Leaside Lock Phase 3 (Formerly: Land at Imperial Street and Imperial Phase 3), Land at Imperial Street… Data via plota.co.uk

PA/26/00975/NC - Full Planning Permission Approved

Proposal

Proposed temporary change of use of the Block 1 commercial unit from Flexible Class E use to a Marketing Suite (Sui Generis) providing flexible space for sales and workspace in connection with the marketing of the development at Leaside Lock Phase 3. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
24 Jul 2026
✓
Approved
14 Sept 2026

Approved on 14 Sept 2026 · Delegated · Last checked 16 Sept 2026

Site constraints 11

In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. A site survey can differ.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Archaeological priority area: Tower Hamlets APA 3.2
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Radon affected area, class 2; Conservation area about 49 m away: Three Mills (part in Newham); Heritage at risk about 73 m away: Three Mills, Stratford/Bow; Public transport access: PTAL 4 (good), TfL 2023, for the 100 m square; Flood defence about 45 m from the postcode pin (wall, designed for a 1 in 50 year flood).
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
E3 3ED
Received
24 Jul 2026
Validated
24 Jul 2026
Ward
Bromley North
Case officer
Show
Target decision
18 Sept 2026
Decision
Permit
Decision date
14 Sept 2026
Decision level
Delegated
Applicant
Show
Agent
Turley

How this decision compares

Decided in 52 days from validation, 4 days faster than Tower Hamlets's median of 56 for changes of use. Approved, as 59% of changes of use here are.

53%decided within 8 weeks
59%approved
71decided in the last year

Plota live figures for changes of use decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Comments by
26 Aug 2026
Site or press notice
13 Aug 2026
Statutory expiry
18 Sept 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Change of use

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026