20-bed co-living building at 241 - 243 Milton Road, Portsmouth
Summary of planning committee decision
Decided by Portsmouth Planning Committee on 21 Oct 2026.
What was proposed
The application proposed demolishing a single-storey building and constructing a five-storey building with 20 co-living bedrooms and shared facilities.
“Construction of 5-storey building to form a 20 bed Co-Living development (Sui Generis) with associated communal internal and external amenity spaces and laundry; accessible dry recycling and refuse storage; servicing and delivery zone; landscaping; safe and accessible cycle storage; boundary treatments and other associated works (following demolition of existing single storey building).”
“The proposed internal arrangement would comprise: • Ground floor - bin & cycle storage, reception desk, laundry room, two bedrooms, a shared kitchen/ diner and external amenity area • First floor - 5 bedrooms and a shared kitchen/ diner, including a recessed balcony • Second floor - 5 bedrooms and a shared kitchen/ diner, including a terrace spanning the width of the building • Third floor - 5 bedrooms and a shared kitchen/ diner • Fourth floor - 3 bedrooms and a shared…”
Officer report
The site and surroundings
The site is on the east side of Milton Road, between Edgeware Road and Warren Avenue, beside community and residential uses.
“The application site comprises a single storey building situated to the east side of Milton Road (the A288). The site is positioned centrally on a row of development, sandwiched between Edgeware Road (north) and Warren Avenue (south). This row of development comprises community uses (place of worship) and residential.”
“Opposite the application site is a petrol station. Slightly further south, on the western side of Milton Road there are residential and commercial uses. Whilst acknowledging the wider surroundings has an array of uses and a mixed character, the immediate surroundings, to the rear (east) of the application site comprise residential properties and their respective gardens.”
Officer report
Earlier site history
Earlier permissions covered motor showroom, retail, equipment-repair, boxing-gym and dance-studio uses, while some signage and boundary-wire applications were refused.
“A*19022/G CHANGE OF USE FROM MOTOR CAR SHOWROOM TO RETAIL SHOP WITH ANCILLARY STORAGE Conditional Permission (August 1974)”
“A*19022/AC INSTALLATION OF 3 AND 2 STRAND BARBED SECURITY WIRE ON ANGLED BRACKETS ABOVE EXISTING BOUNDARY WALLS/STRUCTURES AFTER REMOVAL OF EXISTING BARBED WIRE Refused (January 2000)”
Officer report
What officers recommended
Officers recommended refusal because the scheme failed to achieve co-living principles, harmed future occupiers and neighbours, lacked Solent mitigation and lacked transport contributions.
“Having regard to all material planning considerations and representations it is concluded that the proposals would be unacceptable in terms of; achieving the 'co- living' principles, adverse impact upon future occupiers and neighbouring amenities as a result of the second-floor terrace, as well as the adverse harm arising to the SPA given the lack of mitigations, and the lack of S106 contributions.”
“1) The proposals fail to meet the established criteria for a co-living development. This is a direct result of the internal layout and the limited overall capacity of the scheme. This is contrary to Policy PLP19 of the Emerging Portsmouth Local Plan (2025- 2040), and the aims and objectives of the National Planning Policy Framework (2026).”
Officer report
Consultation responses
The Milton Neighbourhood Forum objected, while consultees generally raised no objection or sought conditions, contributions, further information or a licence.
“Comments July 2026: Further information required.”
“The Milton Neighbourhood Forum (MNF) welcomes investment in the area and appreciates the constructive engagement shown by the applicant. However, concerns that the proposals are contrary to the Milton Neighbourhood Plan policies, specifically; BNG and cycle parking. Concern regarding scale and massing. MNF keen to see the site brought back into use.”
Officer report
Who spoke
The applicant and an agent spoke in favour, while a councillor read the neighbourhood forum’s statement and gave a deputation against.
Members’ debate
Members welcomed redevelopment of a long-vacant site but found the co-living offer unconvincing and considered the issues too extensive for deferral.
“Co-living relied on substantial shared facilities and communal spaces and it was considered that the scheme fell short of that model.”
“Members' Comments. Members welcomed the proposed redevelopment of a long-vacant site but considered that the scheme did not provide a convincing co-living offer. Concerns included the scale and massing, the rear terrace and overlooking, the effect on bedrooms 11 and 12, cycle provision, biodiversity, parking pressures and the limited extent of genuinely communal facilities. Members considered that the issues were too extensive to be resolved by a deferral.”
Minutes
The committee’s decision
The committee refused planning permission for the reasons set out in the officer report.
“RESOLVED that planning permission be refused for the reasons set out in the officer report.”
Minutes
Reasons for refusal
The stated reasons concerned the co-living model, privacy and overlooking from the second-floor terrace, missing Solent mitigation and absent transport contributions.
“2) The proposed second-floor terrace would result in unacceptable loss of privacy/ overlooking for the amenities of adjoining neighbouring properties (east) as well as bedrooms 11 & 12. The proposals are therefore contrary to Policy PCS23 of the Portsmouth Plan (2012), Policy PLP1(5) of the Emerging Portsmouth Local Plan (2025-2040), and the aims and objectives of the National Planning Policy Framework (2026).”
“3) The application fails to provide the required mitigation to offset the impacts of the development upon the Solent Special Protection Area, from additional recreational pressure and nitrogen and phosphate loading generated by the population increase and additional sewage resulting from the development.”
Officer report
The members' reasons
“Members considered that the issues were too extensive to be resolved by a deferral. 3 RESOLVED that planning permission be refused for the reasons set out in the officer report. 124.”
Minutes
Source: the council's minutes, quoted word for word.
Councillors at the meeting
- Gerald Vernon-JacksonChairLib DemFor refusal(no vote against recorded)
- Peter CandlishLib DemFor refusal(no vote against recorded)
- Matthew CordyReform UKFor refusal(no vote against recorded)
- Lee HuntLib DemFor refusal(no vote against recorded)
- Carl InmanReform UKFor refusal(no vote against recorded)
- Denise PerryLib DemFor refusal(no vote against recorded)
- Joe StandenReform UKFor refusal(no vote against recorded)
The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.
Apologies Suzy Horton Lib Dem, Hugh Mason Lib Dem, Mary Vallely Labour
Source: Plota analysis of the council's minutes; parties from the council's list of councillors.
Sources
- Portsmouth Planning Committee minutes, 21 October 2026
- Agenda and papers (council website)
Source: Plota analysis of Portsmouth's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Portsmouth Planning Committee
- Council
- Portsmouth
- Date
- Wednesday 21 October 2026
- Recommendation
- Officers recommended refusal
- Committee decided
- Refused
- Councillors
- 7Lib Dem 4Reform UK 3Show votes
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Portsmouth committee decisions →
This committee's year
101 decisions in the 12 months to this meeting, 23 against officer advice.
Source: Plota analysis of the committee's minutes.