District heat network pipework at Multi Storey Car Park, Worthing
Summary of planning committee decision
Decided by Adur Worthing Planning Committee on 15 Oct 2025.
No officer report was published for this decision; this summary is from the committee minutes.
What was proposed
The application sought to extend buried pipework connecting the energy centre to the district heat network, running underground through the High Street, Steyne Gardens and the promenade.
“Proposal: Extension to buried pipework and associated equipment to connect to the district heat network. The pipework will run underground along High St, through Steyne Gardens and east and west along the promenade to connect the energy centre with Splashpoint and Pavilion Theatre.”
Minutes
What officers explained
Officers recommended approval subject to satisfactory information on biodiversity net gain, and explained the pipeline's route, its effect on trees, and the applicant's response to objections from phase one.
“The Principal Planning Officer presented the report and clarified for Members the proposed route of the pipeline and the effect it may have on trees and existing structures. The officer stated that the recommendation was to approve subject to satisfactory submission of information on biodiversity net gain.”
“Officers advised Councillors regarding their remit to impose conditions that would place embargos on works being carried out on specific dates and explained the applicants response to objections received regarding the first phase of works.”
Minutes
Concerns about phase one
Three speakers raised concern about the harm phase one of the works had caused to town centre businesses and urged that phase two avoid similar effects.
“There were three registered speakers who gave representations that expressed concern over the detrimental effects that phase one of Hemiko works had inflicted on the town centre and specifically on the businesses within it. They strongly appealed to the committee to ensure that phase two did not result in similar negative effects.”
Minutes
What members discussed
Members agreed on extra conditions to protect businesses and trees during phase two, including replacement tree sizes, access to the car park and seafront premises, and timing restrictions on works.
“During debate Members discussed that it was essential to impose conditions that would allow Hemiko to complete phase two but would also protect the businesses and allow them to operate successfully. Following lengthy discussion the committee agreed on some supplementary conditions and additions to some existing conditions. In brief these were -”
“amend condition 4 to specify girth size of 20cm of replacement tree T62 ● amend condition 9 to include that the archaeologist shall be agreed with the LPA ● additional condition 11 for a replacement tree if T63 is removed, girth size to be specified ● additional condition 12 requiring access to the High Street Car Park to be maintained at all times ● additional condition 13 preventing work occurring between 1 Dec 25 - 1 Jan 26, 28 Mar-12 Apr 26, 22 July-30 Aug, 24 Oct-5…”
Minutes
What was decided
The committee voted unanimously to delegate approval of the application, with the additional conditions to be agreed by the committee before the decision was issued.
“The committee then proposed to accept the Officers recommendation and agree that the application be delegated with a view to approval of the amendments/additional conditions above to be agreed with the Committee prior to the issuing of the decision…”
“Decision - Application be delegated with a view to approval with the above amendments/additional conditions to be agreed with the Committee prior to the issuing of the decision, and subject to conditions:-”
Minutes
Councillors at the meeting
- Helen AbrahamsChairLabour
- Samuel TheodoridiVice-ChairLabour
- Noel AtkinsConservative
- Rosey WhorlowLabour
- Lysanne SkinnerLabour
- Carl WalkerIndependent
- Kevin JenkinsSubstitute for Richard NowakConservative
Absent Richard Nowak Conservative, Ferdousi Henna Chowdhury Labour
Source: Plota analysis of the council's minutes; parties from the council's list of councillors.
Sources
- Adur Worthing Planning Committee minutes, 15 October 2025
- Agenda and papers (council website)
Source: Plota analysis of Adur's committee minutes. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Adur Worthing Planning Committee
- Council
- Adur
- Date
- Wednesday 15 October 2025
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Vote
- Unanimous
- Councillors
- 7Labour 4Conservative 2Independent 1Show councillors
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Adur committee decisions →
This committee's year
5 decisions in the 12 months to this meeting.
Source: Plota analysis of the committee's minutes.