Pentir Substation, Bangor, LL57 4ED Data via plota.co.uk

C25/0947/25/EIA - Environmental Impact Assessment Approved

Proposal

Amnewid ceblau tanddaearol presennol a gosod ceblau tanddaearol traws-safle newydd yn is-orsaf presennol Pentir yn ogystal a gwaith cysylltiol. Replacement of existing underground cables and installation of new cross site underground cables in the existing Pentir substation and ancillary works Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
24 Dec 2025
✓
Approved
6 May 2026

Approved on 6 May 2026 · Pwyllgor Cynllunio / Planning Committee · Last checked 19 Oct 2026

Planning committee

Decided by Gwynedd Planning Committee on 27 Apr 2026.

Approved

As officers recommended.

  • Officers advised approval because the works could be satisfactorily mitigated and would improve electricity connections across North Wales.
  • The committee approved the application with conditions, including a Construction Traffic Management Plan.
Read how the committee decided The proposal, site, planning history, officer assessment, consultation responses, public comments, speakers, debate, vote and conditions.

Source: Plota analysis of Gwynedd's committee minutes of 27 Apr 2026.

Documents 100

Statements & assessments 25

PDF 29_01_26-Disodli-Superseded-ES-Vol-2-Pentir-9-Traffic-and-Transport.pdf Supporting Documents · 29 Jan 2026 View ↗ PDF 29_01_26-Diwygiedig-Amended-ES-Vol-2-Pentir-9-Traffic-and-Transport.pdf Supporting Documents · 29 Jan 2026 View ↗ PDF ES-Vol-8-Appendix-7_4_B-Cumulative-Effects-Assessment.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-7_1_B-Habitats-Regulation-Assessment.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_C-Wider-Works-Bat-Survey-Report.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_B-Wider-Works-Aquatic-Survey-Report-copi-idox.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_A-Wider-Works-Habitat-Survey-Report-copi-idox.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_M-Wider-Works-Flood-Consequence-Assessment.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_I-Wider-Works-Historic-Environment-Desk-Based-Assessment-copi-idox.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_H-Wider-Works-Arboricultural-Impact-Assessment.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_F-Wider-Works-GCN-Survey-Report-copi-idox.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_5_C-Pentir-Arboriculture-Impact-Assessment.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_5_A-Pentir-Aquatic-Survey-Report.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_13_A-Pentir-Climate-Change-Risk-Assessment.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_7_A-Pentir-Initial-Conceptual-Site-Model-and-Risk-Assessment.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_6_A-Pentir-Historic-Environment-Desk-Based-Assessment.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_5_D-Pentir-Green-Infrastructure-Statement.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-1_4_A-Topic-Assessment-Methodology.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-11-Noise-and-Vibration.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-5-Ecology-and-Nature-Conservation.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Pentir-Drainage.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Pentir-Works-Welsh-Langauge-Statement.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Pentir-Works-Planning-Statement.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Pentir-Works-Design-and-Access-Statement.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Pentir Works Design and Access Statement.pdf Supporting Documents · 24 Dec 2025 View ↗

Plans & drawings 38

PDF ES-Vol-6-Figures-6_A_14.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_13-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_12.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_11-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_10-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_9-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_8-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_7-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_6-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_5-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_4-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_3-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_2-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_1-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_5_5-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_5_4-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_5_3_-copi-idox.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_5_2.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_5_1.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_2_2.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_2_1.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_17.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_16.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-6-Figures-6_A_15.pdf Plans · 30 Dec 2025 View ↗ PDF ES-Vol-2-Chapter-9-Figures.pdf Plans · 29 Dec 2025 View ↗ PDF ES-Vol-2-Chapter-7-Figures.pdf Plans · 29 Dec 2025 View ↗ PDF ES-Vol-2-Chapter-5-Figures.pdf Plans · 29 Dec 2025 View ↗ PDF ES-Vol-2-Chapter-2-Figures.pdf Plans · 29 Dec 2025 View ↗ PDF ES-Vol-2-Chapter-12-Figures.pdf Plans · 29 Dec 2025 View ↗ PDF ES-Vol-2-Chapter-10-Figure.pdf Plans · 29 Dec 2025 View ↗ PDF ES-Vol-1-Figures.pdf Plans · 29 Dec 2025 View ↗ PDF Pentir-Outline-Construction-Traffic-Management-Plan.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Pentir-Existing-and-Proposed-Sections.pdf Plans · 29 Dec 2025 View ↗ PDF Pentir-Proposed-Plan-and-Cross-Sections-for-the-Underground-Works.pdf Plans · 29 Dec 2025 View ↗ PDF Pentir-Overground-Works.pdf Plans · 29 Dec 2025 View ↗ PDF Pentir Underground Works.pdf Plans · 24 Dec 2025 View ↗ PDF Pentir Existing Site Layout.pdf Plans · 24 Dec 2025 View ↗ PDF Pentir Location Plan.pdf Plans · 24 Dec 2025 View ↗

Other documents 33

PDF 29_01_26-Diwygiedig-Amended-ES-Vol-2-Pentir-10-Air-Quality-and-Emissions.pdf Supporting Documents · 29 Jan 2026 View ↗ PDF 29_01_26-Disodli-Superseded-ES-Vol-2-Pentir-10-Air-Quality-and-Emissions.pdf Supporting Documents · 29 Jan 2026 View ↗ PDF ES-Vol-8-Appendix-7_1_A-Electric-and-Magnetic-Fields-Compliance-Report.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-7_4_A-Screening-for-In-Combination-Effects.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_L-Wider-Works-Socio-Economic-Land-Use-Receptors.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_K-Wider-Works-Climate-Change-Risk-Register.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_J-Wider-Works-Gazetteer-of-Historic-Assets.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-6_5_G-Wider-Works-Designated-Sites-Citations.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_5_B-Pentir-Statutory-Designated-Sites-Citation.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_2_A-OCEMP.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_9_B-Pentir-Traffic-Base-Counts.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_9_A-Pentir-Traffic-Flows.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-2_6_B-Gazetteer-of-Historic-Assets.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-8-Appendix-1_1_A-Legislation-Policy-and-Guidance.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Volume-6-Wider-Works.pdf Supporting Documents · 30 Dec 2025 View ↗ PDF ES-Vol-7-The-Project-and-Cumulative-Effects.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-Chapter-15-16-and-Bibliography.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-Executive-Summary-and-Chapters-1-to-3.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-14-Materials-and-Waste.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-13-Climate-Change.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-12-Socio-Economics.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-10-Air-Quality-and-Emissions.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-7-Geology-Hydrogeology-Land-Use-and-Agriculture-Soils.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-6-Historic-Environment.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-2-Pentir-4-Landscape-and-Visual-Amenity.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF ES-Vol-1-Project-Introduction.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Datganiad-Amgylcheddol-Cyfrol-0-Crynodeb-Annhechnegol.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Gwaith-Pentir-Datganiad-Cynllunio.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Gwaith-Pentir-Adroddiad-yr-Ymgynghoriad-Cyn-Ymgeisio.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Pentir-PAC-Report.pdf Supporting Documents · 29 Dec 2025 View ↗ PDF Cover letter draft - Pentir Letter head - Welsh.pdf Supporting Documents · 24 Dec 2025 View ↗ PDF Cover letter draft - Pentir Letter head - English.pdf Supporting Documents · 24 Dec 2025 View ↗ PDF Datganiad Iaith Gymraeg Gwaith Pentir.pdf Supporting Documents · 24 Dec 2025 View ↗

All documents on the council site ↗

Site constraints 2

Agricultural land, grade 5
Very poor quality farmland, not best and most versatile. Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. A site survey can differ.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Also on the record
Radon affected area, class 3.
Not affected
Outside flood zones 2 and 3 · No listed building at the site · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Gwynedd - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Gwynedd
Application type
Environmental Impact Assessment
Postcode
LL57 4ED
Received
24 Dec 2025
Validated
24 Dec 2025
Ward
Y Faenol
Case officer
Show
Target decision
6 May 2026
Decision
Approved with Conditions
Decision date
6 May 2026
Decision level
Pwyllgor Cynllunio / Planning Committee
Applicant
Show
Agent
WSP

How this decision compares

Decided in 133 days from validation, about the council's usual 133 days. Approved, as 84% of utility and infrastructure works here are.

10%decided within 8 weeks
84%approved
19%go to committee

Plota live figures for utility and infrastructure works decided by Gwynedd in the last twelve months, from validation. Gwynedd decision record →

Consultation & key dates

Comments by
12 Feb 2026
Statutory expiry
6 May 2026