Vauxhall Bridge Cliftonwood Spike Island Bristol BS1 6TT Data via plota.co.uk

26/14103/LB - Listed Building Application Pending consideration

Proposal

The project is to refurbish the Vauxhall Bridge. The initial part of the project is to remove the existing slabs and install a lightweight scaffold to allow the designers access to the bridge to inspect the structural stability, to determine the full scope of works. The general scope of works is to replace any damaged / unsuitable steel work, shot blasting of steel works, repainting of steelwork, addressing any stonework and replacing of the walkway. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
30 Sept 2026
✓
Validated
15 Oct 2026
Decision
Expected by 10 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 10 Dec 2026 and 17 Dec 2026, from Bristol's recent commercial and major works.

Comments are open until 2 Dec 2026

Comment on this application ↗

Documents 107

Plans & drawings 91

PDF 8889-GA004_C1 REPARATION SCHEME - TYPICAL BAY - OPTION 2 NORTH SOUTH ELEVATION - DECK BEAM Plan · 22 Oct 2026 View ↗ PDF 8889-GA061_C2 TEMPORARY WORKS - NORTH SPAN (SPAN 1) EAST GIRDER SUPPORT Plan · 22 Oct 2026 View ↗ PDF 8889-GA023_C2 RIVER SPAN (SPAN 2) EAST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 4 OF 4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA009_C3 NORTH SPAN (SPAN 1) EAST ELEVATION (INTERNAL VIEW) SPECIAL BAYS SHEET 2 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA048_C0 NON STANDARD REPAIR DETAILS LOWER CHORD STRENGHTENING REPAIRS Plan · 22 Oct 2026 View ↗ PDF 8889-GA030_C2 SOUTH SPAN (SPAN 3) EAST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 1 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA020_C3 RIVER SPAN (SPAN 2) EAST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 1 OF 4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA042_C1 NONSTANDARD REPAIR DETAILS LOWER FLANGE PLATE REPAIRS SOUTH SPAN Plan · 22 Oct 2026 View ↗ PDF 8889-GA025_C3 RIVER SPAN (SPAN 2) WEST ELEVATION (INTERNAL VIEW) BAY REAPIR SHEET 1 OF 4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA016_C0 NORTH SPAN (SPAN 1) COLLUMN REPAIR DETAIL 1 REPAIRS Plan · 22 Oct 2026 View ↗ PDF 8889-GA066_C0 TEMPORARY WORKS NORTH SPAN (SPAN 1) ADDITIONAL BRACING SHEET 1 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA038_C2 NONSTANDARD REPAIR DETAILS LOWER CHORD RSA REPAIRS STAGES 1-4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA006_C3 REPARATION SCHEME - TYPICAL BAY Plan · 22 Oct 2026 View ↗ PDF 8889-GA040_C0 NONSTANDARD REPAIR DETAILS STIFFENER SHOE REPAIRS Plan · 22 Oct 2026 View ↗ PDF 8889-GA010_C0 NORTH SPAN (SPAN 1) EAST ELEVATION (INTERNAL VIEW) SPECIAL BAYS SHEET 3 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA046_C0 NONSTANDARD REPAIR DETAILS BEARING END REPAIR SHEET 2 RIVER SPAN (SPAN 2) Plan · 22 Oct 2026 View ↗ PDF 8889-GA033_C2 SOUTH SPAN (SPAN 3) WEST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 2 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA019_C0 NORTH SPAN (SPAN 1) EAST AND WEST ELEVATION BEARING END REPAIR - EXPLODED VI Plan · 22 Oct 2026 View ↗ PDF 8889-GA065_C2 TEMPORARY WORKS NORTH SPAN (SPAN 1) NORTH APPROACH BEAM SUPPORT Plan · 22 Oct 2026 View ↗ PDF 8889-GA041_P0 NONSTANDARD REPAIR DETAILS UPPER WEB PLATE REPAIRS Plan · 22 Oct 2026 View ↗ PDF 8889-GA028_C3 RIVER SPAN (SPAN 2) WEST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 4 OF 4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA015_C0 NORTH SPAN (SPAN 1) COLUMN REPAIR LOCATION PLAN ELEVATIONS Plan · 22 Oct 2026 View ↗ PDF 8889-GA007_C1 REPARATION SCHEME NORTH SPAN REPAIR SEQUENCING ENABLING WORKS Plan · 22 Oct 2026 View ↗ PDF 8889-GA001_C0 KEY PLAN Plan · 22 Oct 2026 View ↗ PDF 8889-GA063_C2 TEMPORARY WORKS NORTH SPAN (SPAN 1) WEST STAIR SUPPORT Plan · 22 Oct 2026 View ↗ PDF 8889-GA039_C0 NONSTANDARD REPAIR DETAILS PRIMARY STIFFENER PLATE REPAIRS Plan · 22 Oct 2026 View ↗ PDF 8889-GA011_C0 NORTH SPAN WEST ELEVATION (INTERNAL VIEW) SPECIAL BAY SHEET 1 OF 3) Plan · 22 Oct 2026 View ↗ PDF 8889-GA018_C0 NORTH SPAN (SPAN 1) COLUMN REPAIR ALTERNATE REPAIRS Plan · 22 Oct 2026 View ↗ PDF 8889-GA070_P0 DRAIANGE LAYOUT Plan · 22 Oct 2026 View ↗ PDF 8889-GA060_C2 TEMORARY WORKS NORTH SPAN (SPAN 1) PROPPING REPAIR SEQUENCE Plan · 22 Oct 2026 View ↗ PDF 8889-GA032_C2 SOUTH SPAN (SPAN 3) EAST ELEVATION (INTERAL VIEW) BAY REPAIR SHEET 2 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA014_C3 NORTH SPAN (SPAN 1) EAST AND WEST ELEVATION SPECIAL BAY BEARING END REPAIR Plan · 22 Oct 2026 View ↗ PDF 8889-GA064_C2 TEMPORARY WORKS NORTH SPAN (SPAN 1) NORTH APPROACH RAMP SUPPORT Plan · 22 Oct 2026 View ↗ PDF 8889-GA045_C0 NONSTANDARD REPAIR DETAILS BEARING END REPAIRS SHEET 1 RIVER SPAN (SPAN 2) Plan · 22 Oct 2026 View ↗ PDF 8889-GA027_C3 RIVER SPAN (SPAN 2) WEST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 3 OF 4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA022_C2 RIVER SPAN (SPAN 2) EAST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 3 OF 4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA002_C1 REPARATION SCHEME - TYPICAL BAY - OPTION 1- EAST WEST ELEVATION LOWER WEB PL Plan · 22 Oct 2026 View ↗ PDF 8889-GA012_C0 NORTH SPAN WEST ELEVATION (INTERNAL VIEW) SPECIAL BAYS SHEET 2 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA062_C2 TEMPORARY WORKS NORTH SPAN (SPAN 1) WEST GIRDER SUPPORT Plan · 22 Oct 2026 View ↗ PDF 8889-GA008_C0 NORTH SPAN EAST ELEVATION (INTERNAL VIEW) SPECIAL BAYS SHEET 1 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA031_C2 SOUTH SPAN (SPAN 3) WEST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 1 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA017_C1 NORTH SPAN (SPAN 1) COLUMN REAPAIR DETAIL 2 REPAIRS Plan · 22 Oct 2026 View ↗ PDF 8889-GA048_C1 NONSTANDARD REPAIR DETAILS LOWER CHORD STRENGTHENING REPAIRS Plan · 22 Oct 2026 View ↗ PDF 8889-GA026_C3 RIVER SPAN (SPAN 2) WEST ELEVATION (INTERNAL VIEW) BAY REPAIRS SHEET 2 OF 4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA013_C0 NORTH SPAN WEST ELEVATION (INTERNAL VIEW) SPECIAL BAYS SHEET 3 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA067_C0 TEMPORARY WORKS NORTH SPAN (SPAN 1) ADDITIONAL BRACING SHEET 2 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA044_C0 NONSTANDARD REPAIR DETAILS UNDERPLATING ALL SPANS Plan · 22 Oct 2026 View ↗ PDF 8889-GA021_C2 RIVER SPAN (SPAN 2) EAST ELEVATION (INTERNAL VIEW) BAY REAPIRS SHEET 2 OF 4 Plan · 22 Oct 2026 View ↗ PDF 8889-GA0008.1.5-C0 SOUTH PART INSTALLATION SEQUENCE 2 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA100_C0 GENERAL NOTES Plan · 22 Oct 2026 View ↗ PDF 8889-GA078_C0 DECKING PLAN BRACING TYPICAL DETAILS Plan · 22 Oct 2026 View ↗ PDF 8889-GA0008.1.2-C2 SOUTH PART SECTIONS Plan · 22 Oct 2026 View ↗ PDF 8889-GA103_C0 EAST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN SHEET 1 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA098_P0 CENTRAL PIER (SPAN 2 AND 3) SECTION VIEWS SHEET 4 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA080.3.1-P1 MIDDLE PIER CLADDED Plan · 22 Oct 2026 View ↗ PDF 8889-GA43_C0 NONSTANDARD REPAIR DETAILS LOWER CHORD RSA REPAIRS SPAN 2 STAGES 4-15 Plan · 22 Oct 2026 View ↗ PDF 8889-GA101_C0 EAST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN Plan · 22 Oct 2026 View ↗ PDF 8889-GA096-C1 CENTRAL PIER (SPAN 2 AND 3) ELEVATION VIEW EAST 2 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA080.2.3-C1 CENTRAL PART ELEVATIONS AND DETAILS Plan · 22 Oct 2026 View ↗ PDF 8889-GA107_C0 EAST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN Plan · 22 Oct 2026 View ↗ PDF 8889-GA110_C2 SPANS 2 AND 3 SEQUENCE OF WORKS Plan · 22 Oct 2026 View ↗ PDF 8889-GA080.2.6-C0 CENTRAL PART INSTALLATION SEQUENCE 3 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA0008.1.1-C1 SOUTH PART PLAN VIEW Plan · 22 Oct 2026 View ↗ PDF 8889-GA106_C0 WEST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN SHEET 2 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA097_P0 CENTRAL PIER (SPAN 2 AND 3) ELEVATION VIEW WEST 3 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA080.2.2-C1 CENTRAL PART SECTIONS Plan · 22 Oct 2026 View ↗ PDF 8889-GA102_P1 NORTH SPAN WEST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN Plan · 22 Oct 2026 View ↗ PDF 8889-GA095_P0 CENTRAL PIER SPAN 2 AND 3 REPAIR DETAILS SHEET 1 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA0008.1.7-C0 MIDDLE PIER TOWERS Plan · 22 Oct 2026 View ↗ PDF 8889-GA108_C0 WEST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN Plan · 22 Oct 2026 View ↗ PDF 8889-GA097-C1 CENTRAL PIER SPAN 2 AND 3 ELEVATION VIEW WEST 3 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA080.2.5-C0 CENTRAL PART INSTALLATION SEQUENCE 2 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA0008.1.4-C0 SOUTH PART INSTALLATION SEQUENCE 1 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA105_C0 RIVER SPAN WEST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN 1 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA095-C1 CENTRAL PIER SPAN 2 AND 3 REPAIR DETAILS SHEET 1 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA080.2.1-C1 CENTRAL PART PLAN VIEW Plan · 22 Oct 2026 View ↗ PDF 8889-GA102_C0 NORTH SPAN WEST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN Plan · 22 Oct 2026 View ↗ PDF 8889-GA099_P0 CENTRAL PIER SPAN 2 AND 3 DETAIL VIEWS SHEET 5 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA091_C0 DECKING - SPAN 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA0008.1.6-C0 SOUTH PART INSTALLATION SEQUENCE 3 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA104_C0 EAST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN SHEET 2 OF 2 Plan · 22 Oct 2026 View ↗ PDF 8889-GA096_P0 CENTRAL PIER SPAN 2 AND 3 ELEAVATION VIEW EAST SHEET 2 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA0008.1.3-C1 SOUTH PART ELEVATION AND DETAILS Plan · 22 Oct 2026 View ↗ PDF 8889-GA101_P1 NORTH SPAN EAST ELEVATION (INTERNAL VIEW) REPAIR SCHEME KEY PLAN Plan · 22 Oct 2026 View ↗ PDF 8889-GA091_P0 DECKING - SPAN 3 Plan · 22 Oct 2026 View ↗ PDF 8889-GA080.2.4-C0 CENTRAL PART INSTALLATION SEQUENCE 1 OF 3 Plan · 22 Oct 2026 View ↗ PDF 8899-GA094-C0 CENTRAL PIER TEMPORARY BRACING Plan · 22 Oct 2026 View ↗ PDF 8889-GA099-C1 CENTRAL PIER SPAN 2 AND 3 DETAIL VIEWS 5 OF 5 Plan · 22 Oct 2026 View ↗ PDF 8889-GA140 P0 EXISTING VS PROPOSED TOP OF DECK LEVEL FOR PLANNING REQUIREMENTS ONLY Plan · 22 Oct 2026 View ↗ PDF SITE LOCATION PLAN Plan · 21 Oct 2026 View ↗ PDF 8889-GA140 REV PO EXISTING AND PROPOSED TOP OF DECK LEVELS Plan · 19 Oct 2026 View ↗

All documents on the council site ↗

Site constraints 12

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
City Docks conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Article 4 direction
Ashley Ward, Cabot Ward, Clifton East Ward, Cotham Ward and Lawrence Hill Ward (1999 ward boundary). Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Local nature reserve about 49 m away: Avon New Cut
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
Air quality management area: Bristol AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Public footpath about 25 m away
Matters where it crosses or adjoins the site: obstructing a path without a diversion order is an offence, and work cannot start until the order is confirmed.
Compiled from highway authority data, not the legal definitive map. A few authorities have not published, so no path shown is not proof there is none.
Radon affected area, class 5
An estimated 10 to 30% of homes reach the radon action level. Indicative for the 1 km square, which takes the highest class found in it; a radon test gives the answer for a building.
From the British Geological Survey and UK Health Security Agency indicative atlas. Under building regulations, as the BRE guide BR 211 (2023) sets out, new buildings and extensions need basic radon protection from class 3 in England and Wales and from class 2 in Scotland, and full protection from class 5. The class at the site itself, from the detailed BGS map, decides which.
UKHSA radon ↗
1 listed building within 150 m of the postcode pin
Nearest: Vauxhall Bridge, Grade II, about 54 m from the postcode pin
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Historic England ↗
National infrastructure project about 974 m away: Portishead Branch Line - MetroWest Phase 1
The site is about 974 m from the project boundary. Railway, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Coalfield, development low risk area; Tree preservation order about 17 m away: 26 Meredith Court Canada Way Bristol BS1 6XX; Inside the Bristol built-up area.
Not affected
Not green belt · No scheduled monument at the site

Checked on 3 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Bristol - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Bristol
Application type
Listed Building Application
Postcode
BS1 6TT
Received
30 Sept 2026
Validated
15 Oct 2026
Ward
Southville
Parish
Greater Bedminster Community Partnership
Target decision
10 Dec 2026
Applicant
Show

Decision outlook

Day 29 of the 56-day target. Bristol usually decides commercial and major works by day 60.

Day 2931 days to the predicted decision (day 60)
44%decided within 8 weeks
79%approved
89decided in the last year

Plota live figures for commercial and major works decided by Bristol in the last twelve months, from validation. Bristol decision record →

Public comments

No public comments yet.

Last counted 11 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14893481
Planning Portal ref
PP-14893481
Comments by
2 Dec 2026
Statutory expiry
10 Dec 2026
Bristol
Planning Authority Score
5.8/10
Average
#109 of 296 councils
Relevant to this application:
Other decisions

Bristol ranks #112 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Bristol decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #190 of 296
92%
Householder approved
Above avg (90%) #149 of 296
71%
Decided in 8 weeks
Above avg (63%) #112 of 296
37%
Extended time limit
Below avg (41%) #118 of 296
74%
Minor dwellings approved
374 decided (1-9 homes)
93%
Major dwellings approved
30 decided (10+ homes)
82%
Change of use approved
150 decided
2,098
Total decisions
293 refused in the year to March 2026