision has been issued yet. Plota predicts a decision between 10 Dec 2026 and 1 Jan 2027, from East Riding's recent agricultural works.

Comments are open until 9 Dec 2026

Comment on this application ↗

Site constraints 3

In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
National infrastructure project: Yorkshire and Humber CCS Cross Country Pipeline
The site is inside the project boundary. Pipeline, decided. The project page says whether consent was granted. Also within 2 km: East Yorkshire Solar Farm (decided, 1.7 km); Humber Carbon Capture Pipeline (at pre-application, 298 m); East Coast Hydrogen Humber Pipeline (at pre-application, 597 m); Project Union: East Coast (at pre-application, 1.5 km).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 1. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 12 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Looking for land for a solar farm?

Plota Sites searches every land parcel in England and Wales: 29,327 sites fit this search. On and off the market, free to search.

Land for solar farms
Work with planning data?

Every application in East Riding - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
DN14 7HF
Received
15 Oct 2026
Validated
10 Nov 2026
Ward
Howden
Parish
Asselby Parish Council
Case officer
Show
Target decision
5 Jan 2027
Applicant
Show
Agent
JR Planning

Decision outlook

Day 13 of the 56-day target. East Riding usually decides agricultural works by day 43.

Day 1343 days to the 56-day target
85%decided within 8 weeks
87%approved
142decided in the last year

Plota live figures for agricultural works decided by East Riding in the last twelve months, from validation. East Riding decision record →

Public comments

18comments received
18 objecting

100% object · above the UK average of 74%

Last counted 18 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15300214
Planning Portal ref
PP-15300214
Comments by
9 Dec 2026
Env. assessment
No
East Riding
Planning Authority Score
8.1/10
Excellent
#24 of 296 overall
Relevant to this application:
Change of use

East Riding is one of the fastest councils in England for householder decisions: #7 of 296 on speed. Only 14% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
East Riding decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #110 of 296
92%
Householder approved
Above avg (90%) #152 of 296
95%
Decided in 8 weeks
Above avg (63%) #7 of 296
14%
Extended time limit
Below avg (41%) #9 of 296
76%
Minor dwellings approved
190 decided (1-9 homes)
95%
Major dwellings approved
42 decided (10+ homes)
86%
Change of use approved
79 decided
1,887
Total decisions
198 refused in the year to March 2026