120 Holborn London Camden EC1N 2TD Data via plota.co.uk

25/01165/OBS - Observations from other Boroughs No Objections to OBS

Proposal

Consultation by the London Borough of Camden on extensions and alterations including removal of rooftop plant and additional storey on west side (i.e. a 9 storey building adjacent to Leather Lane - including a 9 storey 'courtyard' extension) and 10 storeys with rooftop plant and terraces on east side (Holborn/Hatton Garden). Facade renewal including new balconies on Holborn Circus elevation. Ground and lower ground floor re-configurations to provide re-configured commercial and retail floorspace (Class E), affordable jewellery workspace and/or competitive socialising (sui generis) on lower ground floor, reconfiguration of entrances and servicing arrangements, new hard and soft landscaping, provision of cycle parking and other ancillary works. (LBC ref. ). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Aug 2025
✓
Consultation
1 Sept 2025
Decision
Target date was 12 Sept 2025

Under consideration

No decision has been issued yet. The council's target date, 12 Sept 2025, has passed.

The consultation period closed on 15 Sept 2025.

Site constraints 13

Hatton Garden conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
2 Article 4 directions
Basements · Commercial, Business, and Service (Use Class E) to residential (Use Class C3) (in CAZ). Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Protected view corridor: 4A.1 Primrose Hill summit to St Paul's Cathedral
Inside the landmark viewing corridor of a protected vista. A building that rises above the corridor's threshold height should be refused. How high that is depends on where along the view the site is. Also in the wider setting of 5A.2 Greenwich Park Wolfe statue to St Paul's Cathedral; 6A.1 Blackheath Point to St Paul's Cathedral.
The London Plan (policy HC4) designates strategic views, and the Mayor's London View Management Framework (March 2012) gives 13 of them a protected vista toward St Paul's Cathedral, the Palace of Westminster or the Tower of London. A vista has a threshold height that rises or falls with the line of sight. In the landmark viewing corridor, a building above it would harm the view and should be refused. In the wider setting consultation area around the corridor, a building above it is referred for consultation and its effect on the view is judged. The threshold changes along each view and is set out in the framework. A revised framework is out for consultation until 4 December 2026 and is not yet in force.
London View Management Framework ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Camden AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: New Oxford Street
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
National infrastructure project about 428 m away: Thames Tideway Tunnel
The site is about 428 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 834 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Scheduled monument about 94 m away: Barnard's Inn Hall (Mercers' School)
Its setting is a consideration for work nearby.
Nationally important archaeology protected by the Secretary of State. Work that affects the monument or its setting is rarely permitted.
Historic England ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
19 listed buildings within 150 m of the postcode pin
Nearest: Prudential Assurance Building, Grade II*, about 49 m from the postcode pin · 2 Grade I, 3 Grade II*, 14 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 19 with distances
Historic England ↗
Also on the record
Registered park or garden about 245 m away: Gray's Inn; Inside the Camden built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in City of London - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Observations from other Boroughs
Postcode
EC1N 2HT
Received
22 Aug 2025
Validated
22 Aug 2025
Ward
Castle Baynard
Case officer
Show
Target decision
12 Sept 2025
Decision level
Delegated Decision
Applicant
Show

Public comments

No public comments yet.

Last counted 17 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Consultation
1 Sept 2025
Comments by
15 Sept 2025
Committee
10 Oct 2025
Statutory expiry
12 Sept 2025
Env. assessment
No
City of London
Planning Authority Score
6.7/10
Good
#71 of 296 overall
Relevant to this application:
Householder decisions

City of London is one of the fastest councils in England for householder decisions: #1 of 296 on speed. The council extends the time limit on 84% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 100% approval rate vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
City of London decision statistics
Based on MHCLG data, the year to March 2026
97%
Overall approval rate
Above avg (87%) #3 of 296
100%
Householder approved
Above avg (90%) #1 of 296
100%
Decided in 8 weeks
Above avg (63%) #1 of 296
84%
Extended time limit
Above avg (41%) #296 of 296
50%
Minor dwellings approved
4 decided (1-9 homes)
91%
Change of use approved
22 decided
460
Total decisions
14 refused in the year to March 2026