14 Cambrian Place Maritime Quarter Swansea SA1 1PQ Data via plota.co.uk

2025/2171/DOC - Discharge of Conditions Approved

Proposal

Conversion, extension and change of use of building from retail with associated workshops/storage (Class A1) to Restaurant and Bar (Class A3) and Offices (class B1) to ground floor and 11 residential units to upper floors with associated external alterations and works - Discharge of Condition 7 (method of stonework repairs) of Planning Permission granted 25th February 2021 Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
14 Oct 2025
✓
Consultation
16 Oct 2025
✓
Approved
4 Dec 2025

Approved on 4 Dec 2025 · Delegated Decision · Last checked 11 Oct 2026

Associated applications 6

Site constraints 5

Grade II listed: 13 Cambrian Place
List entry 11567 · 21 m away · 14 more listed buildings within 150 m (1 Grade II*, 13 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 14 with distances
Cadw ↗
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Maritime Quarter conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
National infrastructure project 924 m away: Tidal Lagoon Swansea Bay
The site is 924 m from the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Coalfield, development low risk area.
Not affected
No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area484 m² (5,210 sq ft)
Energy ratingC (asset rating 71)
UseA1/A2 Retail and Financial/Professional services
HeatingHeating and Natural Ventilation

From the energy performance certificate lodged in August 2017, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Swansea - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Swansea
Application type
Discharge of Conditions
Postcode
SA1 1PQ
Received
14 Oct 2025
Validated
14 Oct 2025
Ward
Waterfront - Bay Area
Case officer
Show
Target decision
9 Dec 2025
Decision
Approve
Decision date
4 Dec 2025
Decision level
Delegated Decision
Applicant
Show
Agent
Asbri Planning Ltd

How this decision compares

Decided in 51 days from validation, about the council's usual 48 days. Approved, as 99% of discharge of conditions here are.

68%decided within 8 weeks
99%approved
239decided in the last year

Plota live figures for discharge of conditions decided by Swansea in the last twelve months, from validation. Swansea decision record →

Public comments

No public comments yet.

Last counted 11 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14371774
Planning Portal ref
PP-14371774
Consultation
16 Oct 2025
Comments by
6 Nov 2025
Statutory expiry
9 Dec 2025
Env. assessment
No

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.