Pavement at Trafalgar Road, near jcn w/ Mell Street, Greenwich, SE10 9TZ Data via plota.co.uk

25/3955/F - Full Planning Permission Refused

Proposal

The installation of 1no. BT Street Hub and removal of associated BT payphones. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
24 Nov 2025
✗
Refused
19 Jan 2026
✓
Consultation
9 Feb 2026
✗
Appeal dismissed
23 Jun 2026

Refused on 19 Jan 2026 · Delegation · Last checked 10 Oct 2026

Site constraints 11

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Air quality management area: Greenwich AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 42 m away: Thames Tideway Tunnel
The site is 42 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: Silvertown Tunnel (decided, 995 m); London Strategic Heat Main Project (at pre-application, the site is inside its boundary).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Town centre: East Greenwich
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Radon affected area, class 2; 4 listed buildings within 150 m; Conservation area 74 m away: East Greenwich; World heritage site 210 m away: Maritime Greenwich; Inside the Greenwich built-up area; Public transport access: PTAL 3 (moderate), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Greenwich - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Greenwich
Application type
Full Planning Permission
Postcode
SE10 9TZ
Received
24 Nov 2025
Validated
24 Nov 2025
Ward
EAST GREENWICH
Parish
Greenwich
Case officer
Show
Target decision
19 Jan 2026
Decision
Refuse
Decision date
19 Jan 2026
Decision level
Delegation
Appeal
Dismissed · 23 Jun 2026 · Written Representations · Inspectorate case 6004724 ↗
Applicant
Show
Agent
Mitie

How this decision compares

Decided in 56 days from validation, about the council's usual 56 days. Refused, as 34% of full applications here are.

58%decided within 8 weeks
66%approved
6%go to committee

Plota live figures for full applications decided by Greenwich in the last twelve months, from validation. Greenwich decision record →

Public comments

No public comments yet.

Last counted 10 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14497938
Planning Portal ref
PP-14497938
Consultation
9 Feb 2026
Comments by
31 Dec 2025
Statutory expiry
19 Jan 2026
Env. assessment
No
Greenwich
Planning Authority Score
5.4/10
Average
#123 of 296 councils
Relevant to this application:
Householder decisions

Greenwich is faster than most councils at deciding householder applications, ranking #76 out of 296. Only 29% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Greenwich is also one of the strictest councils - it refuses more householder applications than almost any other, with only 78% approved vs 90% nationally.

One of the strictest councils
only 78% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Greenwich decision statistics
Based on MHCLG data, the year to March 2026
77%
Overall approval rate
Below avg (87%) #278 of 296
78%
Householder approved
Below avg (90%) #287 of 296
75%
Decided in 8 weeks
Above avg (63%) #76 of 296
29%
Extended time limit
Below avg (41%) #49 of 296
60%
Minor dwellings approved
114 decided (1-9 homes)
100%
Major dwellings approved
13 decided (10+ homes)
66%
Change of use approved
195 decided
1,468
Total decisions
331 refused in the year to March 2026