Royal Bank Of Scotland 9-11 Silver Street Kingston Upon Hull HU1 1JE Data via plota.co.uk

25/00275/FULL - Full Planning Permission Approved

Proposal

1. Change of use of 1st, 2nd, & 3rd floors and roof top to 3 serviced apartments (3 x 2 bed). 2. Change of use of ground floor from Bank to flexible use (either Shop / cafe of Gym). 3. External alterations including replacing existing curtain wall glazing & Doors, external marble cladding to be replaced and construction of a roof top extension. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
17 Mar 2025
✓
Approved
24 Oct 2025

Approved on 24 Oct 2025 · Delegated Decision · Last checked 9 Nov 2026

Documents 42

All documents on the council site ↗

Site constraints 9

Grade II listed: Former Lloyds Bank
List entry 1283100 · 0 m away · 94 more listed buildings within 150 m (2 Grade I, 4 Grade II*, 88 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 94 with distances
Historic England ↗
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Old Town conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Air quality management area: Hull AQMA No.1(A)
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 7 m away: A63 Castle Street Improvement-Hull
The site is 7 m from the project boundary. Highway, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Special area of conservation 367 m away: Humber Estuary; SSSI 367 m away: Humber Estuary - 2000480 SSSI; Scheduled monument 247 m away: Beverley Gate and adjacent archaeological remains forming part of Hull's medieval and post-medieval defences; Inside the Kingston upon Hull built-up area.
Not affected
Not green belt

Checked on 9 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Hull - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Hull
Application type
Full Planning Permission
Postcode
HU1 1JE
Received
17 Mar 2025
Validated
17 Mar 2025
Ward
St Andrews And Dockland
Case officer
Show
Decision
Application Permitted
Decision date
24 Oct 2025
Decision level
Delegated Decision
Agent
Rowe Architects

How this decision compares

Decided in 221 days from validation, 139 days slower than Hull's median of 82 for full applications. Approved, as 92% of full applications here are.

34%decided within 8 weeks
92%approved
309decided in the last year

Plota live figures for full applications decided by Hull in the last twelve months, from validation. Hull decision record →

Public comments

No public comments yet.

6 neighbours consulted · Last counted 9 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-13858144
Planning Portal ref
PP-13858144
Comments by
23 Apr 2025
Env. assessment
No
Hull
Planning Authority Score
2.6/10
Poor
#248 of 296 councils
Relevant to this application:
Change of use

Hull is slower than most councils at deciding householder applications, ranking #231 out of 296. The council extends the time limit on 62% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Frequently extends decision deadlines
expect longer than the statutory limit
These figures are council-wide context, not a prediction for this application. View full council performance
Hull decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #85 of 296
92%
Householder approved
Above avg (90%) #156 of 296
51%
Decided in 8 weeks
Below avg (63%) #231 of 296
62%
Extended time limit
Above avg (41%) #273 of 296
88%
Minor dwellings approved
16 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
88%
Change of use approved
33 decided
436
Total decisions
36 refused in the year to March 2026