Landscaping and open space at Parcel Nos, 0006 2700 2972 9680 Evesham Road, Bishop's Cleeve

Summary of planning committee decision

Decided by Tewkesbury Planning on 16 Dec 2025.

24/00574/FULApproved

The site and its setting

The 6.2-hectare site comprises agricultural fields east of the A435, beside Dean Brook, and lies in Flood Zones 2 and 3.

“This application relates to the southern extent of two field parcels currently in agricultural use located to the east of the A435. The site to which the current application relates, measures 6.2ha in area and is bound by Dean Brook to the south with hedgerows delineating the northern and western boundaries.”

“The site lies entirely within Flood Zone 2 with the southern boundary of the site falling within Flood Zone 3.”

Officer report

Consultation responses

The parish council objected, while specialist consultees raised no objections or supported the scheme subject to conditions.

“Bishops Cleeve Parish Council –objection.”

“Tree Officer – no objection subject to conditions.”

Officer report

Objections received

Three neighbours objected on grounds including appearance, highways, ecology, privacy, pollution, flooding, trees and landscaping.

“The application has been publicised through the posting of a site notice and direct neighbour letters for a period of 21 days.”

“Design and visual appearance • Highway safety, traffic and parking • Nature conservation and ecology • Overlooking and loss of privacy • Pollution and disturbance • Flooding • Trees, landscaping…”

Officer report

Who spoke

No public speakers addressed this application; the county highways representative answered members’ questions about paths, cycling and traffic calming.

What members discussed

Members discussed flooding, year-round accessibility, alternative surfacing, safe connections, cycle facilities and the proposed speed limit.

“PL.16.12.25 be flooded. The Member asked what sustainable methods could be used to ensure the area could continue to be used whilst it was wet, noting that boardwalks were being considered for certain areas within the Garden Town, and the County Highways representative clarified that the streets built on the new estate to the south had not yet been adopted by County Highways so the connections shown between this site and that one would not necessarily need to be dedicated as…”

“Another Member noted that the A435 might have a designated cycle lane and asked what the speed limit would be on the road to accommodate that. In response, the County Highways representative explained that the primary school application intended to introduce a segregated cycle track but, as this application was not dependent upon that, the applicant had made clear they would not be bound by a condition to provide that facility.”

Minutes

The committee vote

A motion to permit the application in line with the officer recommendation was proposed, seconded and approved.

“The Chair indicated that the Officer recommendation was to permit the application, subject to conditions set out in the Committee report and the amendment to Condition 8, and sought a motion from the floor. It was proposed and seconded that the application be permitted in accordance with the Officer recommendation.”

Minutes

The decision

The application was permitted subject to the report’s conditions and an amendment requiring further details for the bridge crossings.

“Whilst the Environment Agency had raised no objections in principle, further details of the bridge crossings had been sought to ensure appropriate clearance of the watercourse and this was proposed to be secured via Condition 8.”

Minutes

Conditions and bridge details

The permission included conditions on tree protection, ecological management, biodiversity gain, lighting and detailed footbridge connections.

“Prior to the commencement of development, a Construction and Environmental Management Plan (CEMP: Biodiversity) shall be submitted to the Local Planning Authority. The CEMP will follow the recommendations to protect wildlife during the construction phase made within the Ecological Appraisal (FPCR, April 2024) and Ecology Surveys: Technical Note (FPCR, Jan 2025).”

“Demonstrate how a minimum 10% Biodiversity Net Gain (BNG) will be achieved and maintained for a period of at least 30 years post-development. • Provide detailed designs and specifications for all habitat creation, restoration, and enhancement measures. • Outline long-term management strategies for all retained and created habitats. • Include a monitoring schedule detailing methods, frequency, and duration of ecological surveys to assess the success of BNG measures.”

Officer report

Councillors at the meeting

Apologies Thomas Budge Lib Dem, Matt Dimond-Brown Green, Mary Jordan Lib Dem, Jim Mason Conservative

Also attending Mike Sztymiak Independent

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Tewkesbury Planning minutes, 16 December 2025
  • Agenda and papers (council website)

Source: Plota analysis of Tewkesbury's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Tewkesbury
Date
Tuesday 16 December 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
9Lib Dem 5Conservative 2Independent 2Show councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

12 decisions in the 12 months to this meeting, 1 against officer advice.

Source: Plota analysis of the committee's minutes.