River bus pier extension at Passenger Ferry Landing Stage, Tilbury
Summary of planning committee decision
Decided by Thurrock Planning Committee on 14 Oct 2025.
What was proposed
The application sought a floating pontoon, mooring piles and access connection extending the existing landing stage for river bus services.
“This full planning application, submitted by Thurrock Council, seeks approval for the provision of an extension to Tilbury Pier to facilitate a new River bus service. The extension is formed of a new floating pontoon, dolphin piles and a connecting link to the existing pier structure.”
“The Tilbury Town Fund bid seeks to revitalise Tilbury’s Riverside and strengthen its connection to the town centre. This will be achieved by increasing activity in the area and enhancing its existing heritage assets. A central feature of the redevelopment is the installation of a new pontoon, linked to the current Tilbury Landing Stage, designed to support expanded river passenger services. The upgraded pier will enable river bus access to central London.”
Officer report
The site
The landing stage is beside the London International Cruise Terminal and within the settings of several listed heritage assets and Tilbury Fort.
“The landing stage is located at Tilbury Riverside, adjacent to the London International Cruise Terminal. Tilbury Riverside Station is grade II* Listed and includes the baggage hall, the station, the floating landing stage and linking walkways. The Site is also within the setting of the grade II World’s End Inn (List UID: 1111632) and the Scheduled Monument Tilbury Fort (List UID: 1021092).”
“The north of the site is within a Primary Industrial and Commercial land designation within the Core Strategy.”
Officer report
Earlier applications
Earlier proposals included advice on a pier extension and approved works involving the landing stage, lighting, passenger shelter and a replacement dolphin.
“Reference Proposal Decision 24/00754/TBC Planning application for the provision of an extension to Tilbury Pier to facilitate a new River bus service. The extension is formed of a new floating pontoon, dolphin piles and a connecting link to the existing pier structure. Pending Committee Decision 24/00540/FUL and 24/00541/LBC Works to building comprising: 1.”
“(TRAAC) building. New vehicle crossover. Use of building for mixed use comprising event and market space, lettable units for creative uses, cafe purposes and dance studio and education space. 23/30023/PMIN Proposed extension to the existing Tilbury Terminal pier to facilitate new connections to a river bus service Advice Given 17/00995/LBC Replace existing timber dolphin with a replacement steel dolphin of a design that matches the existing corresponding dolphin.”
Officer report
Officers’ recommendation
Officers recommended consent because the proposal supported river transport, employment and connectivity, while remaining heritage harm could be controlled by conditions.
“In principle, the proposed development is considered acceptable. The site is already in active use for river transport purposes, and the nature of the proposal is consistent with this established use. There are no identified land use objections, and the extension would support further employment opportunities adjacent to an existing employment area…”
“Moreover, the development aligns with wider strategic transport objectives. The use of the River Thames for passenger transport is supported in Thurrock’s transport planning framework. An update to the Borough’s Transport Strategy, discussed by the Planning, Transport and Regeneration Overview and Scrutiny Committee in February 2023, includes a stated ambition to "strengthen the river as a transport artery." The strategy promotes the development of riverside stations…”
Officer report
Heritage impact
The extension would cause low-level less than substantial harm to the listed landing stage, outweighed by public benefits including sustainable use and improved connectivity.
“The council’s heritage advisor considers the scheme will result in a low level of less than substantial harm to the significance of the listed Riverside Station. This harm arises from alterations to the historic form and appearance of the landing stage, which has remained largely unchanged since the early-to-mid 20th century.”
“In conclusion, the proposal is considered to result in less than substantial harm to the significance of the Grade II* listed Riverside Station, and this harm must be weighed against the public and heritage benefits of the scheme, in accordance with the NPPF and the Planning (Listed Buildings and Conservation Areas) Act 1990. Subject to conditions securing…”
Officer report
Consultation responses
Historic England and Place Services raised no objections, while recommending controls over materials, lighting, signage, balustrades and heritage details; no public comments were received.
“No objection, subject to detailed design considerations. Historic England acknowledges that the proposed pontoon extension will result in a degree of harm to the significance of the Grade II* listed Tilbury Riverside Station landing stage, due to changes to its historic form. However, the harm is considered limited and mitigated by the proposal’s subservient design and reversible construction method.”
“Previously raised concerns about bollards and balustrades have been addressed, though the illuminated signage and balustrade design still require careful control via conditions. The lack of repair or restoration works to the existing structure is considered a missed opportunity to enhance heritage value. Conditions are recommended to secure high- quality materials, lighting, signage details, and balustrade design…”
Officer report
Members’ discussion
Members had no further questions or debate before moving to a vote.
“There were no further questions or debate from members.”
“Recommendation That the Chief Planning Officer be authorised to GRANT LISTED BUILDING CONSENT for the development, subject to conditions.”
Minutes
Conditions
Conditions required the development to start within three years, follow approved plans, and secure external materials, fixtures, lighting and signage details.
“Samples of the materials to be used on the external finishes of the development including for the decking, waiting shelters, handrails and balustrade, shall be submitted to and approved in writing by the local planning authority prior to their first use on site. The development shall be implemented in accordance with the approved details and permanently maintained as such.”
“Prior to the installation of any exterior fixtures and fittings including lighting and signage, details of their location, design and materials shall be submitted to and approved in writing by the local planning authority. Development shall be implemented in accordance with the approved details and shall be permanently maintained as such.”
Officer report
Sources
- Thurrock Planning Committee minutes, 14 October 2025
- Agenda and papers (council website)
Source: Plota analysis of Thurrock's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Thurrock Planning Committee
- Council
- Thurrock
- Date
- Tuesday 14 October 2025
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Vote
- 6 for, 0 against, 1 abstained
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Thurrock committee decisions →
Source: Plota analysis of the minutes.