CHAPEL COTTAGE Old Road, Sarre, Birchington, Kent, CT7 0LB Data via plota.co.uk

TCA/TH/25/0810 - Trees in a conservation area application Approved

Proposal

T1) Pine tree - Fell T2) Silver Birch tree - Fell Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
16 Jul 2025
✓
Approved
22 Aug 2025

Approved on 22 Aug 2025 · Delegated decision · Last checked 15 Oct 2026

Site constraints 7

Nutrient neutrality catchment: Stodmarsh SAC/SPA/Ramsar
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Sarre Conservation Area conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Article 4 direction
Birchington & Rural ED. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 1. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 139 m away: Richborough Connection Project
The site is 139 m from the project boundary. Electricity line, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
14 listed buildings within 150 m
Nearest: Lambs Cottage, Grade II, 37 m away · 14 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 14 with distances
Historic England ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 1 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Thanet - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Thanet
Application type
Trees in a conservation area application
Postcode
CT7 0LB
Received
16 Jul 2025
Validated
16 Jul 2025
Ward
Thanet Villages
Parish
Sarre Parish Council
Case officer
Show
Target decision
27 Aug 2025
Decision
Raise No Objection
Decision date
22 Aug 2025
Decision level
Delegated decision
Applicant
Show
Agent
D.Parr Tree Surgeons

How this decision compares

Decided in 37 days from validation, 16 days faster than Thanet's median of 53 for tree and landscaping works. Approved, as 97% of tree and landscaping works here are.

81%decided within 8 weeks
97%approved
13%go to committee

Plota live figures for tree and landscaping works decided by Thanet in the last twelve months, from validation. Thanet decision record →

Consultation & key dates

Statutory expiry
27 Aug 2025
Thanet
Planning Authority Score
4.5/10
Below average
#175 of 296 councils
Relevant to this application:
Other decisions

Thanet ranks #171 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (94%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Thanet decision statistics
Based on MHCLG data, the year to March 2026
91%
Overall approval rate
Above avg (87%) #103 of 296
94%
Householder approved
Above avg (90%) #122 of 296
62%
Decided in 8 weeks
Below avg (63%) #171 of 296
45%
Extended time limit
Above avg (41%) #196 of 296
79%
Minor dwellings approved
105 decided (1-9 homes)
85%
Major dwellings approved
27 decided (10+ homes)
90%
Change of use approved
50 decided
751
Total decisions
67 refused in the year to March 2026