Field Access Point (4) Land To The East Of Intwood Lane Intwood Norfolk Data via plota.co.uk

2026/0573 - Full Withdrawn

Proposal

Retention of vehicular crossover Access Point 4 created by Orsted Power (UK) Ltd for the 'Hornsea Project Three Offshore Wind Farm' Project Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
3 Mar 2026
✓
Validated
18 Mar 2026
✓
Consultation
22 Apr 2026
−
Withdrawn
20 May 2026

Withdrawn on 20 May 2026 · Delegated · Last checked 12 Sept 2026

Site constraints 8

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Nutrient neutrality catchment: Yare Broads and Marshes
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Public footpath 0 m away
Matters where it crosses or adjoins the site: obstructing a path without a diversion order is an offence, and work cannot start until the order is confirmed.
Compiled from highway authority data, not the legal definitive map. A few authorities have not published, so no path shown is not proof there is none.
National infrastructure project: Hornsea Project Three Offshore Wind Farm
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Sheringham and Dudgeon Extension Projects (decided, 437 m); A47 - A11 Thickthorn Junction (decided, 1.2 km).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Priority habitat: Coastal and floodplain grazing marsh
A habitat of principal importance. It shapes the ecology work and the biodiversity net gain a scheme has to show.
Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 3. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Habitat network: Restorable Habitat
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Registered park or garden 47 m away: Intwood Hall
Its setting is a consideration for work nearby.
Registered parks and gardens, battlefields, world heritage sites and protected wrecks are designated heritage assets: harm needs clear and convincing justification.
Historic England ↗
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Looking for land for a wind farm?

Plota Sites searches every land parcel in England and Wales: 8,347 sites fit this search. On and off the market, free to search.

Land for wind farms
Work with planning data?

Every application in South Norfolk Broadland - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full
Received
3 Mar 2026
Validated
18 Mar 2026
Ward
Cringleford
Parish
Keswick And Intwood
Case officer
Show
Target decision
29 May 2026
Decision
Withdrawn
Decision date
20 May 2026
Decision level
Delegated
Applicant
Show
Agent
Ceres Rural LLP

Public comments

No public comments yet.

Last counted 12 Sept 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14712481
Planning Portal ref
PP-14712481
Consultation
22 Apr 2026
Comments by
14 May 2026
Site or press notice
9 Apr 2026
Statutory expiry
13 May 2026
Env. assessment
No
South Norfolk Broadland
Planning Authority Score
5.9/10
Average
#106 of 296 overall
Relevant to this application:
Householder decisions

South Norfolk Broadland is #136 of 296 councils on householder decision speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
South Norfolk Broadland decision statistics
Based on MHCLG data, the year to March 2026
93%
Overall approval rate
Above avg (87%) #50 of 296
95%
Householder approved
Above avg (90%) #71 of 296
67%
Decided in 8 weeks
Above avg (63%) #136 of 296
42%
Extended time limit
Above avg (41%) #161 of 296
82%
Minor dwellings approved
137 decided (1-9 homes)
92%
Major dwellings approved
12 decided (10+ homes)
100%
Change of use approved
33 decided
1,013
Total decisions
67 refused in the year to March 2026